Indonesia : West Kalimantan Power Grid Strengthening Project

Sovereign Project | 41074-013

The proposed project is perfectly aligned with ADB's Energy Sector Assessment Strategy and Roadmap, which supports investment in strategic transmission assets that connects regions or countries across seas or international boundaries to optimize power networks by reducing the overall need for reserve capacity, improving system reliability, removing transmission bottlenecks, and transmitting cheaper power from one area to the other, addressing overall regional socio-economic and environmental improvement.

Project Details

  • Project Officer
    Palupi, Ira
    Southeast Asia Department
    Request for information
  • Country/Economy
    Indonesia
  • Modality
  • Sector
    • Energy
Project Name
West Kalimantan Power Grid Strengthening Project
Project Number
41074-013
Country / Economy
  • Indonesia
Project Status
Closed
Project Type / Modality of Assistance
  • Grant
  • Loan
Source of Funding / Amount
Grant 0354-INO: West Kalimantan Power Grid Strengthening Project
Source Amount
Clean Energy Fund under the Clean Energy Financing Partnership Facility US$ 2.00 million
Loan 3015-INO: West Kalimantan Power Grid Strengthening Project
Source Amount
Ordinary capital resources US$ 49.50 million
Loan 8272-INO: West Kalimantan Power Grid Strengthening Project
Source Amount
Agence Francaise de Developpement US$ 49.50 million
Strategic Agendas
  • Environmentally sustainable growth
  • Inclusive economic growth
  • Regional integration
Drivers of Change
  • Governance and capacity development
  • Partnerships
Sector / Subsector
  • Energy / Electricity transmission and distribution

Gender
No gender elements
Description

The proposed project is perfectly aligned with ADB's Energy Sector Assessment Strategy and Roadmap, which supports investment in strategic transmission assets that connects regions or countries across seas or international boundaries to optimize power networks by reducing the overall need for reserve capacity, improving system reliability, removing transmission bottlenecks, and transmitting cheaper power from one area to the other, addressing overall regional socio-economic and environmental improvement.

Project Rationale and Linkage to Country/Regional Strategy

In West Kalimantan, Sumatera and the other outer islands of Indonesia, most of the power generation is either oil or diesel based, and, as a result, cost of power generation is more than 25 cents/kWh. Large numbers of customers also do not have access to grid connected power supply in those areas, and the power grid will need strengthening to accommodate new customer connection. In addition to strengthened network, supply to new customers will need new generation capacity, especially low cost power generation to reduce the overall cost of power generation. The proposed project will address all these issues in West Kalimantan.

PLN, the state owned power utility in Indonesia, plans to reduce its cost of power generation in West Kalimantan by importing hydropower generated electricity from neighboring Sarawak, Malaysia by building about 83 km 275 kV transmission line from its Bengkayang substation to the border with Sarawak, Malaysia. On the other side of the border, in Sarawak, PLN's counterpart, SESCO, the state owned power utility in Sarawak will build about 42 km 275 kV transmission line from Mambong substation to the border with West Kalimantan. Together, these transmission lines in the two countries will form the first regional BIMP-EAGA flagship project and the first leg of the Trans Borneo Power Grid that aims to connect West Kalimantan across Sarawak, and Brunei, to Sabah (Malaysia) enabling power trading between the BIMP-EAGA countries.

PLN's investment in West Kalimantan is part of its nationwide plan to connect about 10 million new customers between 2011 and 2015 to support Government's commitment to 90% electrification by 2020 from about 62% in 2009. This national plan will need large investments and PLN will have to increase its operational income for it. Currently, PLN's income from its operation is insufficient to cover its cost of operation as the tariffs have been set low by the Government (average of 6.9 cents/kWh) for social reasons. As the cost of generation is much higher than the average tariff, PLN's operations are subsidized by the Government through a public service obligation (PSO) program that is approved by the Parliament each year. For 2011 PLN subsidy, the Government has allocated about $7.3 billion from the 2010 level of $6.46 billion ($82 million for West Kalimantan). PLN's cost reduction will reduce the need for larger subsidy by PLN.

The proposed strengthening of the 150 kV distribution network, and PLN's import of cheaper power will also avoid emissions of about 400,000 tons of CO2 that would have been generated by the old rental oil fired that PLN currently uses in West Kalimantan.

This is a priority project for strengthening distribution network in rural areas and for regional cooperation. It is consistent with ADB's country strategy and program for 2006-2009 and country operations business plan 2009-2011 that support the Government's economic growth target rate of 6.3%-6.8% per annum in 2010-2014 to reach at least 7% by 2014. They highlight the importance of removing infrastructure bottlenecks and promoting regional cooperation.

Impact

Sustainable power supply in West Kalimantan

Project Outcome

Description of Outcome

Cost of operating West Kalimantan power system reduced

Progress Toward Outcome
Packages 6 and 7 were awarded in August 2017. Package 5 contract was awarded in December 2017. Second loan extension from 30 June 2018 to 30 November 2019 is approved to complete construction of Packages 5, 6, and 7. Loan reallocation was approved on 10 Sept 2019. Land acquisition is completed. As of April 2022, construction progress of P5, P6, and P7 is 98.42%, 100%, and 91.95% respectively and expected to be completed by September 2022. PLN will ensure completion of the remaining contract activities beyond loan closing date on 30 Nov 2019 up to project completion and is financing the remaining contract amount.

Implementation Progress

Description of Project Outputs

Construction of Sarawak-West Kalimantan interconnection network

Construction of new transmission network in West Kalimantan (Bengkayang-Ngabang-Tayan)

New connections to households in West Kalimantan

Construction of new transmission network in West Kalimantan (Tayan-Sanggau-Sekadau)

Status of Implementation Progress (Outputs, Activities, and Issues)
Construction of P5 (substations) as of April 2022 = 98.42%. Tayan SS 9.89%, Sanggau SS 48.28%, Sekadau SS 40.24%. Physical completion for Tayan SS was completed, CC was issued on 20 April 2021. Target for Sanggau and Sekadau SS:- physical completion by 15 August 2022 - point to point test by 15 July 2022 (Sanggau and Sekadau SS through P7). Construction of P6 (Tayan-Sanggau TL) as of April 2022= 100%. Commissioning was completed in October 2020. CC was issued on 27 October 2020. Construction of P7 (Sanggau-Sekadau TL) as of April 2022 = 91.95%. Target for commissioning by July 2022. Physical completion target by September 2022.Bengkayang substation is fully constructed and energized. 150/20kV Bengkayang SS financed by PLN completed in May 2016.81.375 km of 275kV TL double circuit transmission line from Sarawak border to Bengkayang is now fully constructed. First and second circuits were energized on 20 January 2016 and 19 May 2016 respectively.150/20 kV substation in Ngabang and four-line feeder extension in 150 kV Tayan substation and Bengkayang substation fully energized in November 2017. 144.65 km of 150 kV double-circuit transmission line between BengkayangNgabangTayan fully energized in June 2018. As of April 2022, 1,896 households connected to ADB 52.973 km medium voltage (MV) and 46.760 km low voltage (LV) lines which contributed to total 27,815 households connected to ADB financed high-voltage (HV) lines in the targeted regencies under the grant against target of 8,000 new households connected to electricity network.
Geographical Location
Bengkayang, Kabupaten Bengkayang, Kabupaten Landak, Kabupaten Sanggau, Kabupaten Sekadau, Ngabang, Tayan, West Kalimantan

Safeguard Categories

Environment
B
Involuntary Resettlement
B
Indigenous Peoples
B

Summary of Environmental and Social Aspects

Environmental Aspects
This is classified as a Category B project for environment. The projects poses no significant environmental risks. The draft IEE prepared shows the proposed 275 kV transmission line: (i) passing through flat to hilly country, with scattered villages and associated small farms and gardens mainly along the roads including shifting cultivation and re-growth; (ii) does not pass through any protected areas, areas with rare or endangered species, or areas of high ecological diversity; (iii) requires 9.04ha land in West Kalimantan area for tower sites; and (iv) requires tall trees to be cleared on land of 30m width, from the centre line, in West Kalimantan In the project area, the vegetation is already highly modified by human activity through shifting and permanent cultivation. The area involves no protected areas, no primary forest, no cultural heritage sites, 30% of land occupied by crops and grassland, 68% is high canopy vegetation such as plantations and forest, and only 2% other land use. Update Initial Environmental Examination (IEE) has been approved for the 150 kV section from Tayan-Sanggau and Sanggau-Sekadau.
Involuntary Resettlement
- Resettlement and Customary Communities Plan (RCCP) for 275 kV section of Jagoibabang-Bengkayang and 150 kV section of Bengkayang-Ngabang-Tayan were approved by ADB in September 2016. The summary of RCCP in the form of leaflets has been posted on all affected village office boards. - Additional RCCP has been approved for the 150 kV section from Tayan-Sanggau and Sanggau-Sekadau. The updated RCCP has been approved by ADB on 29 January 2019 and disclosed on ADB's website and to the APs and stakeholders in the form of leaflet in May 2019.
Indigenous Peoples
The ethnic minority plans are incorporated in the RCCPs.

Stakeholder Communication, Participation, and Consultation

During Project Design
Stakeholders meetings were conducted in West Kalimantan; near the border area in Bengkayang and in other areas along the proposed route of the transmission line.
During Project Implementation
PLN and ADB confirmed that social internal monitoring are conducted semi-annually, and external monitoring has been conducted twice (three months after compensation payment for 50% of towers, and once 30% of ROW compensation has been provided, for 275 kV TL and 150 kV TL each), according to the updated RCCP for 275 kV and draft RCCP for 150 kV. All the monitoring reports have been submitted to ADB for web posting. During construction, PLN is required to submit the progress of EMP implementation and monitoring twice a year which to be uploaded on ADB website.

Business Opportunities

Consulting Services
The PIC is already contracted and mobilized: a Joint Venture of Tractebel Engineering GDF Suez (TE) (Thailand) and Powergrid International Limited (Thailand) in subconsultancy with PT Caturbina Guna Persada (Indonesia).
Procurement

Four ICB packages have been bidded out in August 2012 and were awarded in 2013:

Package 1: Design, Supply, Installation, Testing and Commissioning of 275kV Overhead Transmission Lines Bengkayang Substation - Jagoibabang

Package 2: Design, Supply, Installation, Testing and Commissioning of 275/150kV Bengkayang Substation

Package 3: Design, Supply, Installation, Testing and Commissioning of 150kV Transmission Lines Bengkayang - Ngabang - Tayan

Package 4: Design, Supply, Installation, Testing and Commissioning of 150/20kV Substation at Ngabang and Tayan;

Grant component: Connection to Households in West Kalimantan through Extension of MV and LV Network

Contact

Responsible ADB Officer
Palupi, Ira
Responsible ADB Department
Southeast Asia Department
Responsible ADB Division
Indonesia Resident Mission (IRM)
Executing Agencies
P.T. Perusahaan Listrik Negara

Timetable

Concept Clearance
28 Aug 2010
Fact Finding
14 Feb 2011 to 17 Feb 2011
MRM
09 Aug 2011
Approval
27 Aug 2013
Last Review Mission
-
Last PDS Update
13 Apr 2022

Funding

Grant 0354-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Aug 2013 20 Oct 2013 04 Apr 2014 31 Jul 2016 31 Jul 2017 18 Dec 2017
Financing Plan
  Total (Amount in US$ million)
Project Cost 2.00
ADB 0.00
Counterpart 0.00
Cofinancing 2.00
Grant Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 10 Jul 2024 0.00 1.66 83%
Cumulative Disbursements 10 Jul 2024 0.00 1.66 83%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory - Satisfactory - Satisfactory

Loan 3015-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Aug 2013 17 Oct 2013 04 Apr 2014 31 Jul 2016 30 Nov 2019 10 Sep 2020
Financing Plan
  Total (Amount in US$ million)
Project Cost 78.50
ADB 49.50
Counterpart 29.00
Cofinancing 0.00
Loan Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 10 Jul 2024 48.76 0.00 100%
Cumulative Disbursements 10 Jul 2024 48.76 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory - Satisfactory - Satisfactory

Loan 8272-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
16 Nov 2011 08 Feb 2013 08 Feb 2013 31 Jul 2016 30 Jun 2018 09 Aug 2018
Financing Plan
  Total (Amount in US$ million)
Project Cost 49.50
ADB 0.00
Counterpart 0.00
Cofinancing 49.50
Loan Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 10 Jul 2024 0.00 38.76 100%
Cumulative Disbursements 10 Jul 2024 0.00 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2023) Audited Project Financial Statements Jul 2024
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2022) Audited Project Financial Statements Aug 2023
West Kalimantan Power Grid Strengthening Project: Completion Report Project/Program Completion Reports Jul 2023
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2021) Audited Project Financial Statements Jun 2022
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Aug 2021
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Mar 2021
Amendment to the Loan Agreement for Loan 3015-INO: West Kalimantan Power Grid Strengthening Project Loan Agreement (Ordinary Resources) Jan 2021
West Kalimantan Power Grid Strengthening Project: Updated Project Administration Manual Project/Program Administration Manual Oct 2019
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2018) Audited Project Financial Statements Sep 2019
West Kalimantan Power Grid Strengthening Project: Updated Project Administration Manual Project/Program Administration Manual Jun 2019
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2017) Audited Project Financial Statements Jun 2018
West Kalimantan Power Grid Strengthening Project: Procurement Plan Procurement Plans Mar 2018
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2016) Audited Project Financial Statements Jun 2017
Amendment to the Loan Agreement for Loan 3015-INO: West Kalimantan Power Grid Strengthening Project Loan Agreement (Ordinary Resources) Aug 2016
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2015) Audited Project Financial Statements Jun 2016
West Kalimantan Power Grid Strengthening Project: Audited Project Financial Statements (January-December 2014) Audited Project Financial Statements Jun 2015
Grant Agreement for Strengthening West Kalimantan Power Grid Project Grant Agreement Oct 2013
Project Agreement for Strengthening West Kalimantan Power Grid Project Project/Program Agreements Oct 2013
Loan Agreement for Strengthening West Kalimantan Power Grid Project Loan Agreement (Ordinary Resources) Oct 2013
West Kalimantan Power Grid Strengthening Project: Report and Recommendation of the President Reports and Recommendations of the President Aug 2013
West Kalimantan Power Grid Strengthening Project Project/Program Administration Manual Jul 2013
Trans Borneo Power Grid, Sarawak to West Kalimantan Link – Indonesian Section: Initial Poverty and Social Analysis Initial Poverty and Social Analysis Aug 2010

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2021) Social Monitoring Reports Jan 2022
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports Jan 2022
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2021) Environmental Monitoring Reports Jul 2021
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2021) Social Monitoring Reports Jul 2021
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2020) Social Monitoring Reports Jan 2021
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Dec 2020
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2020) Environmental Monitoring Reports Jul 2020
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2020) Social Monitoring Reports Jul 2020
West Kalimantan Power Grid Strengthening Project: Independent Monitoring Agency Report Social Monitoring Reports Mar 2020
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2019) Social Monitoring Reports Dec 2019
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2019) Environmental Monitoring Reports Dec 2019
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2019) Social Monitoring Reports Jul 2019
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2019) Environmental Monitoring Reports Jun 2019
West Kalimantan Power Grid Strengthening Project: 150 kV Tayan – Sanggau – Sekadau Transmission Lines and 150/20 kV Sanggau and Sekadau Substations Social Monitoring Report Social Monitoring Reports Apr 2019
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2018) Social Monitoring Reports Dec 2018
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2018) Environmental Monitoring Reports Dec 2018
West Kalimantan Power Grid Strengthening Project: Tayan-Sanggau-Sekadau Updated Resettlement and Customary Communities Plan Combined Resettlement Plan and Indigenous Peoples Plans Sep 2018
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jun 2018
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2018) Social Monitoring Reports Jun 2018
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2017) Social Monitoring Reports Jan 2018
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2017) Environmental Monitoring Reports Dec 2017
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2017) Social Monitoring Reports Jul 2017
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2017) Environmental Monitoring Reports Jun 2017
West Kalimantan Power Grid Strengthening Project: 150 kV Bengkayang-Ngabang-Tayan Transmission Line Independent Monitoring Agency Report Social Monitoring Reports Apr 2017
West Kalimantan Power Grid Strengthening Project: 275 kV Bengkayang-Jagoibabang Transmission Line Independent Monitoring Agency Report Social Monitoring Reports Apr 2017
West Kalimantan Power Grid Strengthening Project: Semiannual Environmental Monitoring Report (July-December 2016) Environmental Monitoring Reports Dec 2016
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2016) Social Monitoring Reports Dec 2016
West Kalimantan Power Grid Strengthening Project: Tayan-Sanggau-Sekadau Resettlement and Customary Communities Plan Combined Resettlement Plan and Indigenous Peoples Plans Aug 2016
West Kalimantan Power Grid Strengthening Project: 150 kV Tayan-Sanggau-Sekadau Transmission Line Initial Environmental Examination Initial Environmental Examination Jul 2016
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2016) Social Monitoring Reports Jul 2016
West Kalimantan Power Grid Strengthening Project: Semiannual Environmental Monitoring Report (January-June 2016) Environmental Monitoring Reports Jun 2016
West Kalimantan Power Grid Strengthening Project: Quarterly Social Monitoring Report (January-March 2016) Social Monitoring Reports Mar 2016
West Kalimantan Power Grid Strengthening Project: Quarterly Environmental Monitoring Report (January-March 2016) Environmental Monitoring Reports Mar 2016
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2015) Social Monitoring Reports Dec 2015
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2015) Environmental Monitoring Reports Dec 2015
West Kalimantan Power Grid Strengthening Project: Resettlement and Customary Communities Plan Implementation (July-September 2015) Social Monitoring Reports Oct 2015
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2015) Environmental Monitoring Reports Jun 2015
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (January-June 2015) Social Monitoring Reports Jun 2015
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Dec 2014
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July-December 2014) Social Monitoring Reports Dec 2014
West Kalimantan Power Grid Strengthening Project: Social Monitoring Report (July 2014) Social Monitoring Reports Jul 2014
West Kalimantan Power Grid Strengthening Project: Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Jul 2014
West Kalimantan Power Grid Strengthening Project: Updated Resettlement and Customary Communities Plan Combined Resettlement Plan and Indigenous Peoples Plans Mar 2014
West Kalimantan 275 KV Transmission Line Project: Updated Resettlement Customary Communities Development Plan Combined Resettlement Plan and Indigenous Peoples Plans Aug 2013
Strengthening West Kalimantan Power Grid: Initial Environmental Examination Initial Environmental Examination Aug 2011
Strengthening West Kalimantan Power Grid: West Kalimantan 275 KV Transmission Line project (Draft) Combined Resettlement Plan and Indigenous Peoples Plans Jul 2011
Strengthening West Kalimantan Power Grid: West Kalimantan 150 KV Transmission Line project (Draft) Combined Resettlement Plan and Indigenous Peoples Plans Jul 2011

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
INO: Strengthening West Kalimantan Power Grid Project (INO) Advance Notice Archived

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
DESIGN,SUPPLY,INSTALLATION,TESTING,AND COMMISSIONI NG OF 150 KV SUBSTATIONS AT TAYAN,SANGGAU,SEKADAU Loan 3015 15 Jan 2018 SIEMENS CONSORTIUM | JL.JEND.A. YANI KAV B67-68 PULOMAS JAKARTA TIMUR INDONESIA P.T. Perusahaan Listrik Negara 10,626,931.00 4,538,275.00
DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 150KV TRANSMISSION LINES TAYAN-SANGGAU Loan 3015 28 Jul 2017 PT KRAKATAU ENGINEERING-PT CITRAMAS HEAVY IND | JL JEND GATOT SUBROTO KAV54 JAKARTA 12950 - INDONESIA INDONESIA P.T. Perusahaan Listrik Negara 12,050,346.00 6,022,912.00
DESIGN, SUPPLY, INSTALLATION, TESTING,AND COMMISSIONING OF 150KV TRANSMISSION LINES SANGGAU-SEKADAU Loan 3015 28 Jul 2017 PT KRAKATAU ENGINEERING-PT CITRAMAS HEAVY IND | JL JEND GATOT SUBROTO KAV54 JAKARTA 12950 - INDONESIA INDONESIA P.T. Perusahaan Listrik Negara 8,170,885.00 4,083,909.00

Procurement Plan

Title Document Type Document Date
West Kalimantan Power Grid Strengthening Project: Procurement Plan Procurement Plans Mar 2018