Mongolia : Western Regional Road Corridor Investment Program

Sovereign Project | 41193-014

Project Name Western Regional Road Corridor Investment Program
Project Number 41193-014
Country / Economy Mongolia
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
MFF Facility Concept 0065-MON: Western Regional Road Corridor Development Program
Asian Development Fund US$ 45.00 million
Ordinary capital resources US$ 125.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Sector / Subsector

Transport /

Gender Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Inclusive economic growth is promoted by enhanced local and regional connectivity

Project Outcome
Description of Outcome

Transport accessibility within the project area and between countries improved

Progress Toward Outcome Tranche 1 financially completed. For Tranche 2, Output 1 construction is 100% completed for CW1-1, CW1-2, and CW1-3. CW1-4 was able to commence in 2021 and achieve 85.3% progress. For Output 2, Ulgii bypass lot CW-1 is 95% complete, lot CW-2 is 60% complete, and lot CW-3 is 78% complete. For Output 3, two road maintenance equipment units have been established, equipped, and operationalized. Output 4 activities are ongoing. MFF extension of availability period from 8 December 2021 to 31 December 2023 approved.
Implementation Progress
Description of Project Outputs

1. Western regional road constructed

2. Local roads constructed

3. Road maintenance component

4. Capacity development program

Status of Implementation Progress (Outputs, Activities, and Issues) Output 1 completed. Output 2 is almost complete, while Output 3 two road maintenance units established, equipped, and operationalized. Output 4 activities ongoing. FY2021 audit report approved and disclosed in ADB website.
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects Category A
Involuntary Resettlement Category C
Indigenous Peoples Category C
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services

All consultants will be recruited according to ADB's Guidelines on the Use of Consultants.

The project will finance 87 PM of international and 342 PM of national consulting services to provide for the construction supervision services. This is required to extend the current services beyond the end of ongoing contract, which ends on 31 December 2013, for the same section of road which is made necessary due to substantial delays incurred in implementation under the Phase 1 project. Since this is an extension of the current contract as part of Phase 1, the services will be single sourced to Korea Consultants International which has performed satisfactorily. An additional 62 PM of international and 294 PM of national consulting services will be required to (i) facilitate project management and implementation, and (ii) strengthen the institutional and operational capacity of the executing agency. The following expertise will be required: (i) an international project management specialist to provide project and contract management support to EA/IA; and (ii) safeguards specialists to provide for monitoring services (national individual consultants) and safeguard related studies to be sourced through individual (international) and local institutes. Due to the specialized nature of the services and small amount of the contracts assigned to the local institutes, services will be contracted through the single source selection (SSS) method. In addition to the services above, 5 PM of international and 12 PM of national will be financed through Phase 1 project to provide services in the areas of (i) value engineering, and (ii) procurement support.

Procurement

All procurement of goods and works will be undertaken in accordance with ADB's Procurement Guidelines (2010, as amended from time to time).

For the procurement of works, the road will be divided into three (3) lots. Procurement will be through international competitive bidding (ICB) procedures using the single stage two envelope (SSTE) modality. Procurement shall use the latest ADB standard bidding documents which can be downloaded from ADB's website. Documents for all procurement under ICB will be subject to the prior review of ADB.

The procurement of equipment for maintenance will be through National Competitive Bidding (NCB) whereby (i) the advertisement may be limited to the national press, an official gazette or an open access website; (ii) bidding documents may be only in the Mongolian language, and Mongolian currency may be used for the purpose of bidding and payment. Procurement under NCB will be subject to the provisions of the NCB annex (see procurement plan in Appendix 1). Additionally, before the start of any procurement ADB and the Government will review the public procurement laws of the central and state governments to ensure consistency with ADB's Procurement Guidelines.

Responsible ADB Officer Stapleton, Rebecca
Responsible ADB Department East Asia Department
Responsible ADB Division EASI, East Asia Department
Timetable
Concept Clearance 07 Dec 2010
Fact Finding 22 Aug 2011 to 29 Aug 2011
MRM 19 Oct 2011
Approval 09 Dec 2011
Last Review Mission -
Last PDS Update 19 Sep 2022

MFF Facility Concept 0065-MON

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 170.00 Cumulative Contract Awards
ADB 170.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Western Regional Road Corridor Investment Program: Proposed Extension of Facility Availability Period Change in Scope, Amount, and Implementation Arrangements Jul 2021
Western Regional Road Corridor Investment Program: Revised Facility Administration Manual Facility Administration Manual Jun 2021
Framework Financing Agreement for Western Regional Road Corridor Investment Program between Mongolia and Asian Development Bank dated 1 December 2011 Framework Financing Agreement Dec 2011
Western Regional Road Corridor Investment Program Reports and Recommendations of the President Nov 2011
Western Regional Road Corridor Investment Program Facility Administration Manual Nov 2011
Western Regional Road Corridor Development Program Summary Poverty Reduction and Social Strategies Sep 2011

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Western Regional Road Corridor Investment Program Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks Oct 2011
Western Regional Road Corridor Investment Program: Indigenous Peoples Planning Framework (as of Board approval) Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks Oct 2011
Western Regional Road Corridor Investment Program Environmental Assessment and Review Framework Oct 2011
Western Regional Road Corridor Investment Program: Environmental Assessment and Review Framework (as of Board approval) Environmental Assessment and Review Framework Sep 2011
Баруун бүсийн босоо тэнхлэгийн автозамын хөрөнгө оруулалтын хөтөлбөр Resettlement Frameworks Sep 2011
Баруун бүсийн босоо тэнхлэгийн автозамын хөрөнгө оруулалтын хөтөлбөр Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks Sep 2011
Western Regional Road Corridor Investment Program - Tranche 1 Environmental Impact Assessments Sep 2011
Western Regional Road Corridor Investment Program: Resettlement Framework Resettlement Frameworks Sep 2011
Western Regional Road Corridor Investment Program - Tranche 1: Environmental Impact Assessment (as of Board approval) Environmental Impact Assessments Sep 2011
Western Regional Roads Development Project Phase II Environmental Impact Assessments Aug 2010

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.