Viet Nam: Power Transmission Investment Program - Tranche 1

Sovereign Project | 42039-034 Status: Active

Summary

ADB is supporting power transmission upgrades in Viet Nam to meet growing demand for electricity. The first tranche of the multitranche loan facility will finance the expansion and upgrading of 500 kilovolt and 220kV transmission lines and associated substations. It covers capacity development and support for project implementation, including detailed engineering and construction supervision.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Power Transmission Investment Program - Tranche 1
Project Number 42039-034
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2848-VIE: Power Transmission Investment Program - Tranche 1
Ordinary capital resources US$ 104.51 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector

Energy - Electricity transmission and distribution - Energy sector development and institutional reform

Gender Equity and Mainstreaming Some gender elements
Description

The Project proposed for financing under Tranche 1 comprises the following three components:

(i) expansion and upgrading of 500kV and 220kV transmission lines and associated substations throughout Viet Nam. Tranche 1 will financed four subprojects.

(ii) build on ongoing capacity support provided by ADB through capacity building technical assistance. Under Tranche 1, the services of a consulting firm will be engaged to provide training to at least 20 staff on (i) strategic corporate planning, business planning, and management, and (ii) accounting, financial management, planning, and control.

(iii) support project implementation with focus on detailed engineering, construction supervision, procurement, safeguard compliance, and the preparation of subsequent tranches of the investment program.

Project Rationale and Linkage to Country/Regional Strategy

Viet Nam's rapid development has been accompanied by steadily growing demand for electricity for both industrial development and private consumption. Consumption grew by an average of 14% annually during 2004-2010, substantially surpassing the average economic growth rate of 7% per year in the same period. Demand for electricity is expected to continue growing by an average of 14% per year during 2011-2015 and 11% during 2016-2020. It is projected that electricity consumption will increase from 85,932 gigawatt-hours in 2010 to 251,763 gigawatt-hours in 2020.

Industry consumes 52% of electricity, residential consumers 39%, service businesses 8%, and agriculture 1%. While industry is the largest electricity consumer, it is also the most important sector economically, projected by 2015 to account for 41% of gross domestic product, 29% of the workforce, and 87% of export revenues. Ensuring reliable electricity supply is therefore an important prerequisite to sustaining economic growth at the target of 7.5%-8.0% per year.

Viet Nam has made remarkable progress in expanding access to electricity, as the percentage of households without electricity fell from 22% in 1999 to only 3% in 2010. Those communities that are not yet connected to the grid are mainly in the less-developed and rather sparsely populated mountainous areas of the northwest. Per capita income reached $1,168 in 2010, and the poverty rate fell to 14.2%. The high concentration of industrial parks and general economic development induce many people to migrate to the centers of dynamic development and employment opportunities in the southeast, Central Highlands, and Red River Delta. Without additional generation capacity and transmission network expansion, the main load centers in these regions are expected to suffer a worsening electricity supply deficit and the share of urban and rural populations without electricity is expected to increase, in particular among populations with lower income and electricity consumption.

Impact Enhanced capacity to balance power load in northern and southern Viet Nam

Project Outcome

Description of Outcome Strengthened operational capacity
Progress Toward Outcome Extension of loan closing date from 31 December 2015 to 31 December 2016 is envisaged as construction of 500kV Pho Noi Substation is still ongoing and completion estimated by May 2016.
Implementation Progress
Description of Project Outputs

Component 1: Expanded Transmission Network

Component 2: Improved Operational Effectiveness and Efficiency of NPT

Component 3: Project Implementation Support

Status of Implementation Progress (Outputs, Activities, and Issues)

Component 1. Being closely monitored as construction of 500kV Pho Noi Substation is still ongoing. Three subprojects completed.

Component 2. Deferred to Tranche 4.

Component 3. Being closely monitored as remaining compensation payments is still ongoing. Submission of safeguards-related monitoring reports are being complied by project management boards.

Geographical Location Viet Nam

Safeguard Categories

Environment B
Involuntary Resettlement A
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects Subprojects of tranche 1 are category B under ADB's environment guidelines. No component of any of the four subprojects is located in an environmentally sensitive or protected area, and potential impacts during construction will be mitigated by using good international construction practices. An initial environmental examination report with an environmental management plan and implementation budget was prepared for each of the subprojects of tranche 1 and is disclosed on ADB's website. Environmental and social units will be formed within each PPMB to supervise implementation and assure occupational and community health and safety until operation.
Involuntary Resettlement Two subprojects of tranche 1 are category A - the 500kV/220kV Pho Noi substation and the 220kV Song May-Uyen Hung transmission line - and the other two subprojects are category B. There is no need to relocate houses, but 1,880 households will be affected by land acquisition, including 293 households likely to be significantly affected.
Indigenous Peoples Provincial governments confirmed that ethnic minorities do not reside in the subproject areas financed under tranche 1.
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services The procurement plan is provided on ADB's website.
Procurement The procurement plan is provided on ADB's website.

Responsible Staff

Responsible ADB Officer Hyunjung Lee
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
National Power Transmission Corporation
[email protected]
18 Tran Nguyen Han Street,
Hoan Kiem District, Hanoi-Vietnam
Ha Noi

Timetable

Concept Clearance -
Fact Finding -
MRM 16 Dec 2011
Approval 29 Dec 2011
Last Review Mission -
Last PDS Update 21 Mar 2016

Loan 2848-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
29 Dec 2011 10 Feb 2012 09 Jul 2012 31 Dec 2015 31 Dec 2016 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 139.78 Cumulative Contract Awards
ADB 104.51 29 Dec 2011 87.69 0.00 84%
Counterpart 35.27 Cumulative Disbursements
Cofinancing 0.00 29 Dec 2011 79.39 0.00 76%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - -

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Power Transmission Investment Program - Tranche 1: Environmental Monitoring Report (April-June 2016) Environmental Monitoring Reports Sep 2016
Power Transmission Investment Program - Tranche 1: Environmental Monitoring Report (January-March 2016) Environmental Monitoring Reports Jul 2016
Power Transmission Investment Program - Tranche 1: 500 kV Pho Noi Substation Environmental Monitoring Report (October-December 2015) Environmental Monitoring Reports Jun 2016
PTIP - Tranche 1: 220 kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (October-December 2015) Environmental Monitoring Reports May 2016
Power Transmission Investment Program - Tranche 1: 220 kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (October-December 2015) Environmental Monitoring Reports May 2016
Power Transmission Investment Program - Tranche 1: 500 kV/220 kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (July-September 2015) Environmental Monitoring Reports Mar 2016
Power Transmission Investment Program - Tranche 1: 500 kV/220 kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (April-June 2015) Environmental Monitoring Reports Mar 2016
Power Transmission Investment Program - Tranche 1: 220 kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (July-September 2015) Environmental Monitoring Reports Mar 2016
Power Transmission Investment Program - Tranche 1: 220 kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (July-September 2015) Environmental Monitoring Reports Mar 2016
Power Transmission Investment Program - Tranche 1: Pho Noi 500kV Substation Environmental Monitoring Report (July-September 2015) Environmental Monitoring Reports Nov 2015
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (January-June 2015) Environmental Monitoring Reports Aug 2015
Power Transmission Investment Program - Tranche 1: 220kV Phu My 2 Industrial Zone Substation Semiannual Environmental Monitoring Report (January-June 2015) Environmental Monitoring Reports Aug 2015
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (April-June 2015) Environmental Monitoring Reports Jun 2015
Power Transmission Investment Program - Tranche 1: 220 kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (April-June 2015) Environmental Monitoring Reports Jun 2015
PTIP - Tranche 1: 500/220kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (January-March 2015) Environmental Monitoring Reports Mar 2015
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (January-March 2015) Environmental Monitoring Reports Mar 2015
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (January-March 2015) Environmental Monitoring Reports Mar 2015
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (October-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program, Tranche 1: Semi-Annual Monitoring Report on Resettlement Plan Implementation (July-December 2014) Social Monitoring Reports Jan 2015
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (October-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 1: 220kV Phu My 2 Industrial Zone Substation Semiannual Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Semiannual Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 1: 220kV Phu My 2 Industrial Zone Substation and Connection Lines Internal Monitoring Report on Resettlement Plan Implementation (October-December 2014) Social Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Internal Monitoring Report on Resettlement Plan Implementation (October-December 2014) Social Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 1 - 500kV/220kV Bac Ninh 2–Pho Noi Transmission Line Subproject: Semiannual Environmental Monitoring Report No. 2 (July-December 2014) Environmental Monitoring Reports Dec 2014
PTIP - Tranche 1: 500/220kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (October-December 2014) Environmental Monitoring Reports Dec 2014
PTIP - Tranche 1: Bac Ninh 2-Pho Noi 500/220kV Transmission Line and Pho Noi 500kV Substation Social Monitoring Report (September-December 2014) Social Monitoring Reports Dec 2014
Power Transmission Investment Program (Tranche 1) - Bac Ninh 2-Pho Noi Transmission Line: Resettlement Plan (November 2014) Resettlement Plans Nov 2014
Power Transmission Investment Program (Tranche 1) - Pho Noi 500 kV Substation: Resettlement Plan (October 2014) Resettlement Plans Oct 2014
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (July-September 2014) Environmental Monitoring Reports Oct 2014
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (July-September 2014) Environmental Monitoring Reports Oct 2014
Power Transmission Investment Program (Tranche 1) - 220kV Song May-Uyen Hung Transmission Line: Resettlement Plan (September 2014) Resettlement Plans Sep 2014
Power Transmission Investment Program (Tranche 1) - 220kV Phu My 2 Industrial Zone Substation and Connection Lines: Resettlement Plan (September 2014) Resettlement Plans Sep 2014
Power Transmission Investment Program (Tranche 1) - 500kV/220kV Bac Ninh 2–Pho Noi Transmission Line Subproject: Semiannual Environmental Monitoring Report No. 1 (April-September 2014) Environmental Monitoring Reports Sep 2014
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (April-June 2014) Environmental Monitoring Reports Aug 2014
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (April-June 2014) Environmental Monitoring Reports Aug 2014
Power Transmission Investment Program - Tranche 1: 220kv Phu My 2 Industrial Zone Substation Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Jun 2014
Power Transmission Investment Program - Tranche 1: 220kv Song May - Uyen Hung Transmission Line Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Jun 2014
PTIP - Tranche 1: 500/220kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (April-June 2014) Environmental Monitoring Reports Jun 2014
PTIP- Tranche 1: 220kV Phu My 2 Industrial Zone Substation Environmental Monitoring Report (January-March 2014) Environmental Monitoring Reports Mar 2014
PTIP - Tranche 1: 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report (January-March 2014) Environmental Monitoring Reports Mar 2014
PTIP - Tranche 1: 500/220kV Bac Ninh 2–Pho Noi Transmission Line Environmental Monitoring Report (January-March 2014) Environmental Monitoring Reports Mar 2014

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.