ADB is helping Afghanistan upgrade its energy infrastructure to improve supply and increase regional power trade. The project will install transmission lines to expand the network in North-West Afghanistan and to connect to the Turkmenistan system. It will also extend the distribution network southeast of Kabul, the capital.
Project Name | Energy Sector Development Investment Program - Tranche 4 | ||||
Project Number | 42094-052 | ||||
Country | Afghanistan |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Grant |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Inclusive economic growth Regional integration |
||||
Drivers of Change | |||||
Sector / Subsector | Energy / Renewable energy generation - small hydro |
||||
Gender Equity and Mainstreaming | No gender elements | ||||
Description | The sub-projects, collectively the Project, under this Tranche 4 include (i) an electricity transmission sub-project in the North West Afghanistan to extend the network and connect to the Turkmenistan (TKM) system, and (ii) an electricity distribution sub-project to extend the distribution network south east of Kabul. The transmission sub-project will include a 500kV transmission line from the TKM border to Andkhoy and from Andkhoy to Sheberghan and a 220kV transmission line from Sheberghan to Mazar-e-Sharif. The 220kV substations will be constructed at Andkhoy and Sheberghan and the existing 220kV substation at Mazar-e-Sharif will be expanded. The distribution sub-project will include 20kV lines and 220/20 kV substations and low voltage network at Pul-e-Alam (Logar) and Gardez (Paktia). |
||||
Project Rationale and Linkage to Country/Regional Strategy | The transmission subproject will allow TKM to supply electricity to North-West AFG where demand is estimated at 210 megawatts (MW) requiring 1,000 megawatt-hour (MWh) by 2020 to supply 120,000 households, and at 330 MW requiring 1,750 gigawatt-hour (GWh) by 2030 to supply 145,000 households. It will also allow Uzbekistan (UZB) imports, to be used to supply the Kabul region, which is currently facing a supply shortfall. While electrification rate has increased from 5% in 2002 to 25% in 2012, AFG continues to place high priority on further increasing electrification. The distribution subproject meets this aim and is coordinated with related projects financed by the United States Government. The related project will extend the 220 kV network to Pul-e-Alam and Gardez where 220/20 kV substations will be constructed. The distribution subproject proposed under Tranche 4 will construct 20 kV and low voltage networks to be supplied from Pul-e-Alam and Gardez substation and bring electricity supply to 20,000 new households. |
||||
Impact | Increased regional power trade and energy supplies in Afghanistan |
Project Outcome | |
---|---|
Description of Outcome | Reliable power supplies to all grid connected customers |
Progress Toward Outcome | EPC contract for 220/20 kV sub-stations at Mazar-e-Sharif and Sheberghan was awarded to Siemens Consortium in Q4 2015. The distribution network contracts are unlikely to be completed by grant closing date. ADB requested the Government for their best effort to complete the works as much as possible before grant closing. |
Implementation Progress | |
Description of Project Outputs | Commissioning of 108 kms 500 kV transmission line from AFG/TKM border to Andkhoy to Sheberghan Commissioning of 142 kms 220 line from Sheberghan to Mazar-e-Sharif Commissioning of 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220 kV substation at Mazar-e- Sharif Commissioning of 13,000 new power connections at Pul-e-Alam, 13,000 new power connections in Gardez city, Wazay Zadran (5,000 connections), and Khost (13,000 connections) |
Status of Implementation Progress (Outputs, Activities, and Issues) | Target is unlikely achievable by closing date. Target is unlikely achievable by closing date. Target is unlikely achievable by closing date. Target is unlikely achievable by closing date. |
Geographical Location | Andkhoy, Gardez, Mazar-e Sharif, Pul-e 'Alam, Shibirghan |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | An IEE report for the Project has been prepared and posted in accordance with ADB Guidelines and ADB Safeguard Policy Statement, June 2009, Laws on the protection of nature of the Government of Afghanistan, discussions with the MEW and National Environmental Protection Agency (NEPA). The IEE will be updated during Project implementation based on contractor's detailed designs. The IEE for the distribution network projects have been submitted to ADB in July 2018. The Environmental Monitoring Reports will be submitted to ADB on an semi-annual basis. The quality of the consultant's Environmental Monitoring Reports have been below acceptable standards. |
Involuntary Resettlement | The Project may have some involuntary resettlement impacts that are not significant. A draft LARP for the transmission line (Andkhoy to Mazar-i-Sharif) was prepared in October 2012. Upon detailed design by the turnkey contractors, the LARPs will be updated. No civil works will be initiated until and unless all affected persons have been duly compensated and all LARPS fully implemented. The updated LARP for the transmission line project (220 kV D/C OHL Sheberghan-Mazar-E-Sharif) was disclosed in March 2018. The Resettlement due Diligence Report for the substation project (New Andkhoy 220/110/20 KV Substation) was disclosed in February 2018. The LARP for the transmission line project (Aquina-Shabergan 500 kV Single Circuit Transmission) was disclosed in January 2018. |
Indigenous Peoples | Impacts on indigenous peoples are not envisaged under the project. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | The security situation during project processing made it difficult to undertake effective community consultation without compromising the safety of staff and consultants. No public consultation were carried out at this stage. |
During Project Implementation | Necessary public consultation are being conducted on-site by the Program Management Office of DABS with assistance from the implementation consultant prior to commencement of construction and will be reported to ADB in due course. The project impacts are not considered significant. As the project develops and if particular risks or impacts to the local community are identified; then a community relation plan and grievance mechanism will be developed. |
Business Opportunities | |
---|---|
Consulting Services | 1. Program Management and Implementation Consultants - Quality-Based Selection using Full Technical Proposal 2. External Auditor - Single Source Selection SMEC was recruited as a program management and implementation consultant in February 2015. |
Procurement | 1. 500 kV Transmission Line (100 kms approx) from AFG/TKM border to Sheberghan and 220 kV Transmission Line (142 kms approx) between Sheberghan and Mazar Sharif - ICB Turnkey 2. 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220kv substation at Mazar Sharif - ICB Turnkey 3. 220/20 kv Distribution Networks 20 kV Distribution Networks: Lot 1: Pul-e-Alam(13,000 connections), Lot 2: Gardez (13,000 connections) and Wazay Zadran (5,000 connections); Lot 3:Khost (13,000 connections)- ICB Turnkey All EPC contracts were awarded. |
Responsible ADB Officer | Durrani, Hamidullah |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Afghanistan Resident Mission |
Executing Agencies |
Da Afghanistan Breshna Sherkat [email protected] Chaman Houzouri, Kabul, Islamic Republic of Afghanistan |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | 23 Nov 2012 |
Approval | 18 Dec 2012 |
Last Review Mission | - |
Last PDS Update | 24 Sep 2018 |
Grant 0332-AFG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
18 Dec 2012 | 07 Mar 2013 | 05 Jun 2013 | 30 Jun 2017 | 28 Nov 2020 | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 203.00 | Cumulative Contract Awards | |||
ADB | 200.00 | 18 Dec 2012 | 195.23 | 0.00 | 98% |
Counterpart | 3.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 18 Dec 2012 | 183.74 | 0.00 | 92% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | - | Satisfactory | Satisfactory | Satisfactory | - | Partly satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Office Manager | Individual - Consulting | Closed | 16 Jan 2020 | 22 Jan 2020 |
Social Safeguard Specialist | Individual - Consulting | Closed | 15 Jan 2020 | 21 Jan 2020 |
Security Coordinator | Individual - Consulting | Closed | 15 Jan 2020 | 21 Jan 2020 |
Security Coordinator | Individual - Consulting | Closed | 24 Dec 2019 | 30 Dec 2019 |
Office Manager - National | Individual - Consulting | Closed | 24 Dec 2019 | 30 Dec 2019 |
Social Safeguards Specialist | Individual - Consulting | Closed | 24 Dec 2019 | 30 Dec 2019 |
Finance and Admin Specialist | Individual - Consulting | Closed | 24 Nov 2019 | 30 Nov 2019 |
Procurement and Contract Specialist | Individual - Consulting | Closed | 24 Nov 2019 | 30 Nov 2019 |
Distribution System Engineer/Project Manager | Individual - Consulting | Closed | 25 Sep 2019 | 01 Oct 2019 |
Substation Electrical Engineer / Project Manager | Individual - Consulting | Closed | 24 Sep 2019 | 30 Sep 2019 |
Team Leader / Transmission Line Engineer | Individual - Consulting | Closed | 24 Sep 2019 | 30 Sep 2019 |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
TURNKEY CONTRACT FOR 220/110/20KV SUBSTATIONS AT ANDKHOY SHEBERGHAN AND EXPANSION OF MAZAR-E-SHARI | Grant 0332 | 06 Feb 2018 | SIEMENS PAKISTAN ENGINEERING CO. LTD | FEYESLEBENSTR.1D-91058 ERLANGEN B-72 ESTATE AVE SITE KARACHI PAKISTAN | Da Afghanistan Breshna Sherkat | 35,653,240.00 | — |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Energy Sector Development Investment Program - Project 4: Procurement Plan | Procurement Plans | May 2020 |