Afghanistan: Energy Sector Development Investment Program - Tranche 4

Sovereign Project | 42094-052 Status: Active

Summary

ADB is helping Afghanistan upgrade its energy infrastructure to improve supply and increase regional power trade. The project will install transmission lines to expand the network in North-West Afghanistan and to connect to the Turkmenistan system. It will also extend the distribution network southeast of Kabul, the capital.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Energy Sector Development Investment Program - Tranche 4
Project Number 42094-052
Country Afghanistan
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0332-AFG: MFF - Energy Sector Development Investment Program Project 4 (formerly MFF - Energy Development Project Tranche 4)
Asian Development Fund US$ 200.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector

Energy - Renewable energy generation - small hydro

Gender Equity and Mainstreaming No gender elements
Description

The sub-projects, collectively the Project, under this Tranche 4 include (i) an electricity transmission sub-project in the North West Afghanistan to extend the network and connect to the Turkmenistan (TKM) system, and (ii) an electricity distribution sub-project to extend the distribution network south east of Kabul. The transmission sub-project will include a 500kV transmission line from the TKM border to Andkhoy and from Andkhoy to Sheberghan and a 220kV transmission line from Sheberghan to Mazar-e-Sharif. The 220kV substations will be constructed at Andkhoy and Sheberghan and the existing 220kV substation at Mazar-e-Sharif will be expanded.

The distribution sub-project will include 20kV lines and 220/20 kV substations and low voltage network at Pul-e-Alam (Logar) and Gardez (Paktia).

Project Rationale and Linkage to Country/Regional Strategy

The transmission subproject will allow TKM to supply electricity to North-West AFG where demand is estimated at 210 megawatts (MW) requiring 1,000 megawatt-hour (MWh) by 2020 to supply 120,000 households, and at 330 MW requiring 1,750 gigawatt-hour (GWh) by 2030 to supply 145,000 households. It will also allow Uzbekistan (UZB) imports, to be used to supply the Kabul region, which is currently facing a supply shortfall.

While electrification rate has increased from 5% in 2002 to 25% in 2012, AFG continues to place high priority on further increasing electrification. The distribution subproject meets this aim and is coordinated with related projects financed by the United States Government. The related project will extend the 220 kV network to Pul-e-Alam and Gardez where 220/20 kV substations will be constructed. The distribution subproject proposed under Tranche 4 will construct 20 kV and low voltage networks to be supplied from Pul-e-Alam and Gardez substation and bring electricity supply to 20,000 new households.

Impact Increased regional power trade and energy supplies in Afghanistan

Project Outcome

Description of Outcome Reliable power supplies to all grid connected customers
Progress Toward Outcome

The turnkey contract for 220/20 kV sub-stations at Mazar-e-Sharif and Sheberghan was awarded to Siemens Consortium in Q4 2015.

The turnkey contract for transmission line was awarded to Gammon India in Q4 2015.

Both turnkey contractors have been fielded and works started.

The distribution package for 40,000 distribution connections in eastern Afghanistan is under evaluation with EA. The contract is expected to be awarded by early November 2016.

The supervision implementation consulting contract was awarded in Q2 2015 and consulting firm has been fielded since Q4 2015.

All contract awards were delayed by nearly one year because of the late signing of the power purchase and sales agreement (300-MW) between the governments and Afghanistan and Turkmenistan.

Implementation Progress
Description of Project Outputs

Commissioning of 108 kms 500 kV transmission line from AFG/TKM border to Andkhoy to Sheberghan

Commissioning of 142 kms 220 line from Sheberghan to Mazar-e-Sharif

Commissioning of 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220 kV substation at Mazar-e- Sharif

Commissioning of 13,000 new power connections at Pul-e-Alam, 13,000 new power connections in Gardez city, Wazay Zadran (5,000 connections), and Khost (13,000 connections)

Status of Implementation Progress (Outputs, Activities, and Issues)

Target achievable

Target achievable

EPC contract for 500 kV transmission line was awarded to Gammon India Limited in Q4 2015.

target achievable.

Target achievable.

Geographical Location Andkhoy, Sheberghan, Mazar-e-Sharif, Pul-e-Alam, and Gardez

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects

An IEE report for the Project has been prepared and posted in accordance with ADB Guidelines and ADB Safeguard Policy Statement, June 2009, Laws on the protection of nature of the Government of Afghanistan, discussions with the MEW and National Environmental Protection Agency (NEPA). The IEE will be updated during Project implementation based on contractor's detailed designs.

The Environmental Monitoring Reports will be submitted to ADB an a bi-annual basis, once detailed design of both turnkey contracts is completed and physical works begin.

Involuntary Resettlement The Project may have some involuntary resettlement impacts that are not significant. A draft LARP for the transmission line (Andkhoy to Mazar-i-Sharif) was prepared in October 2012. Upon detailed design by the turnkey contractors, the LARPs will be updated. No civil works will be initiated until and unless all affected persons have been duly compensated and all LARPS fully implemented.
Indigenous Peoples Impacts on indigenous peoples are not envisaged.
Stakeholder Communication, Participation, and Consultation
During Project Design The current security situation makes it difficult to undertake effective community consultation without compromising the safety of staff and consultants. No public consultation has been carried out at this stage.
During Project Implementation Necessary public consultation will be conducted on-site by the Program Management Office of DABS with assistance from the implementation consultant prior to commencement of construction and will be reported to ADB in due course. The project impacts are not considered significant. As the project develops and if particular risks or impacts to the local community are identified; then a community relation plan and grievance mechanism will be developed.

Business Opportunities

Consulting Services

1. Program Management and Implementation Consultants - Quality-Based Selection using Full Technical Proposal

2. External Auditor - Single Source Selection

Procurement

1. 500 kV Transmission Line (100 kms approx) from AFG/TKM border to Sheberghan and 220 kV Transmission Line (142 kms approx) between Sheberghan and Mazar Sharif - ICB Turnkey

2. 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220kv substation at Mazar Sharif - ICB Turnkey

3. 220/20 kv Distribution Networks 20 kV Distribution Networks:

Lot 1: Pul-e-Alam(13,000 connections), Lot 2: Gardez (13,000 connections) and Wazay Zadran (5,000

connections); Lot 3:Khost (13,000 connections)- ICB Turnkey

Responsible Staff

Responsible ADB Officer Aleem, Asad
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Da Afghanistan Breshna Sherkat (DABS)
[email protected]
Chaman Houzouri,
Kabul,
Islamic Republic of Afghanistan

Timetable

Concept Clearance -
Fact Finding -
MRM 23 Nov 2012
Approval 18 Dec 2012
Last Review Mission -
Last PDS Update 23 Sep 2016

Grant 0332-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
18 Dec 2012 07 Mar 2013 05 Jun 2013 30 Jun 2017 28 Nov 2018 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 203.00 Cumulative Contract Awards
ADB 200.00 18 Dec 2012 97.67 0.00 49%
Counterpart 3.00 Cumulative Disbursements
Cofinancing 0.00 18 Dec 2012 14.53 0.00 7%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - -

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.