Bangladesh : Dhaka Environmentally Sustainable Water Supply Project – Additional Financing
The proposed additional financing will finance cost overruns experienced in the ongoing project and additional scope (tertiary distribution network) to further ensure achievement of project outcome.
Project Details
-
Project Officer
Tada, Momoko
South Asia Department
Request for information -
Country/Economy
Bangladesh -
Sector
- Water and other urban infrastructure and services
Project Name | Dhaka Environmentally Sustainable Water Supply Project – Additional Financing | ||||||||||||||||
Project Number | 42173-016 | ||||||||||||||||
Country / Economy | Bangladesh |
||||||||||||||||
Project Status | Active | ||||||||||||||||
Project Type / Modality of Assistance | Grant Loan |
||||||||||||||||
Source of Funding / Amount |
|
||||||||||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships |
||||||||||||||||
Sector / Subsector | Water and other urban infrastructure and services / Urban policy, institutional and capacity development - Urban sanitation - Urban water supply |
||||||||||||||||
Gender | Effective gender mainstreaming | ||||||||||||||||
Description | The proposed additional financing will finance cost overruns experienced in the ongoing project and additional scope (tertiary distribution network) to further ensure achievement of project outcome. The proposed additional financing will cover the remaining works of Package 1, and most of the works of Packages 2 and 3.1 which are scheduled to be awarded by the end of 2020. For Package 2, the contract price (ADB fund) is likely to be around $58.8 million, an increase by around 6% from the cost estimate at the appraisal of the ongoing project, which is within a generally acceptable range. For Package 3.1, the technical bid evaluation report is currently under ADB's review. Large cost increase is not anticipated in this package because the bids were based on detailed design and the nature of works are relatively simple. Government has proposed an additional scope, Package 3.2, with estimated cost of $39.3 million. Issuance of invitation for bid of Package 3.2 is targeted in late September 2020, with contract award targeted in June 2021. Again, large cost increase is not anticipated for this package due to the same reasons as mentioned earlier for Package 3.1. The impact, outcomes, and outputs of the overall project will remain the same as the ongoing project, except for (i) additional indicator for Output 1 for Package 3.2, and (iii) additional Output 4 for the ADF grant. |
||||||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | The population in Dhaka was around 19.6 million in 2018. It is expected to increase to 28.1 million in 2030, leading to increasing demand for water supply service. Also, average annual ground water depletion in Dhaka in the next 10-12 years is projected to be around 5 meters due to rapid ground water extraction. To address the high dependency on ground water resources, DWASA strategically aims to increase the ratio of surface water resource from current 22% to 70% by end 2021. The overall project is a pivotal investment in DWASA's strategic direction by developing a new surface water supply scheme with Meghna River as water source, which has good water quality and ample quantity even during the dry season. The overall project will also help mitigate the effects of COVID-19 pandemic or other epidemic/pandemic in the future through securing reliable water supply service. | ||||||||||||||||
Impact | Improved access to and quality of sustainable water supply services in Dhaka |
Project Outcome | |
---|---|
Description of Outcome | More reliable and improved security of water supply and sanitation in Dhaka achieved |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | New surface water supply system developed Existing distribution network in zone 6 strengthened DWASA's management and administration capacity improved Empowerment of women and vulnerable groups in LICs supported |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Dhaka |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | All consultant recruitment under the project will adhere to the ADB Procurement Policy (2017, as amended from time to time) and the Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Procurement | All procurement of goods and works under the project will adhere to the ADB Procurement Policy (2017, as amended from time to time) and the Procurement Regulations for ADB Borrowers (2017, as amended from time to time).' |
Responsible ADB Officer | Tada, Momoko |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Urban Development and Water Division, SARD |
Executing Agencies |
Dhaka Water Supply and Sewerage Authority Mr. A.Q. Chowdhury [email protected] 98 Kazi Nazrul Islam Avenue, Kawran Bazar, Dhaka |
Timetable | |
---|---|
Concept Clearance | 13 Nov 2020 |
Fact Finding | 23 Nov 2020 to 01 Dec 2020 |
MRM | 29 Mar 2021 |
Approval | 11 Oct 2021 |
Last Review Mission | - |
Last PDS Update | 11 Oct 2021 |
Grant 0805-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
11 Oct 2021 | 01 Mar 2022 | 08 Apr 2022 | 31 Mar 2026 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 5.00 | Cumulative Contract Awards | |||
ADB | 5.00 | 01 Jul 2022 | 0.00 | 0.00 | 0% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 01 Jul 2022 | 0.00 | 0.00 | 0% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | - | Unsatisfactory | Unsatisfactory | Unsatisfactory | - | Unsatisfactory |
Loan 4124-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
11 Oct 2021 | 01 Mar 2022 | 08 Apr 2022 | 31 Mar 2026 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 198.50 | Cumulative Contract Awards | |||
ADB | 50.00 | 01 Jul 2022 | 39.70 | 0.00 | 79% |
Counterpart | 148.50 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 01 Jul 2022 | 0.00 | 0.00 | 0% |
Loan 4126-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
11 Oct 2021 | 01 Mar 2022 | 08 Apr 2022 | 31 Mar 2026 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 85.00 | Cumulative Contract Awards | |||
ADB | 85.00 | 01 Jul 2022 | 1.00 | 0.00 | 1% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 01 Jul 2022 | 0.00 | 0.00 | 0% |
Loan 8405-BAN
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 141.50 | Cumulative Contract Awards | |||
ADB | 0.00 | - | 0.00 | 0.00 | % |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 141.50 | - | 0.00 | 0.00 | % |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
42173-BAN: Dhaka Environmentally Sustainable Water Supply Project-Additional Financing (DESWSP-AF) [OCB-03.7B/PG/DESWSP/DWASA] | Invitation for Bids | Closed | ||
ADB Loan 42173-BAN: Dhaka Environmentally Sustainable Water Supply Project – Additional Financing [06/FL/DESWSP/2020] - CORRIGENDUM | Invitation for Bids | Closed | ||
ADB Loan 42173-BAN: Dhaka Environmentally Sustainable Water Supply Project – Additional Financing [06/FL/DESWSP/2020] - ORIGINAL | Invitation for Bids | Closed | ||
42173-BAN: Dhaka Environmentally Sustainable Water Supply Project – Additional Financing- | Advance Notice | Active |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Management, Design and Supervision Consultant | Loan 4126 | 05 May 2023 | Mott MacDonald Limited JV | Demeter House, Station Rd, Cambridge, CBI 2RS, United Kingdom | Dhaka Water Supply and Sewerage Authority | 9,804,834.59 | 9,731,324.55 |
Strengthening access of women and vulnerable groups in selected slums to improve water and sanitation services - Social | Grant 0805 | 07 Mar 2023 | Hasne Ara Begum | Japan Garden City Building No. 13 Flat No. 102, Mohammadpur, Dhaka, 1207 Bangladesh | Dhaka Water Supply and Sewerage Authority | 356,030.60 | — |
Strengthening access of women and vulnerable groups in selected slums to improved water and sanitation services - Administrative and Finance Expert | Grant 0805 | 19 Feb 2023 | Mr. Kaisarul Islam | House #4, Road #18 Sector #11, Uttara, Dhaka-1230 | Dhaka Water Supply and Sewerage Authority | 120,495.82 | — |
Package 3.2: Design and Construction of Feeder Lines inside Dhaka City (Contract No.: 06/FL/DESWSP/2020) | Loan 4126 | 29 Dec 2022 | China Geo-Engineering Corporation | Building 2, Yard 92 Xiangshan South Road, Haidian District, Beijing P.R.C | Dhaka Water Supply and Sewerage Authority | 35,253,632.82 | 25,975,712.08 |
MANAGEMENT, DESIGN AND SUPERVISION CONSULTANT | Loan 4126 | 07 Jul 2022 | MOTT MACDONALD LIMITED JV | DEMETER HOUSE, STATION RD, CAMBRIDGE, CBI 2RS, UNITED KINGDOM | Dhaka Water Supply and Sewerage Authority | 14,971,435.60 | 10,980,000.00 |
DESIGN-BUILD CONTRACT FOR INTAKE, RAW WATER PIPELINE, AND WATER TREATMENT PLANT AT GANDHARBPUR (ICB-01/B&D/DESWSP/2014) | Loan 4126 | 07 Jul 2022 | GANDHARBPUR WATER TREATMENT SNC (COMPANY) | 183 AVENUE DU 18 JUIN 1940 IN RUEIL MALM, AISON CITY 92500, FRANCE | Dhaka Water Supply and Sewerage Authority | 322,284,462.30 | 14,900,000.00 |
Package 3.1 ICB-4.0(DRPL)/DESWSP/2018 - Distribution Reinforcement Pipeline inside Dhaka 21-24KM | Loan 4124 | 21 Jun 2022 | CHINA GEO-ENGINEERING CORPORATION | Building 2, Yard 92, Xiangshan SouthRoad, Haidian District Beijing, PRC | Dhaka Water Supply and Sewerage Authority | 63,471,199.52 | 36,237,403.50 |
NGO/Consulting Firm for Preparation and Assistance for Implementation of Resettlement Plan for Packages 3.1 and 3.2 (RFP 7) | Loan 4126 | 13 May 2022 | Knowledge Management Consultants (KMC) Ltd. - Lead Firm and Global Capacity Building and Consultancy Ltd (GCBCL) | House #09 (Level 3), Road #1B, Banani, Dhaka-1213, Bangladesh | Dhaka Water Supply and Sewerage Authority | 272,175.09 | 210,733.44 |
Treated Water Pipeline from WTP to injection point 14 Km (Package 2) ICB3.0/TWP/DESWSP/2018 | Loan 4124 | 12 May 2022 | CHINA CAMC ENGINEERING CO. LTD. | 3 DANLING STREET, HAIDIAN DISTRICT, BEIJING, PRC | Dhaka Water Supply and Sewerage Authority | 89,742,064.19 | 5,776,724.31 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Dhaka Environmentally Sustainable Water Supply Project - Additional Financing: Procurement Plan | Procurement Plans | Dec 2020 |