Project Name | Support for the Implementation of the Poverty Reduction Program V - Subprogram 2 | ||||
Project Number | 42191-023 | ||||
Country / Economy | Viet Nam |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development Partnerships |
||||
Sector / Subsector | Public sector management / Economic affairs management |
||||
Gender | |||||
Description | same as subprogram 1 | ||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | a continued reduction in poverty in Viet Nam in 2008 2010 and beyond. |
Project Outcome | |
---|---|
Description of Outcome | the successful implementation of the Government's SEDP 2006 2010, which will not only reduce poverty in 2006 2010 but also improve Viet Nam's economic competitiveness and strengthen the foundations for inclusive and sustainable growth and a continued reduction in poverty beyond 2010. |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | same as subprogram 1 |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | no |
Procurement | no |
Responsible ADB Officer | Konishi, Ayumi |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Viet Nam Resident Mission (VRM) |
Executing Agencies |
State Bank of Vietnam |
Timetable | |
---|---|
Concept Clearance | 26 Jun 2008 |
Fact Finding | 18 May 2009 to 20 May 2009 |
MRM | 06 Jul 2009 |
Approval | 15 Oct 2009 |
Last Review Mission | - |
PDS Creation Date | 17 Mar 2009 |
Last PDS Update | 21 Oct 2009 |
Loan 2570-VIE
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
15 Oct 2009 | 20 Oct 2009 | 04 Dec 2009 | 31 May 2010 | - | 25 Dec 2009 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 100.00 | Cumulative Contract Awards | |||
ADB | 100.00 | 17 Jun 2022 | 102.02 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Jun 2022 | 102.02 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Support for the Implementation of the Poverty Reduction Program V - Subprogram 2 | Reports and Recommendations of the President | Sep 2009 |
Loan Agreement for Support for the Implementation of the Poverty Reduction Program V - Subprogram 2 between Socialist Republic of Viet Nam and Asian Development Bank dated 20 October 2009 | Loan Agreement (Special Operations) | Oct 2009 |
Support for the Implementation of the Poverty Reduction Program V (Program Cluster) - Subprogram 2 | Design and Monitoring Frameworks | Dec 2009 |
Support the Implementation of the Poverty Reduction Programs IV and V | Project/Program Completion Reports | Sep 2013 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Viet Nam: Support the Implementation of the Poverty Reduction Programs IV and V | Validations of Project Completion Reports | Aug 2014 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.