Project Name | Rajasthan Secondary Towns Development Sector Project | ||||
Project Number | 42267-031 | ||||
Country | India |
||||
Project Status | Approved | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships |
||||
Sector / Subsector | Water and other urban infrastructure and services / Urban policy, institutional and capacity development - Urban sanitation - Urban water supply |
||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Rajasthan |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | Initial environmental examinations (IEE) conducted for 5 sample subprojects indicate that the project is unlikely to have any significant adverse environmental impacts that are irreversible, diverse, or unprecedented. Potential impacts are site-specific, temporary in nature and can be mitigated through proper engineering designs and recommended mitigation measures. An environmental assessment and review framework in accordance with SPS and applicable laws and regulations will guide subproject selection, screening and categorization, environmental assessment, and the implementation of subprojects identified after ADB Board approval. Category A subprojects will not be considered under the project. All draft IEEs will be cleared by ADB prior to start of construction and environmental management plans included in contract documents. All statutory clearances and no objections will be obtained prior to start of construction activities. |
Involuntary Resettlement | RUDSICO prepared a resettlement framework in line with SPS and applicable laws to guide subproject screening and assess resettlement impacts. Subprojects with significant involuntary resettlement impacts (Category A) will not be eligible for funding under the project. Based on the draft resettlement plans and one due diligence report of 3 sample subprojects, the project will cause impacts that are not deemed significant: (i) permanent economic impacts on non-titleholders on government land; and (ii) temporary impacts during civil works. The measures in the draft resettlement plans are adequate to deal with identified risks. Draft resettlement plans will form part of the contract documents, updated during detailed design and submitted to ADB for review and disclosure. The draft resettlement framework and plans will be disclosed to project-affected people and on ADB and project websites, and final plans disclosed to affected persons. |
Indigenous Peoples | Scheduled tribes comprise only 3.2% of the state's urban population. In comparison, scheduled tribes comprise 10.6% of the total population in the sample town of Abu Road, and 33.8% in 6 nearby villages, all located in a scheduled area. Scheduled tribes will benefit from the improved WSS services and receive free household connections. In the sample subprojects appraised to date, the beneficiary scheduled tribes are not rendered vulnerable by the project. RUDSICO has prepared an indigenous peoples planning framework in line with SPS and applicable laws to ensure that, for subprojects to be prepared after Board approval, scheduled tribes will receive culturally appropriate benefits and adverse impacts will be addressed. Category A subprojects will not be considered under the project. The draft resettlement and indigenous peoples plan (RIPP) for Abu Road identifies only beneficial impacts to scheduled tribes and has adequate measures to include tribes in project benefits. Combined RIPPs will also be required for Banswara and Pratapgarh. The draft and final RIPPs will be disclosed to affected/benefited Indigenous Peoples communities and disclosed on ADB and project websites. Project management and implementation consultants will assist RUDSICO to manage indigenous peoples risks and impacts. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Public consultations were conducted for sample subprojects during preparation of the safeguards documents. Key stakeholders were consulted during feasibility study on priorities for investment in each town. |
During Project Implementation | RUDSICO is mobilizing a Community Awareness and Public Participation Consultant to support stakeholder communication, participation and consultation throughout project implementation. Two social mobilizers will be assigned to each project town and supported by a larger team. The project also has a community level management committee that will meet monthly and help ensure good communication between the different agencies, local leaders and urban local bodies. Grievances will be handled following the project's grievance redress mechanism. |
Business Opportunities | |
---|---|
Consulting Services | All consultant recruitment will be undertaken by RUDSICO in accordance with the ADB Procurement Policy (2017, as amended from time to time) and the Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Procurement | All procurement of goods and works will be undertaken by RUDSICO in accordance with the ADB Procurement Policy (2017, as amended from time to time) and the Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Responsible ADB Officer | Kim, Na Won |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Urban Development and Water Division, SARD |
Executing Agencies |
Local Self Government Department (LSGD) Urban Governance,Government Secretariat Jaipur - 302005 Rajasthan, India |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | - |
Last Review Mission | - |
Last PDS Update | 25 Sep 2020 |
Loan 3972-IND
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
25 Sep 2020 | - | - | 31 May 2028 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 428.50 | Cumulative Contract Awards | |||
ADB | 300.00 | 25 Sep 2020 | 0.00 | 0.00 | 0% |
Counterpart | 128.50 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 25 Sep 2020 | 0.00 | 0.00 | 0% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
ADB, India Sign $300 Million Loan to Develop Rajasthan’s Secondary Towns
ADB and the Government of India have signed a $300 million loan to finance inclusive and sustainable water supply and sanitation infrastructure and services in 14 secondary towns of the state of Rajasthan.
Tenders
No tenders for this project were found.
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT LAXMANGARH | Loan 3972 | 18 Jan 2021 | LARSEN & TOUBRO LIMITED | MOUNT POONAMALLEE ROAD MANNAPAKKAM, CHENNAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 6,754,910.01 | 4,923,815.08 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT FATEHPUR | Loan 3972 | 18 Jan 2021 | LARSEN & TOUBRO LIMITED | MOUNT POONAMALLEE ROAD MANNAPAKKAM, CHENNAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 15,692,082.11 | 12,154,532.01 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT RATANGARH | Loan 3972 | 18 Jan 2021 | LARSEN & TOUBRO LIMITED | MOUNT POONAMALLEE ROAD MANNAPAKKAM, CHENNAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 24,917,116.05 | 19,497,881.70 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT SIROHI | Loan 3972 | 18 Jan 2021 | LARSEN & TOUBRO LIMITED | MOUNT POONAMALLEE ROAD MANNAPAKKAM, CHENNAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 29,216,077.16 | 22,687,637.80 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT ABU ROAD | Loan 3972 | 18 Jan 2021 | LARSEN & TOUBRO LIMITED | MOUNT POONAMALLEE ROAD MANNAPAKKAM, CHENNAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 36,025,660.07 | 27,870,844.71 |
PROJECT MANAGEMENT AND CAPACITY BUILDING CONSULTAN | Loan 3972 | 14 Jan 2021 | SHAH TECHNICAL CONSULTANTS PVT LTD INDIA | 407 RAHEJA CENTRE NARUMAN POINT, MUMBAI INDIA | Local Self Government Department (LSGD) | CONSULTANCY | 4,344,383.65 | 4,344,383.65 |
CONTRACT MANAGEMENT SUPERVISION CONSULTANT | Loan 3972 | 14 Jan 2021 | NIPPON KOEI INDIA PVT LTD IN JV WITH NIPPON | 5TH FLR, EROS CORPORATE TOWER NEHRU PLACE, NEW DELHI INDIA | Local Self Government Department (LSGD) | CONSULTANCY | 7,148,397.21 | 7,148,397.21 |
CONTRACT MANAGEMENT SUPERVISION CONSULTANT | Loan 3972 | 14 Jan 2021 | HASKONING DHV CONSULTING PVT LTD JV WITH | ENGINEER GROUP LTD GREEN BLVD, TOWER B,NOIDA, UTTAR PRADESH INDIA | Local Self Government Department (LSGD) | CONSULTANCY | 7,542,809.42 | 7,542,809.42 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT PRATAPGARH | Loan 3972 | 14 Jan 2021 | KHILARI INFRASTRUCTURE PVT LTD | 101 TO 104 PRABHAT CENTER ANNEX SECTOR 1A, CBD BELAPUR,MUMBAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 26,031,142.52 | 19,922,075.32 |
WATER SUPPLY AND SANITATION IMPROVEMENT WORKS AT SARDARSHAHAR | Loan 3972 | 14 Jan 2021 | LARSEN & TOUBRO LIMITED | L&T HOUSE, NAROTTAM MORARJI MARG BALLARD ESTATE, MUMBAI INDIA | Local Self Government Department (LSGD) | CONSTRUCTION | 26,864,244.74 | 20,100,517.68 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Rajasthan Secondary Towns Development Sector Project: Procurement Plan | Procurement Plans | Mar 2020 |