Papua New Guinea : Civil Aviation Development Investment Program

Sovereign Project | 43141-013

The program involves upgrading and rehabilitation of airports identified under project 1: (i) Wewak, (ii) Hoskins, (iii) Gurney, (iv) Mt. Hagen, and (v) Jackson's domestic airport. The first tranche will finance the following under project 1: (i) Improvements in pavements and fencing identified as requiring emergency works to comply with ICAO safety and security standards; (ii) Support for (a) engineering design, preparation of bid documents, and procurement by the NAC; and (b) preparation by the NAC of investment proposals for subsequent projects and tranches for ADB approval; and (iii) Consulting services to NAC for the supervision of (a) airport improvement contracts for the five project 1 airports, and (b) long-term maintenance contracts for these five airports. In addition to the five airports, two others (Kavieng and Goroka) will have new security fences installed.

Project Details

  • Project Officer
    Villareal, Maria Theresa J.
    Pacific Department
    Request for information
  • Country/Economy
    Papua New Guinea
  • Sector
    • Transport
Project Name Civil Aviation Development Investment Program
Project Number 43141-013
Country / Economy Papua New Guinea
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
MFF Facility Concept 0039-PNG: Civil Aviation Development Investment Program
Asian Development Fund US$ 120.00 million
Ordinary capital resources US$ 360.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Private sector development
Sector / Subsector

Transport /

Gender Effective gender mainstreaming
Description The program involves upgrading and rehabilitation of airports identified under project 1: (i) Wewak, (ii) Hoskins, (iii) Gurney, (iv) Mt. Hagen, and (v) Jackson's domestic airport. The first tranche will finance the following under project 1: (i) Improvements in pavements and fencing identified as requiring emergency works to comply with ICAO safety and security standards; (ii) Support for (a) engineering design, preparation of bid documents, and procurement by the NAC; and (b) preparation by the NAC of investment proposals for subsequent projects and tranches for ADB approval; and (iii) Consulting services to NAC for the supervision of (a) airport improvement contracts for the five project 1 airports, and (b) long-term maintenance contracts for these five airports. In addition to the five airports, two others (Kavieng and Goroka) will have new security fences installed.
Project Rationale and Linkage to Country/Regional Strategy Civil aviation (i) supports the socioeconomic development of the country by providing safe, efficient, reliable, sustainable, and affordable aviation services and infrastructure; (ii) gives all weather access to the country and increases the mobility of communities; and (iii) serves important community needs by making noncommercial destinations more accessible. Capacity constraints and deteriorating infrastructure, however, threaten the safety certification of the airports and place these socioeconomic objectives at risk. The CAA's well articulated sector development plan (Civil Aviation Authority. 2008. Strategic Investment Plan. Port Moresby) addresses the risks, but the agency needs help in carrying out the plan and meeting obligations. External funding to rehabilitate and upgrade the national airports will support the Government's Medium Term Development Strategy (MTDS) objectives of economic growth, rural development, poverty reduction, and human resource development.
Impact

The investment program will establish a sustainable civil aviation network to support the economic growth of the country. In that way, it will help meet the objectives of ADB's country strategy and program, particularly those for the transport sector, and the Government's MTDS objectives of (i) economic growth, (ii) rural development, (iii) poverty reduction, and (iv) human resource development.

Project Outcome
Description of Outcome

The investment program will result in safer, more secure, and more efficient all-weather access to air transport services in the project areas through (i) better airport facilities; (ii) safer and more secure air travel; (iii) more accessible markets, natural resource and mineral sites, and livelihood opportunities; and (iv) reduced costs of air travel to all the project areas. It will help achieve the Government's goal of securing and maintaining ICAO certification for the safety and security standards at its airport operations and facilities

Progress Toward Outcome NAC is implementing work in all three Tranche/Project 1 output areas, i.e: i) reformed institutions, ii) improved infrastructure and iii) improved operations, and is set to complete them by 2014. The Design Supervision Consultants (DSC) and individual consultants are assisting the Project Implementation Unit (PIU) and strengthening NAC's capacity to implement Project 1 and also subsequent projects.
Implementation Progress
Description of Project Outputs

The investment program will concentrate first of all on carrying out priority actions to comply with ICAO security and safety standards, and then on increasing capacity for growth in services. The outputs will be as follows: (i) rehabilitated airport infrastructure, including runways, taxiways, and aprons; (ii) upgraded runways and passenger terminals that can accommodate larger aircraft; (iii) communication, navigation, surveillance, and firefighting equipment; (iv) better maintained facilities; and (v) an institutionally strengthened and reformed CAA and its operational units. The inputs will comprise financing for civil works and consulting services in program administration, construction supervision, and support for the ongoing institutional reforms.

Status of Implementation Progress (Outputs, Activities, and Issues)

Restructuring of former CAA is completed. Three separate entities - National Airports Corporation, PNG Air Services Ltd and Civil Aviation Safety Authority - have been established. The three institutions are fully operational.

Security fencing construction work in Kavieng is completed as at June 2012. NAC signed the Port Moresby airport apron extension contract in May 2012 and work is ongoing. NAC also signed the contract for security fencing work at Hoskins, Goroka, Wewak and Gurney airport in August 2012 and contractor has now commenced work. NAC issued bids for Hoskins Airport Upgrade of the runway on 02 March 2012 and bids closed on 11 May 2012. PC approved award of contract on 18 January 2013 and No objection letter for award issued to NAC on 21 January 2013.

NAC issued bids for Mt. Hagen terminal construction on 15 February 2012 and bids closed on 16 May 2012. PC paper approved Feb 12, 2013 and awaiting Govt approval for award.

NAC is formulating initial work for asset management.

Port Moresby Instrument Landing System (ILS) completed. PNG Air Services Ltd commissioned the ILS on 19 April 2011.

ADB approved the contract award for the three fire equipment on 3 February 2012. NAC signed this contract on 27 April 2012. Shipment of the 3 Fire equipments is expected in March 2013.

Geographical Location Nation-wide
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects Measures taken as identified in the Initial Environmental Examination (IEE).
Involuntary Resettlement Consultation with parties likely to be affected ongoing.
Indigenous Peoples None.
Stakeholder Communication, Participation, and Consultation
During Project Design An initial extensive program of consultation has taken place. During the PPTA fact-finding stage, a stakeholder analysis was carried out to identify the major important stakeholders, their interests in the proposed Program, their perceptions of current problems related to safety and security associated with aerodrome operations, passenger terminal logistics and civil aviation services, and the resources they could bring to the achievement of goals and objectives of the program. Meetings have been held at the national level with CAA, Ministry of Transport (MOT), Dept of National Planning and Monitoring, Dept of Treasury, Air Niugini Airlines, Airlines of PNG, PNG Air Services Ltd, PNG Airports Ltd, Australian Aid for International Development (AusAID), Transport Sector Support Program (TSSP).
During Project Implementation There is continuing dialogue and consultation with all stakeholders through the Project Steering Committee Meetings held semi-annually. Regular monthly meetings are also held between the Executing Agency and PIU staff of ADB Country Office parallel to consulatations held at higher level and lower levels of the Government bureacracy associated with the project.
Business Opportunities
Consulting Services Supervising consultants for detailed design and construction supervision -- Beca International was engaged as successful bidder and are supervising design for Tranche 2 of the MFF program.
Procurement

1. Jackson Domestic Airport Parking Apron extension: Construction underway.

2. Security fences - Kavieng Security Fencing completed. Other Security Fencing (Gurney, Hoskins,Goroka and Wewak) currently under construction.

3. Equipment: ILS for Port Moresby Jacksons International Airport completed and commissioned.

Responsible ADB Officer Villareal, Maria Theresa J.
Responsible ADB Department Pacific Department
Responsible ADB Division Papua New Guinea Resident Mission (PNRM)
Timetable
Concept Clearance 28 May 2009
Fact Finding 18 May 2009 to 03 Jun 2009
MRM 15 Jul 2009
Approval 24 Nov 2009
Last Review Mission -
Last PDS Update 21 Mar 2013

MFF Facility Concept 0039-PNG

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 565.00 Cumulative Contract Awards
ADB 480.00 - 0.00 0.00 %
Counterpart 85.00 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Civil Aviation Development Investment Program: Tranche Report Tranche Reports Sep 2019
Civil Aviation Development Investment Program Facility Administration Manual Oct 2010
Civil Aviation Development Investment Program Procurement Plans Oct 2009
Civil Aviation Development Investment Program Reports and Recommendations of the President Oct 2009

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Civil Aviation Development and Investment Program Environmental Assessment and Review Framework Dec 2009

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
BEING CONTRACT FOR MT. HAGEN AIRPORT PAVEMENT STRE NGHTHENING AND RUNWAY EXTENSION. Loan 3497 23 Oct 2017 ESSAR PROJECTS (INDIA) LIMITED | OFF BANDRA KURLA COMPLEX, L.B.S MARG, KULA (W), MUMBAI 400070, INDIA INDIA National Airports Corporation 38,633,467.00 6,690,091.00

Procurement Plan

Title Document Type Document Date
Civil Aviation Development Investment Program Procurement Plans Oct 2009