Papua New Guinea : Civil Aviation Development Investment Program, Tranche 3

Sovereign Project | 43141-044

The Tranche 3 will continue from Tranches 1 and 2, to establish a sustainable civil aviation network to support the economic growth of the country. Tranche 3 will further strengthen and sustain the operations of National Airports Cooperation (NAC), PNG Air Services Limited (PNG ASL), and Civil Aviation Safety Authority of PNG (CASAPNG). The national airports have low level of compliance with safety and security standards, creating risks of accidents and illegal movements of people and goods. The air-side runway pavements, terminal buildings and utilities are in poor condition.Tranche 3 will improve and upgrade nine national airports including pavement strengthening, runway extensions, security fencing, apron extensions, fire stations, traffic control tower and terminal buildings. In addition, runway lights at seven airports, runway security fencing at three other airports and new market sheds will be constructed for women to promote local artifacts.

Project Details

  • Project Officer
    Khpalwan, Bashirullah
    Pacific Department
    Request for information
  • Country/Economy
    Papua New Guinea
  • Modality
  • Sector
    • Transport
Project Name Civil Aviation Development Investment Program, Tranche 3
Project Number 43141-044
Country / Economy Papua New Guinea
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3496-PNG: Civil Aviation Development Investment Program, Tranche 3
Ordinary capital resources US$ 213.00 million
Loan 3497-PNG: Civil Aviation Development Investment Program, Tranche 3
Asian Development Fund US$ 35.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Private sector development
Sector / Subsector

Transport / Air transport

Gender Effective gender mainstreaming
Description The Tranche 3 will continue from Tranches 1 and 2, to establish a sustainable civil aviation network to support the economic growth of the country. Tranche 3 will further strengthen and sustain the operations of National Airports Cooperation (NAC), PNG Air Services Limited (PNG ASL), and Civil Aviation Safety Authority of PNG (CASAPNG). The national airports have low level of compliance with safety and security standards, creating risks of accidents and illegal movements of people and goods. The air-side runway pavements, terminal buildings and utilities are in poor condition.Tranche 3 will improve and upgrade nine national airports including pavement strengthening, runway extensions, security fencing, apron extensions, fire stations, traffic control tower and terminal buildings. In addition, runway lights at seven airports, runway security fencing at three other airports and new market sheds will be constructed for women to promote local artifacts.
Project Rationale and Linkage to Country/Regional Strategy Civil aviation (i) supports the social and economic development of Papua New Guinea (PNG) by providing safe, efficient, reliable and sustainable aviation services and infrastructure; (ii) gives all-weather access to the country and improves the mobility of communities; and (iii) provides access to noncommercial destinations, thereby meeting important service obligations to the community. Capacity constraints and deteriorating infrastructure, however, threaten the safety and security certification of airports and place these objectives at risk. The NAC has a sector development plan for dealing with the risks but requires support to carry out the plan and meet its obligations to rehabilitate and upgrade the national airports and support their certification that will advance the Medium Term Development Strategy objectives of economic growth, poverty reduction, and human resource development.
Impact

To achieve economic growth and poverty reduction in project areas.

Project Outcome
Description of Outcome

Safe, more efficient, and more accessible all-weather air transport services in project areas.

Progress Toward Outcome Procurement is ongoing for contract packages under the tranche. The Momote Airport Pavement Upgrade and Terminal Building and Mt. Hagen Pavement Strengthening and Upgrade both procured under advance contracting are now under construction. Since January 2018, ADB has approved and awarded five (5) more packages under the tranche; for Gurney and Mendi Airport Upgrades and a fencing package comprising 3 contracts for Kerema, Kiunga and Tari. Gurney works have commenced while Mendi Airport Upgrade is still awaiting mobilization of the contractor who has been delayed due to political unrest at the project location. The three (3) fencing contracts are at present also preparing to mobilize to the respective sites. The remaining packages under the tranche (5 Works, 1 Goods and Consulting Services) are at various stages of procurement. ADB on 18 September issued approval of the BER for Vanimo Airport Runway Extension. Contract signing is anticipated around October 2018. A revised procurement plan submitted by the EA is currently being reviewed for approval. The EA has excluded the scope for the airfield lighting system and replaced the Buka Airport upgrade with a new works package for Wapenamanda Airport New Terminal Building and Associated Works. The revised procurement plan will be submitted for approval in PRS once finalized.
Implementation Progress
Description of Project Outputs

Reformed Institutions - Sustainable and focused operational units for airports, air traffic services, and regulatory oversight established

Improved Infrastructure - Airside infrastructure safety and security certification requirements met

Improved operations - Airport maintenance practices improved and runway lights for safe night landing operations introduced to meet airline safety requirements.

Status of Implementation Progress (Outputs, Activities, and Issues)

1. The three entities, NAC, PNGASL and CASAPNG are getting ongoing support under the investment program on improving airport facilities and institutional capacity development to strengthen their regulatory roles.

2. Procurement is ongoing for contract packages for airport covered under this tranche and will comply to ICAO standards by 2019 when these contracts are fully completed.

3. The investment program is assisting in the ongoing upgrade of the existing infrastructures to improve airport operations. Tranche 3 has 12 contract packages; 10 for airport works upgrade and 1 for airport lighting system and Consulting Services. Four of the works packages and a fencing package (split into 3 contracts) have been awarded while the remaining packages are at different stages of procurement.

Geographical Location Nation-wide
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects Proposed airport improvements will not result in any significant adverse environmental impact. All potential environmental impacts can be adequately mitigated and managed, and will be monitored. In accordance with the environmental assessment and review framework prepared for the investment program, an IEE, incorporating an environmental management and monitoring plan, has been prepared for each subproject sites.
Involuntary Resettlement

Airport upgrades will be done in nine existing state-owned airport facilities. Additional land will be required for three airport sites with runway extension for the two sites extending to customary-owned lands while the other site in state-owned land. Overall expected impacts include a total of nine households (30 affected persons) directly affected to be physically displaced and loss of crops and trees constituting less than 10% of the productive assets of the affected persons. Another 511 AP will be indirectly impacted through the loss of customary land and the clans that will release their land to NAC for airport extension. These APs will be compensated as per the approved Resettlement Plans (RPs). A Due Diligence Report was also prepared to confirm sites without any anticipated impacts. Consultations were undertaken with the affected persons and key stakeholders including disclosure of RPs and will be further consulted during implementation.

Indigenous Peoples Contracts in Tranche 3 are not expected to have any adverse impact on, or target any, distinct or vulnerable ethnic or tribal group. All subprojects will be implemented in a culturally appropriate and participatory manner.
Stakeholder Communication, Participation, and Consultation
During Project Design Tranche 3 will continue from Tranches 1 and 2. Periodic financing Request was submitted by GoPNG in June 2016. The GOPNG has assured ADB that implementation of Tranche 3 shall conform to all applicable ADB policies and procedures including those concerning anticorruption measures, safeguards, gender, procurement, consulting services, and disbursement as described in detail in the FAM and loan documents.
During Project Implementation A contract package for Momote Airport Aircraft Pavement Upgrade and New Terminal building was awarded by ADB under advance procurement and the contract was signed on 19 December 2016. The works on the contract has commenced. Tranche 3 loan agreements was signed on 02 March 2017. Quarterly Project Steering Committee meetings are held to ensure constant dialogue with stakeholders to resolve any major implementation issues.
Responsible ADB Officer Khpalwan, Bashirullah
Responsible ADB Department Pacific Department
Responsible ADB Division Papua New Guinea Resident Mission (PNRM)
Executing Agencies
National Airports Corporation
Timetable
Concept Clearance -
Fact Finding -
MRM 11 Aug 2016
Approval 08 Dec 2016
Last Review Mission -
Last PDS Update 28 Sep 2018

Loan 3496-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
08 Dec 2016 02 Mar 2017 25 May 2017 31 Dec 2018 24 Nov 2021 27 Apr 2022
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 240.00 Cumulative Contract Awards
ADB 213.00 07 Aug 2022 210.98 0.00 100%
Counterpart 27.00 Cumulative Disbursements
Cofinancing 0.00 07 Aug 2022 210.98 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory

Loan 3497-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
08 Dec 2016 02 Mar 2017 25 May 2017 31 Dec 2018 24 Nov 2021 27 Apr 2022
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 35.00 Cumulative Contract Awards
ADB 35.00 07 Aug 2022 34.61 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 07 Aug 2022 34.61 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Civil Aviation Development Investment Program, Tranche 3: Audited Project Financial Statements (January-December 2021) Audited Project Financial Statements Jun 2022
Civil Aviation Development Investment Program, Tranche 3: Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Jun 2021
Civil Aviation Development Investment Program, Tranche 3: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Feb 2021
Amendment to the Loan Agreement for Loan 3496-PNG: Civil Aviation Development Investment Program - Project 3 Loan Agreement (Ordinary Resources) Oct 2019
Amendment to the Loan Agreement for Loan 3497-PNG: Civil Aviation Development Investment Program - Project 3 Loan Agreement (Special Operations) Oct 2019
Civil Aviation Development Investment Program, Tranche 3: Audited Project Financial Statements (January-December 2018) Audited Project Financial Statements Jun 2019
Amendment to the Loan Agreement for Loan 3496-PNG: Civil Aviation Development Investment Program - Project 3 Loan Agreement (Ordinary Resources) Aug 2018
Project Agreement for Loans 3496-3497 PNG: Civil Aviation Development Investment Program - Project 3 Project/Program Agreements Mar 2017
Loan Agreement (Ordinary Operations) for Loan 3496-PNG:Civil Aviation Development Investment Program - Project 3 Loan Agreement (Ordinary Resources) Mar 2017
Loan Agreement (Special Operations) for Loan 3497-PNG: Civil Aviation Development Investment Program - Project 3 Loan Agreement (Special Operations) Mar 2017
Civil Aviation Development Investment Program, Tranche 3: Periodic Financing Request Report Periodic Financing Request Reports Dec 2016
Civil Aviation Development Investment Program, Tranche 3: Design and Monitoring Framework Design and Monitoring Frameworks Dec 2016
Civil Aviation Development Investment Program, Tranche 3: Summary Poverty Reduction and Social Srategy Summary Poverty Reduction and Social Strategies Dec 2016
Civil Aviation Development Investment Program, Tranche 3: Facility Administration Manual Facility Administration Manual Dec 2016
Civil Aviation Development Investment Program, Tranche 3: Procurement Plan Procurement Plans Dec 2016
Civil Aviation Development Investment Program, Tranche 3: Gender Action Plan Gender Action Plans Dec 2016
Sivel Eviesen Divelopmen Invesmen Program, Trens 3: Projek Rekot Pepa Translated PDS Sep 2016

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (July-December 2022) Social Monitoring Reports Feb 2023
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2022) Environmental Monitoring Reports Feb 2023
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (January-June 2022) Social Monitoring Reports Jul 2022
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (January-June 2022) Environmental Monitoring Reports Jul 2022
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports Apr 2022
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (July-December 2021) Social Monitoring Reports Apr 2022
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (January-June 2021) Social Monitoring Reports Jul 2021
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (January-June 2021) Environmental Monitoring Reports Jul 2021
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Mar 2021
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (July-December 2020) Social Monitoring Reports Mar 2021
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (January-June 2020) Environmental Monitoring Reports Aug 2020
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (January-June 2020) Social Monitoring Reports Aug 2020
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (January-June 2019) Environmental Monitoring Reports May 2020
Civil Aviation Development Investment Program – Tranches 2 and 3: Social Monitoring Report (July-December 2019) Social Monitoring Reports Mar 2020
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2019) Environmental Monitoring Reports Mar 2020
Civil Aviation Development Investment Program, Tranches 2 and 3: Social Monitoring Report (January-June 2019) Social Monitoring Reports Oct 2019
Civil Aviation Development Investment Program, Tranches 2 and 3: Social Monitoring Report (July-December 2018) Social Monitoring Reports Oct 2019
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2018) Environmental Monitoring Reports Mar 2019
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
Civil Aviation Development Investment Program - Tranches 2 and 3: Environmental Monitoring Report (July-December 2017) Environmental Monitoring Reports Feb 2018
Civil Aviation Development Investment Program - Tranches 2 and 3: Social Monitoring Report (July-December 2017) Social Monitoring Reports Feb 2018
Civil Aviation Development Investment Program, Tranche 3: Social Monitoring Report (January-June 2017) Social Monitoring Reports Jul 2017
Civil Aviation Development Investment Program, Tranche 3: Madang Airport Updated Initial Environmental Examination Environmental Assessment and Measures Jul 2017
Civil Aviation Development Investment Program, Tranche 3: Wewak Airport Updated Initial Environmental Examination Environmental Assessment and Measures Jul 2017
Civil Aviation Development Investment Program - Project 3: Social Monitoring Report (July-December 2016) Social Monitoring Reports Jan 2017
Civil Aviation Development Investment Program, Tranche 3: Initial Environmental Examination Initial Environmental Examination Jun 2016
Civil Aviation Development Investment Program (Tranche 3): Resettlement Plan Resettlement Plans Jun 2016
Civil Aviation Development Investment Program (Tranche 3): Resettlement Due Diligence Report Safeguards Due Diligence Reports Jun 2016

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Financial Management Specialist Individual - Consulting Closed
Design & Supervision Consultant Firm - Consulting Closed
Design Consultant for Control Tower and ATM Equipment Firm - Consulting Closed
Procurement Specialist Individual - Consulting Closed
Aeronautical Charges Specialist Individual - Consulting Closed
Aviation Safety Management (SMS) / Quality Management System (QMS) Specialist Individual - Consulting Closed
Airport Commercial Advisor Individual - Consulting Closed
Aviation Security Specialist Individual - Consulting Closed
Legislative Drafting Specialist Individual - Consulting Closed
Pavement/Materials Engineer Individual - Consulting Closed
CAD Designer Individual - Consulting Closed
Airport Civil Design Engineer Individual - Consulting Closed
3496/3497 – Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-32-2A1] Invitation for Bids Closed
3496/3497-PNG: Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-45-2B1] Invitation for Bids Closed
Contract Management Specialist Individual - Consulting Closed
Construction Supervision Consultant Firm - Consulting Closed
Team leader: Airport Procurement, Training & Maintenance Individual - Consulting Closed
3496/3497-PNG: Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-21-2A1] Invitation for Bids Closed
3496/3497-PNG: Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-20-2A1] Invitation for Bids Closed
3496/3497–Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-32-2A1] Invitation for Bids Closed
Civil Construction Supervisor Individual - Consulting Closed
Building Construction Supervisor Individual - Consulting Closed
Senior Architect Individual - Consulting Closed
Senior Construction Supervision Engineer Individual - Consulting Closed
Financial Management Specialist Individual - Consulting Closed
Loan Nos. 3496/3497-PNG: Civil Aviation Development Investment Program – Tranche 3 [CADIP-B3-23-2A1] Invitation for Bids Closed
Loan No. 3496/3497: Civil Aviation Development Investment Program - Tranche 3 [CADIP-B3-41-2A1] Invitation for Bids Closed
L3497 / 3496 -PNG: Civil Aviation Development Investment Program - Tranche 3[CADIP-B3-MND-2A1 Aircraft Pavement Strengthening, New Terminal Building and Associated Works at Mendi Airport, Southern Highlands Province, Papua New Guinea] Invitation for Bids Closed
43141-044-Civil Aviation Development Investment Program – Project 3 Advance Notice Archived

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
AVIATION SECURITY SPEIALIST INTERNATIONAL. Loan 3496 24 Sep 2021 SHANNON WANDMAKER | BRISBANE QLD AUSTRALIA National Airports Corporation 464,600.00 337,800.00
NAC AIRPORT COMMERCIAL ADVISOR. Loan 3496 24 Sep 2021 STEPHEN PRASSER | QLD AUSTRALIA 4556 National Airports Corporation 343,600.00 343,600.00
Consultancy Services for the Design of Control Towers and ATM Equipment at Port Moresby & Goroka Airports. Loan 3496 30 Jul 2021 EGIS AVIA SA | 15 avenue du Centre CS 20538 Guyancourt 78286 Saint-Quentin-en-Yveliness Cedex FRANCE National Airports Corporation 1,199,983.00 1,199,983.00
AVIATION SECURITY SPEIALIST INTERNATIONAL. Loan 3496 04 Aug 2020 SHANNON WANDMAKER | BRISBANE, QLD AUSTRALIA National Airports Corporation 126,800.00 126,800.00
NAC AERONAUTICAL CHARGES SPECIALIST. Loan 3496 04 Aug 2020 GONZALO EMILIO IBARRA | SINGAPORE SINGAPORE National Airports Corporation 140,800.00 140,800.00
NAC AIRPORT COMMERCIAL ADVISOR. Loan 3496 04 Aug 2020 STEPHEN PRASSER | QLD, AUSTRALIA 4556 AUSTRALIA National Airports Corporation 159,600.00 159,600.00
LEGISLATIVE DRAFTING SPECIALIST INTERNATIONAL FOR NAC. Loan 3496 04 Aug 2020 IRINA NIKOLAEVNA KIREEVA-DUDLEY | B1140, BELGIUM BELGIUM National Airports Corporation 164,510.00 164,510.00
AVIATION SMS/QMS SPECIALIST WITH CADIP, NAC. Loan 3496 07 Jul 2020 JOHN POTTINGER | VANCOUVER, CANADA CANADA National Airports Corporation 144,800.00 144,800.00
PAVEMENT MATERIALS ENGINEER FOR NAC/CADIP. Loan 3496 04 Mar 2020 AKM SHAHID ULLAH | BARANGAY SAN ANTONIO, PASIG CITY METRO MANILA PHILIPPINES National Airports Corporation 280,000.00 280,000.00
CONSTRUCTION SUPERVISION CONSULTANCY SERVICES TO N AC CADIP PROJECT. Loan 3496 04 Feb 2020 KOREA ENGINEERING CONSULTANTS CORPORATION | SANGIL-RO 6-GIL, GANGDONG-GU SEOL,05288, KOREA KOREA, REPUBLIC OF National Airports Corporation 4,470,961.18 4,470,961.18
TEAM LEADER, AIRPORT PROCUREMENT, TRAINING AND MAINTENANCE. Loan 3496 04 Mar 2019 DESMOND A. FEIL | KOMP KOSAMBI BARU JAKARTA BARAT INDIA National Airports Corporation 171,000.00 171,000.00
BEING REIMBURSEMENT CLAIMS. Loan 3496 22 Jun 2019 NATIONAL AIRPORTS CORPORATION | BOROKO NCD PAPUA NEW GUINEA National Airports Corporation 295,400.03 295,400.03
BEING REIMBURSEMENT CLAIMS. Loan 3496 22 Jun 2019 ACCIDENT INVESTIGATION COMMISSION | BOROKO NCD PAPUA NEW GUINEA National Airports Corporation 147,700.02 147,700.02
BEING CONTRACT FOR AIRPORT OPERATIONS SPECIALIST. Loan 3496 11 Jul 2019 ROBERT PARKINSON | AUCKLAND, 0931 NEW ZEALAND National Airports Corporation 290,000.00 290,000.00
GEOTECHNICAL INVESTIGATIONS AT KIETA (AROPA) AIRPO RT, AROB. Loan 3496 30 Oct 2019 GEOSTRATA ENGINEERING LTD | BOROKO NCD PAPUA NEW GUINEA National Airports Corporation 100,944.45 100,944.45
BEING CONTRACT FOR CONTRACT MANAGEMENT SPECIALIST. Loan 3496 14 Nov 2019 SANGARAPILLAI SUNTHARESAN | NEW SOUTH WALES,2136 AUSTRALIA National Airports Corporation 290,000.00 290,000.00
VANIMO AIRPORT RUNWAY EXTENSION, NEW TERMINAL BUIL DING AND ASSOCIATED WORKS. Loan 3496 21 Nov 2018 CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP | BUILDING 1, NOBLE CENTRE NO. 128, WEST S ECTION OF SOUTH 4TH RING ROAD, BEIJING CHINA,PEOPLE'SREP.OF National Airports Corporation 10,676,929.00 7,858,220.00
MADANG AIRPORT PAVEMENT UPGRADE, NEW TERMINAL BUIL DING AND ASSOCIATED WORKS. Loan 3497 21 Nov 2018 ESSAR PROJECTS (PNG) LTD/HBS (PNG) LTD | LAE, MOROBE PROVINCE INDIA National Airports Corporation 23,017,736.00 4,005,086.00
WEWAK AIRPORT RUNWAY EXTENSION, NEW TERMINAL BUILD ING AND ASSOCIATED WORKS. Loan 3497 21 Nov 2018 CHINA SHENYANG INTERNATIONAL ECONOMIC & TECHN | P O BOX 1037, WAIGANI, NCD CHINA,PEOPLE'SREP.OF National Airports Corporation 15,118,039.00 2,630,539.00
WAPENAMANDA AIRPORT PAVEMENT UPGRADE, NEW TERMINAL BUILDING AND ASSOCIATED WORKS. Loan 3497 21 Nov 2018 LORMA CONSTRUCTION LTD/SOCO JV | NCD PAPUA NEW GUINEA National Airports Corporation 11,453,210.00 1,992,859.00
VANIMO AIRPORT RUNWAY EXTENSION, NEW TERMINAL BUIL DING AND ASSOCIATED WORKS. Loan 3497 21 Nov 2018 CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP | BUILDING 1, NOBLE CENTRE NO. 128, WEST S ECTION OF SOUTH 4TH RING ROAD, BEIJING CHINA,PEOPLE'SREP.OF National Airports Corporation 10,676,929.00 1,857,786.00
MADANG AIRPORT PAVEMENT UPGRADING, NEW TERMINAL BU ILDING & ASSOCIATED WORKS. Loan 3496 21 Nov 2018 ESSAR PROJECTS (PNG) LTD/HBS (PNG) LTD JV | MOROBE PROVINCE INDIA National Airports Corporation 23,017,736.00 16,941,054.00
WEWAK AIRPORT RUNWAY EXTENSION, NEW TERMINAL BUILD ING AND ASSOCIATED WORKS. Loan 3496 21 Nov 2018 CHINA SHENYANG INTERNATIONAL ECONOMIC & TECHN | P O BOX 1037, WAIGANI, NCD CHINA,PEOPLE'SREP.OF National Airports Corporation 15,118,039.00 11,126,876.00
WAPENAMANDA AIRPORT PAVEMENT UPGRADE, NEW TERMINAL BUILDING AND ASSOCIATED WORKS. Loan 3496 21 Nov 2018 LORMA CONSTRUCTION LTD/SOCO JV | NCD PAPUA NEW GUINEA National Airports Corporation 11,453,210.00 8,429,563.00
BEING CONTRACT FOR FINANCIAL MANAGEMENT SPECIALIST FOR CADIP. Loan 3496 18 Oct 2018 BHASHKAR BHINDIE | NORTHRIDGE, CA 91325 UNITED STATES UNITED STATES National Airports Corporation 235,897.00 235,897.00
BEING CONTRACT FOT CIVIL CONSTRUCTION SUPERVISOR. Loan 3496 04 Oct 2018 RAMESH CHAND VISHWAKARMA | P O BOX 4422, FUJAIRAH/DUBAI, UAE. INDIA National Airports Corporation 107,487.00 107,487.00
BEING CONTRACT FOR KEREMA AIRPORT SECURITY FENCING INSTALLATION AND ASSOCIATED WORKS. Loan 3496 26 Sep 2018 JEPHTAH CONSTRUCTION LIMITED | WAIGANI, NCD PAPUA NEW GUINEA National Airports Corporation 2,332,836.00 1,705,520.00
BEING CONTRACT FOR TARI AIRPORT SECURITY FENCING I NSTALLATION AND ASSOCIATED WORKS. Loan 3496 26 Sep 2018 HELA OPENE INVESTMENT LIMITED | MENDI, SHP PAPUA NEW GUINEA National Airports Corporation 2,150,306.00 1,572,074.00
BEING CONTRACT FOR KIUNGA SECURITY FENCING AND ASS OCIATED WORKS. Loan 3497 27 Sep 2018 SAMSUNG HOME ENGINEERING AND CONST (E&C) COMP | SEOCHO-GU, SEOUL KOREA, REPUBLIC OF National Airports Corporation 2,433,423.00 420,593.00
BEING CONTRACT FOR KEREMA AIRPORT SECURITY FENCING INSTALLATION AND ASSOCIATED WORKS. Loan 3497 26 Sep 2018 JEPHTAH CONSTRUCTION LIMITED | WAIGANI, NCD PAPUA NEW GUINEA National Airports Corporation 2,317,283.00 403,207.00
BEING CONTRACT FOR TARI AIRPORT SECURITY FENCING I NSTALLATION AND ASSOCIATED WORKS. Loan 3497 26 Sep 2018 HELA OPENE INVESTMENT LIMITED | MENDI, SHP PAPUA NEW GUINEA National Airports Corporation 2,150,306.00 371,659.00
BEING CONTRACT FOR BUILDING CONSTRUCTION SUPERVISO R FOR CADIP. Loan 3496 21 Sep 2018 MARK JASON VILLANUEVA | P O BOX PORT MORESBY NCD PHILIPPINES National Airports Corporation 100,000.00 100,000.00
BEING CONTRACT FOR SENIOR ARCHITECT INTERNATIONAL. Loan 3496 29 Aug 2018 FERNANDO RAMON PRIETO | SUIT 200, LAKE WORTH FLORIDA UNITED STATES National Airports Corporation 247,310.00 247,310.00
BEING CONTRACT FOR CONSTRUCTION SUPERVISION ENGINE ER. Loan 3496 29 Aug 2018 GRAHAM WALTER MOODY | QUEENSLAND AUSTRALIA National Airports Corporation 200,000.00 200,000.00
BEING CONTRACT FOR MENDI AIRPORT AIRCRAFT PAVEMENT STRENGTHENING, NEW TERMINAL BUILDING AND ASSOCIAT ED WORKS. Loan 3496 06 Jun 2018 SYNOHYDRO CORPORATION LIMITED | HAIDAN DISTRICT, BEIJING, 100048 CHINA,PEOPLE'SREP.OF National Airports Corporation 8,490,713.00 6,198,193.00
BEING CONTRACT FOR MENDI AIRPORT AIRCRAFT PAVEMENT STRENGTHENING, NEW TERMINAL BUILDING AND ASSOCIAT ED WORKS. Loan 3497 06 Jun 2018 SYNOHYDRO CORPORATION LIMITED | HAIDAN DISTRICT, BEIJING, 100048 CHINA,PEOPLE'SREP.OF National Airports Corporation 8,490,713.00 1,465,334.00
BEING CONTRACT FOR GURNEY AIRPORT RUNWAY EXTENSION AND ASSOCIATED WORKS. Loan 3496 18 Apr 2018 SYNOHYDRO CORPORATION LIMITED | HAIDIAN DISTRICT, BEIJING, 100048 CHINA,PEOPLE'SREP.OF National Airports Corporation 9,423,909.00 6,935,997.00
BEING CONTRACT FOR GURNEY AIRPORT RUNWAY EXTENSION AND ASSOCIATED WORKS. Loan 3497 18 Apr 2018 SYNOHYDRO CORPORATION LIMITED | HAIDIAN DISTRICT, BEIJING, 100048 CHINA,PEOPLE'SREP.OF National Airports Corporation 9,423,909.00 1,639,760.00
BEING SALARY REIMBURSEMENT FOR CADIP PMU STAFF. Loan 3496 05 Mar 2018 CADIP PMU | BOROKO NCD PAPUA NEW GUINEA National Airports Corporation 664,697.00 662,542.00
BEING PMU COSTS REIMBURSABLES. Loan 3496 18 Oct 2017 CADIP PMU | NCD PAPUA NEW GUINEA National Airports Corporation 783,250.00 780,750.00
BEING CONTRACT FOR MT HAGEN PAVEMENT UPGRADE AND R UNWAY EXTENSION. Loan 3496 23 Oct 2017 ESSAR PROJECTS INDIA LIMITED | OFF BANDRA KURLA COMPLEX, L.B.S MARG, KULA (W), MUMBAI 400070, INDIA INDIA National Airports Corporation 38,633,467.00 28,298,314.00
Being Contract for Momote Airport Works. Loan 3496 16 Jun 2017 China Harbor Engineering Company Ltd | Ncd, China, People's Rep. of National Airports Corporation 31,233,062.00 22,987,534.00
Being Contract for Momote Works. Loan 3497 16 Jun 2017 China Harbor Engineering Company Ltd | Ncd, China, People's Rep. of National Airports Corporation 31,233,062.00 5,434,553.00

Procurement Plan

Title Document Type Document Date
Civil Aviation Development Investment Program, Tranche 3: Procurement Plan Procurement Plans Dec 2016