Pakistan : Uch-II Power Project
The Project involves construction, erection and operation of a 404 MW low British thermal unit (BTU) combined cycle power plant adjacent to the 586 MW Uch power plant (Uch-I, operational since 2000) at Dera Murad Jamali, Balochistan, located 47 km away from the Uch gas reservoir. The Project will be developed under the 2002 Power Policy and will be undertaken according to a 25 year build-own-and-operate structure. The tariff has been approved by the National Electric Power Regulatory Authority - Pakistan's power sector regulator.
Project Details
-
Project Officer
Kim, Viktoriya
Private Sector Operations Department
Request for information -
Country/Economy
Pakistan -
Modality
-
Sector
- Energy
| Project Name | Uch-II Power Project | ||||||||||
| Project Number | 43903-014 | ||||||||||
| Borrower / Company | UCH-II POWER (PRIVATE) LIMITED |
||||||||||
| Country / Economy | Pakistan |
||||||||||
| Location | |||||||||||
| Type or Modality of Assistance |
|
||||||||||
| Strategic Agendas | Inclusive economic growth |
||||||||||
| Drivers of Change | Private sector development |
||||||||||
| Sector / Subsector | Energy / Conventional energy generation |
||||||||||
| Gender | |||||||||||
| Responsible ADB Department | Private Sector Operations Department | ||||||||||
| Responsible ADB Division | Portfolio Management Division, PSOD | ||||||||||
| Responsible ADB Officer | Kim, Viktoriya | ||||||||||
| Project Sponsor(s) | INTERNATIONAL POWER |
||||||||||
| Description | The Project involves construction, erection and operation of a 404 MW low British thermal unit (BTU) combined cycle power plant adjacent to the 586 MW Uch power plant (Uch-I, operational since 2000) at Dera Murad Jamali, Balochistan, located 47 km away from the Uch gas reservoir. The Project will be developed under the 2002 Power Policy and will be undertaken according to a 25 year build-own-and-operate structure. The tariff has been approved by the National Electric Power Regulatory Authority - Pakistan's power sector regulator. | ||||||||||
| Objectives and Scope | The Project addresses Pakistan's growing energy deficit by adding net 375.2 MW (8.9% of the forecasted energy shortfall) power generation capacity and promote higher energy efficiency in the country's power generation mix by commissioning a combined cycle power plant fueled by a low BTU gas. The Project by using domestic gas decreases reliance on imported oil and diesel fuel for power generation, thereby relieving pressure on precarious foreign exchange reserves. In addition, the Project stimulates employment and economic growth in Balochistan - Pakistan's poorest province. | ||||||||||
| Status of Development Objectives | The project's accomplishment of its target development goals has been disclosed in the Extended Annual Review Reports | ||||||||||
| Status of Operation/Construction | Commercial operations started on 4 April 2014 and the plant has been successfully operating since. | ||||||||||
| Material Changes | None | ||||||||||
| Linkage to Country/Regional Strategy | ADB's support for the Project is in line with the Pakistan Country Strategy and Program Update, Country Partnership Strategy (CPS), and the Government's strategic emphasis on energy sector development. As per the ADB CPS, ADB views itself as one of Pakistan's strategic development partners for infrastructure development, with power as one of the main areas of support, and that 'the emphasis on lending for economic infrastructure will be continued, which is consistent with the high priority attached to it in the Government's MTDF. |
| Safeguard Categories | |
|---|---|
| Environment | A |
| Involuntary Resettlement | C |
| Indigenous Peoples | C |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | The Project is housed on barren land adjacent to Uch-I, which was acquired by the sponsors from the government of Balochistan at the time of Uch-I development in the late 1990's. Principally due to its overall size, the potential environmental issues associated with this project include air emissions, water supply, site considerations, wastewater/sewage, occupational/public health and safety risk/hazards. |
| Involuntary Resettlement | The land where the project was constructed had no occupants or sign of occupancy. There are no outstanding issues with land acquisition, and Uch Power confirms that it has not received any complaints or grievances emanating from the original owners of the land. The land and surrounding areas are arid and not suitable for agriculture, with low population density. |
| Indigenous Peoples | No indigenous people are present in or are using the Project site. |
| Stakeholder Communication, Participation, and Consultation | In accordance with the national law, a notification will be placed in national and local newspapers informing the public of the intention of the proponents to develop the proposed project and the availability of the EIA of the same for public review. One month after the notice, public hearing of the EIA of the project will be conducted by the Balochistan Environmental Protection Agency during which comments of the public will be recorded and addressed, where relevant. |
| Timetable for assistance design, processing and implementation | |
|---|---|
| Concept Clearance | 29 Jan 2009 |
| Credit Committee Meeting | 05 Nov 2010 |
| Approval | 13 Dec 2010 |
| PDS Creation Date | 11 Mar 2009 |
| Last PDS Update | 30 Jun 2022 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Uch-II Power Project: Extended Annual Review Report | Extended Annual Review Reports | Dec 2020 |
| Uch-II Power Project | Initial Poverty and Social Analysis | Aug 2010 |
| Proposed Loan and Partial Risk Guarantee Uch-II Power Project | Reports and Recommendations of the President | Nov 2010 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.