Armenia : ARM: ZVARTNOTS AIRPORT EXPANSION PROJECT (PHASE 2)

Nonsovereign Project | 43922-014

Project Details

  • Project Officer
    Kondo, Shinya
    Private Sector Operations Department
    Request for information
  • Country/Economy
    Armenia
  • Modality
  • Sector
    • Transport
Project Name
ARM: ZVARTNOTS AIRPORT EXPANSION PROJECT (PHASE 2)
Project Number
43922-014
Country / Economy
  • Armenia
Location
Type or Modality of Assistance
Approval Number Facility Fund Source Amount Status
7308/2620 Loan USD 40.00 million Approved
Strategic Agendas
  • Inclusive economic growth
  • Regional integration
Drivers of Change
  • Private sector development
Sector / Subsector
  • Transport / Air transport

Gender
Project Sponsor(s)
    Description
    ARM: ZVARTNOTS AIRPORT EXPANSION PROJECT (PHASE 2)
    Objectives and Scope
    Linkage to Country/Regional Strategy

    The Project is in line with ADB's economic report and interim operational strategy 2006-2009 for Armenia as well as ADB's country operations business plan 2008-2010 for Armenia. The economic report and interim operational strategy identifies, among others, the promotion of the private sector and enhancement of regional cooperation as ADB's strategic priorities.

    The Project is consistent with two of the principles underlying the economic report and interim operational strategy: (i) being selective in determining initial operational areas and focusing on delivering swift results, and (ii) partnering with other development agencies to exploit the institutional infrastructure.

    The country operations business plan envisages transport and communications interventions, focusing on modernizing international transport corridors to enhance trade and business opportunities.

    Safeguard Categories

    Environment
    B
    Involuntary Resettlement
    A
    Indigenous Peoples
    C

    Summary of Environmental and Social Aspects

    Environmental Aspects
    Involuntary Resettlement
    Indigenous Peoples
    Stakeholder Communication, Participation, and Consultation

    Contact

    Responsible ADB Officer
    Kondo, Shinya
    Responsible ADB Division
    Infrastructure Finance Division 1 (PSIF1)
    Responsible ADB Department
    Private Sector Operations Department

    Timetable for assistance design, processing, and implementation

    Concept Clearance
    16 Jul 2009
    Credit Committee Meeting
    22 Feb 2010
    Approval
    26 Mar 2010
    PDS Creation Date
    03 Feb 2010
    Last PDS Update
    09 Sep 2014

    Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

    The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

    The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

    In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

    Title Document Type Document Date
    Zvartnots Airport Expansion Project (Phase 2) Extended Annual Review Reports Oct 2013
    Zvartnots Airport Expansion Project (Phase 2): Joint Response from ADB and EBRD Documents Produced Under Grant/Loans/TA Dec 2011
    Zvartnots Airport Expansion Project (Phase 2): Joint Response from ADB and EBRD (Armenian Translation) Documents Produced Under Grant/Loans/TA Dec 2011
    Zvartnots Airport Expansion Project (Phase 2): Letter from Residents of Buildings C and D (Armenian Translation) Documents Produced Under Grant/Loans/TA Dec 2011
    Zvartnots Airport Expansion Project (Phase 2): Letter from Residents of Buildings C and D Documents Produced Under Grant/Loans/TA Dec 2011
    Zvartnots Airport Expansion Project (Phase 2) Reports and Recommendations of the President Mar 2010
    Zvartnots Airport Terminal Expansion Phase II Initial Poverty and Social Analysis Dec 2009

    Safeguard Documents See also: Safeguards
    Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.


    Evaluation Documents See also: Independent Evaluation

    None currently available.


    Related Publications

    None currently available.


    The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

    Requests for information may also be directed to the InfoUnit.