fbpx 44482-024: Transport Network Development Investment Program - Tranche 3 | Asian Development Bank

Afghanistan: Transport Network Development Investment Program - Tranche 3

Sovereign (Public) Project | 44482-024 Status: Active

ADB is helping Afghanistan upgrade its transport network. The third tranche of the program will rebuild 178 kilometers of a national road from Dar-i-Suf to Yakawlang, which will provide an alternative north-south transit route from from Mazar-e-Sharif to Kabul. It will also improve sanitation facilities and practices in Bamyan and Samangan provinces, which particularly benefit women and children.

 
Project Name Transport Network Development Investment Program - Tranche 3
Project Number 44482-024
Country Afghanistan
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0355-AFG: Transport Network Development Investment Program - Tranche 3
concessional ordinary capital resources lending / Asian Development Fund US$ 220.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Sector / Subsector

Transport / Road transport (non-urban)

Gender Equity and Mainstreaming Effective gender mainstreaming
Description Physical interventions under Tranche 3 include 178 km of reconstructed national road from Dar-i-Suf to Yakawlang linking the roads already completed under the ADB financed North South Corridor Project. Completion of this national road provides an alternative north south transit route from Mazar-e-Sharif to Kabul from the currently overloaded Salang Tunnel, a facility which has exceeded its engineering design life and is in need of major rehabilitation if it is going to continue to function. Additionally, Tranche 3 will provide community infrastructure specifically designed to improve the lives of women and children in some of Afghanistan's poorest provinces, Bamyan and Samangan, through betterment of sanitation facilities and practices.
Project Rationale and Linkage to Country/Regional Strategy As planned in the approved facility and linked documents, Tranche 3 of the investment program builds upon the lessons learned and progress from Tranches 1 and 2, and the complementary efforts of other development partners in the sector to further improve domestic and regional connectivity while widening access to social and economic opportunities. The proposed road subproject involves the reconstruction and upgrading of approximately 178 kilometers (km) of the road section from Dar-i-Suf to Yakawlang, which has been previously identified as a priority in the Afghanistan National Development Strategy (ANDS) and subsequent national planning and implementation frameworks. The rationale for the proposed subproject include: (i) completing the North South Corridor, which is an alternative route to using the Salang Tunnel; (ii) supporting completion of CAREC Corridor 5; and (iii) completing the first stage in cross country north south road from Mazar-e-Sharif to Kandahar. After years of use and lack of periodic maintenance, the subproject road in poor condition beyond repair, thus requiring major rehabilitation. Indeed, in its current condition, the road is impassable by motorized vehicles for many months throughout the year. This state of this road is hindering economic development in the central provinces, impeding regional trade and the opening of alternative trade routes, and imposing efficiency losses as traffic volumes continue to rise. In addition to supporting the ANDS, justification of Tranche 3 stems from Afghanistan's strategic geographic center of gravity in the Central Asian region and potential to serve as the nexus between north-south and east-west regional trade corridors. Afghanistan is traversed by three major CAREC corridors, to which the proposed Tranche 3 subproject supports Corridor 5 providing landlocked Central Asian access to populous commercial centers in South Asia, and major ports in the Persian Gulf and Arabian Sea. An efficient and sustained Afghanistan road network will improve regional connectivity, support increased domestic and international trade, and generate jobs and economic growth. The proposed tranche is consistent with the envisaged outputs, outcomes, and impacts of the investment program and additionally Strategy CAREC 2020 aimed at the development of priority transport routes, increasing trade through transport connectivity, and facilitating cross-border movement of goods.
Impact Better connectivity and efficiency through a fully complete North-South Corridor
Project Outcome
Description of Outcome Rehabilitated and reconstructed sections of national and regional highways
Progress Toward Outcome The cvil works and construction supervision consultant contracts for the reconstruction of Dara-i-Suf to Yakawlang Road signed in Dec 2016 and May 2017, respectively. The Contractor mobilized on 15 May 2017. As of 30 June 2020, the physical progress was 19.22% against the target of 70.67%, while the elapsed contract period is around 82%. Due to the contractor's poor performance and the continuous non-compliance in completing the works per required schedule, the government decided to descope the contract to cover only 87 km of road in Bamyan Province, while leaving the 100 km road section in Samangan Province un-constructed and untouched. Based on mutual agreement between the Contractor and the Government, the scope of contract reduced from 186.6 km to 87 km. Submission of the signed Supplementary Agreement between the MPW and the contractor formalizing the reduction of scope is awaited.
Implementation Progress
Description of Project Outputs

87 km (Dar-i-Suf-Yakawlang section of the North-South Corridor) of reconstructed, rehabilitated, and appropriately maintained national and regional highways

Community development infrastructure

Land Acquisition and Resettlement Completed for Projects under Tranche 2 and Tranche 4 of MFF0063

Status of Implementation Progress (Outputs, Activities, and Issues)

The civil works contractor mobilized on 15 May 2017. The target year was revised from 2017 to 2021. As of 30 June 2020, achieved work is 19.22% against the planned target of 70.67% with elapsed contract period of 82%. Based on mutual agreement between the Contractor and the Government, the scope of contract was reduced from 186.6 km to 87 km. Submission of the signed Supplementary Agreement incorporating ADB's comments formalizing the reduction in contract's scope is awaited.

The Contractor submitted the Community Development (CD) Projects Proposals and Cost Estimates which was reviewed by the Engineer on 21 June 2019. The Engineer reviewed the submitted documents of CD Project Proposals and Cost Estimates comprising 39 projects and furnished comments to the Contractor in Aug 2019, since most of the previous comments/observations of the Engineer have not been fulfilled. The Contractor yet to submit the revised CD project proposals and cost estimates complying to all comments/observation of the Engineer. Meanwhile, the following preliminary measures and data for cost estimation have been undertaken in several villages in the project area: potable water pipe scheme and bore well projects, connection road of and bridge projects, Dam projects "Classroom projects" Population Wall projects.

Disbursement requirements such as estimate of expenditure sheet together with the corresponding withdrawal application is under preparation by the MPW for LARP's settlement.

Geographical Location Ahangaran, Baghalak, Bazar-e Yakawlang, Chaghcharan, Chaghcharan, Chahar Deh, Dara-I-Suf, Darah-ye Daymirdad, Deh-e Tarchi, Gardan Dewal, Gird Bayd, Hasani, Hisa-I-Awal Bihsud, Islamic Republic of Afghanistan, Kabul, Kotah, La`l wa Sar Jangal, Marghistan, Markazi Bihsud, Panjab, Qal`ah, Qal`ah Now, Rashak, Sadmardah, Safed Khak, Sar-e Bum, Surkh Joy, Yakawlang, Zayraki
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The road will not pass through any environmentally sensitive areas and rehabilitation activities will be confined with the existing ROW. The project is anticipated to have site specific environmental impacts. A further environmental assessment will re-confirm whether environment category B will be maintained.
Involuntary Resettlement Expected significant land acquisition and resettlement as defined by SPS (2009).
Indigenous Peoples N/A
Stakeholder Communication, Participation, and Consultation
During Project Design Consultation sessions were conducted with the local residents in the project affected areas. The primary issues discussed were affected land, the process of land acquisition planning, compensation, and employment opportunities for the local residents, both skilled and unskilled. The benefits of constructing the projects roads were explained. The community development subcomponent will involve collaborative decision making and empowerment elements.
During Project Implementation Consultation sessions will continue during project implementation.
Business Opportunities
Consulting Services All consulting services financed under Tranche 3 will be procured in accordance with the Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers (2013, as amended from time to time).
Procurement Procurement of all civil works, equipment and goods will be undertaken in accordance with ADB's Procurement Guidelines (2015, as amended from time to time).
Responsible ADB Officer Kailasam, Ganesh
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Transport and Communications Division, CWRD
Executing Agencies
Ministry of Public Works
Aminullah Hatam, Program Director, Project Management Office
[email protected]
First Macrorayan, Kabul,Islamic Republic of Afghanistan
Ministry of Public Works
[email protected]
First Macrorayan, Kabul,Islamic Republic of Afghanistan
Timetable
Concept Clearance -
Fact Finding -
MRM 16 Jul 2013
Approval 11 Sep 2013
Last Review Mission -
Last PDS Update 08 Dec 2020

Grant 0355-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Sep 2013 09 Nov 2013 03 Jan 2014 31 Dec 2017 20 Sep 2021 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 230.00 Cumulative Contract Awards
ADB 220.00 11 Sep 2013 0.00 0.00 0%
Counterpart 10.00 Cumulative Disbursements
Cofinancing 0.00 11 Sep 2013 91.48 0.00 48%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory - - -

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Jr. Quantity Surveyor Individual - Consulting Closed 25 Apr 2021 01 May 2021
Environmental Specialist [National] Individual - Consulting Closed 25 Apr 2021 01 May 2021
Admin/Finance Manager [National] Individual - Consulting Closed 25 Apr 2021 01 May 2021
Materials/Pavement Engineer Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Community Development Specialist [National] Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Sr. Material Pavement Engineer Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Structural/Bridge Engineer Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Sr. Quantity Surveyor Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Contract Specialist Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Site Inspector (4 positions) Individual - Consulting Closed 19 Mar 2021 25 Mar 2021
Materials/Pavement Engineer Individual - Consulting Closed 19 Mar 2021 25 Mar 2021

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
RESETTLEMENT COSTS FOR T4 BAHARAK-ESKHASHIM Grant 0355 11 Oct 2020 VARIOUS VARIOUS AFGHANI. IS. REP. OF Ministry of Public Works 8,154,908.00
LAND ACQUISITION AND RESETTLEMENT COST T2 - SAPARY-SURKHROD SECTION 1A Grant 0355 11 Oct 2020 VARIOUS VARIOUS AFGHANI. IS. REP. OF Ministry of Public Works 27,045,092.00
RECONSTRUCTION OF DARA-I-SUF TO YAKAWLANG ROAD_(87 KM) Grant 0355 04 Aug 2020 CHINA ROAD AND BRIDGE CORPORATION ZHONGLU PLAZA C88 ANDINGMENWAI DAJIE BEIJING CHINA PEOPLE'SREP.OF Ministry of Public Works 93,285,426.00
Construction Supervision of the Reconstruction and Rehabilitation of North South Corridor Road Project Grant 0355 15 May 2017 Sheladia Associates Inc. 15825 Shady Grove Road Suite 100 Rockville Md United States Ministry of Public Works Construction Supervision of the Reconstruction and Rehabilitation of North South Corridor Road Project 8,786,627.00
Construction Supervision Of The Reconstruction And Rehabilitation Of North South Corridor Road Proj Grant 0355 15 May 2017 Sheladia Associates Inc. 15825 Shady Grove Road Suite 100 Rockville Md United States Ministry Of Public Works 8,786,627.00