Viet Nam: Public Private Partnership Support Project

Sovereign (Public) Project | 44507-002 Status: Active

ADB is supporting the development of bankable and commercially viable public-private partnerships (PPP) in Viet Nam. A project development facility will be established to fund preparatory work for proposed PPP projects, which include pre-feasibility studies, feasibility studies, and the engagement of advisors.  The enabling framework and institutional capacity for PPPs will also be strengthened.

Project Details

Project Officer
Dao Viet, Dung Southeast Asia Department Request for information
Country
  • Viet Nam
Modality
  • Loan
Sector
  • Public sector management
 
Project Name Public Private Partnership Support Project
Project Number 44507-002
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 8273-VIE: Public-Private Partnership Support Project --Additional Cofinancing
Agence Francaise de Developpement US$ 10.00 million
Loan 2920-VIE: Public-Private Partnership Support Project
concessional ordinary capital resources lending / Asian Development Fund US$ 20.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Private sector development
Sector / Subsector

Public sector management / Public administration

Gender Equity and Mainstreaming No gender elements
Description The project entails the use of an ADF project loan of $20 million to fund the establishment of a Project Development Facility (PDF) that would help bring bankable PPP projects to the market. The PDF would be used by government ministries / project sponsors to fund PPP project preparation activities which include pre-feasibility studies, full feasibility studies and the engagement of transaction advisors who would structure deals to bring to the private sector for bidding.
Project Rationale and Linkage to Country/Regional Strategy
Impact Increased private sector investment in infrastructure
Project Outcome
Description of Outcome Improved government capacity to catalyze PPPs and infrastructure investments
Progress Toward Outcome

Institutional framework to support PPP program has been developed with the issuance of a Decree 15.

Selection criteria for PPP projects has been developed.

5 PPP flagship PPP projects including 4 North South Expressway sub-projects and an E-Government procurement project. Selection of investor for E-GP project completed. Transaction advisory service for 4 North South Expressway sub-projects is under implementation. Shortlisting of investors for those sub-projects is expected to be approved in Feb. 2020.

Implementation Progress
Description of Project Outputs

Institutional Mechanisms for Developing Bankable PPP Projects Established

Strengthened PPP Enabling Framework and improved institutional capacity for PPP

Status of Implementation Progress (Outputs, Activities, and Issues)

completed

A shortlist of 18 PPP projects

has been finalized.

5 PPP flagship PPP projects including 4 North South Expressway sub-projects and an E-Government procurement project. Selection of investor for E-GP project completed. Transaction advisory service for 4 North South Expressway sub-projects is under implementation. Shortlisting of investors for those sub-projects is expected to be approved in Feb. 2020.

A medium term capacity building has been developed

PPP Steering Committee has been established under the chairmanship of a Deputy Prime Minister

Decree 15 on PPP and Decree 30 on investor selection were issued in 2015.

PDF guideline was issued in April 2017

A decree 15 on PPP has provision on SOE participation.

Geographical Location Nation-wide
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design none
During Project Implementation
Business Opportunities
Consulting Services Two consulting firms have been engaged the technical firm and the legal firm to assist the PPP Office in implementation of Output 1 on (i) strengthened public private partnership (PPP) enabling framework and improved capacity for PPP; and (ii) the establishment of a PDF as an institutional mechanism for developing bankable PPP projects.
Responsible ADB Officer Dao Viet, Dung
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
Ministry of Planning and Investment
6 B Hoang Dieu street, Ba Dinh district, Hanoi, Viet Nam
Timetable
Concept Clearance 15 Feb 2012
Fact Finding 27 Feb 2012 to 02 Mar 2012
MRM 23 May 2012
Approval 25 Oct 2012
Last Review Mission -
Last PDS Update 06 Feb 2020

Loan 2920-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Oct 2012 17 Jan 2013 28 May 2013 30 Jun 2019 31 Mar 2020 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 22.90 Cumulative Contract Awards
ADB 20.00 25 Oct 2012 3.66 0.00 20%
Counterpart 2.90 Cumulative Disbursements
Cofinancing 0.00 25 Oct 2012 1.60 0.00 9%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Unsatisfactory - Unsatisfactory

Loan 8273-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Jul 2012 09 Apr 2013 09 Apr 2013 30 Jun 2018 31 Mar 2020 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 10.00 Cumulative Contract Awards
ADB 0.00 11 Jul 2012 0.00 2.03 22%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 10.00 11 Jul 2012 0.00 0.95 10%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Unsatisfactory - Unsatisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
TECHNICAL ASSISTANCE FOR THE EASTERN NORTH-SOUTH EXPRESSWAY CONSTRUCTION PROJECT (NGHI SON-DIEN CHAU AND DIEN CHAU-BAI VOT SECTIONS0 Loan 2920 30 Jul 2019 JV ERNST & YOUNG SOLUTIONS LLP (SINGAPORE) 1 RAFFLES QUAY, 318-01, SINGAPORE 048583 SINGAPORE Ministry of Planning and Investment CONSULTANCY 595,115.91 594,893.51
TECHNIAL ASSISTANCE FOR NORTH-SOUTH EXPRESSWAY IN THE EAST CONSTRUCTION PROJECT: MAI SON - NATION AL HIGHWAY 45 - NGHI SON SECTIONS Loan 2920 11 Jan 2019 DELOITTE TOUCHE TOHMATSU INDIA LLP 7TH FLOOR, BUILDING 10, TOWER B DLF CYBER CITY COMPLEX, DLF CITY PHASE 2 INDIA Ministry of Planning and Investment CONSULTANCY 439,618.84 439,596.49

Procurement Plan

Title Document Type Document Date
Public-Private Partnership Support Project Procurement Plans Sep 2013