China, People's Republic of : Hubei-Yichang Sustainable Urban Transport Project
The Hubei-Yichang Municipal Government proposes a project with the following components: (i) road reconstruction and installation of bus rapid transit (BRT) corridor (18 kilometers [km]), (ii) establishing BRT services; (iii) construction of two road sections (24.7 km) to support logistics park development and to accommodate increasing pass-dam transshipment demand; and (iv) support for non-motorized transport (NMT), travel demand management (TDM) in Yichang central business district (CBD) through parking management.
Project Details
-
Project Officer
Pettersson, Anders
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Modality
-
Sector
- Transport
Related Projects
Project Name | Hubei-Yichang Sustainable Urban Transport Project | ||||
Project Number | 45023-002 | ||||
Country / Economy | China, People's Republic of |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming |
||||
Sector / Subsector | Transport / Road transport (non-urban) - Transport policies and institutional development - Urban public transport |
||||
Gender | Effective gender mainstreaming | ||||
Description | The Hubei-Yichang Municipal Government proposes a project with the following components: (i) road reconstruction and installation of bus rapid transit (BRT) corridor (18 kilometers [km]), (ii) establishing BRT services; (iii) construction of two road sections (24.7 km) to support logistics park development and to accommodate increasing pass-dam transshipment demand; and (iv) support for non-motorized transport (NMT), travel demand management (TDM) in Yichang central business district (CBD) through parking management. The proposed Project is aligned with the key thrusts of ADB's assistance to the PRC under the PRC Country Partnership Strategy (CPS) in the areas of: (i) inclusive growth and balanced developmentby promoting urbanization in less developed regions, and (ii) resource efficiency and environmental sustainabilityby promoting efficient and sustainable urban transport and transit-oriented development. The focus on public transport and multi-modal integration fits well with ADB's Sustainable Transport Initiative (STI) |
||||
Project Rationale and Linkage to Country/Regional Strategy | Yichang is facing two main transport challenges. The first challenge is to develop its transport system to support urban and industrial development in a sustainable way. The main districts, industrial sites, stations, and terminals need to be served by efficient public transport services to reduce transport cost, provide increased accessibility to jobs and services, and promote economic development. Currently bus services have no lane priority and the route structure is not adequately serving the city. The second challenge is to enhance the logistics hub function of Yichang by providing efficient accessibility to the logistic parks being developed in the city, and provide means of meeting the increasing demand for pass-dam transshipment. An efficient logistics hub function and increased pass-dam transshipment capacity will decrease logistics costs and environmental costs around the region by enabling increased use of inland waterways. | ||||
Impact | Efficient, inclusive, and sustainable transport system in Yichang |
Project Outcome | |
---|---|
Description of Outcome | Efficient passenger and freight transport |
Progress Toward Outcome | All contract awards for civil works and equipment packages completed. Final liquidation ongoing. PCR mission tentatively scheduled in October 2019. |
Implementation Progress | |
Description of Project Outputs | Bus rapid transit system Nonmotorized transport measures Road network improvement Capacity building and quality assurance |
Status of Implementation Progress (Outputs, Activities, and Issues) | All works completed. All works completed. Yemingzhu section fly-over construction (2.5 km) funded by local financing opened to public in June 2017. BRT section under the fly-over, excluding B28 Pinghu station became operational in February 2018. Ongoing. |
Geographical Location | Yichang |
Safeguard Categories | |
---|---|
Environment | A |
Involuntary Resettlement | A |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | The project is classified as environment category A. An environmental impact assessment (EIA) report and environmental management plan (EMP) that comply with ADB Safeguard Policy (2009) and PRC regulatory requirements have been prepared for the project and were disclosed on the ADB website on 14 December 2012. The EIA concludes that anticipated environmental impacts and risks are modest and can be limited to an acceptable level through the implementation of the EMP and compliance with loan covenants. Capacity development and institutional strengthening are proposed to minimize environmental risks. The EMP assesses potential impacts of the project components, sets out mitigation and monitoring measures, institutional arrangements, training requirements, and budgets for implementation of the EMP. |
Involuntary Resettlement | The project is category A for involuntary resettlement.16 The resettlement impacts of the project include land acquisition in rural areas and demolition of rural and urban houses and urban commercial structures (shops). Nine villages and one urban neighborhood in Yichang city will be affected. The total permanent land acquisition is 1,797.5 mu. Demolition will involve 56,106.60 square meters (m2) of residential structures. Together, land acquisition and demolition will affect 1,453 persons in 370 households. The project will also involve demolition of 325 m2 of shops along the BRT corridor that will affect 25 persons in nine shops. The project will temporarily occupy 528.59 mu of land. |
Indigenous Peoples | There are no ethnic minority communities that will be adversely affected by the project, which is category C for indigenous peoples. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Yichang Municipal Governemnt (EA), Yichang Provincial Government are consulted for project scoping and design during mission and through subsequent correspondances. |
During Project Implementation | Consultation and participation strategy will continue during implementation. |
Responsible ADB Officer | Pettersson, Anders |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | EASI, East Asia Department |
Executing Agencies |
Yichang Municipal Government |
Timetable | |
---|---|
Concept Clearance | 15 Dec 2011 |
Fact Finding | 05 Dec 2012 to 12 Dec 2012 |
MRM | 16 Apr 2013 |
Approval | 21 Aug 2013 |
Last Review Mission | - |
Last PDS Update | 27 Sep 2019 |
Loan 3014-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
21 Aug 2013 | 30 Oct 2013 | 06 Jan 2014 | 31 Dec 2018 | - | 20 Jan 2020 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 515.10 | Cumulative Contract Awards | |||
ADB | 150.00 | 17 Jun 2022 | 149.93 | 0.00 | 100% |
Counterpart | 365.10 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Jun 2022 | 149.93 | 0.00 | 100% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Unsatisfactory | Satisfactory | Unsatisfactory | Unsatisfactory | - | Unsatisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
People’s Republic of China: Hubei-Yichang Sustainable Urban Transport Project | Validations of Project Completion Reports | Jun 2021 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Putting Chinese Commuters into the Fast Lane
A new bus rapid transit system is cutting down traffic and pollution in Yichang, People’s Republic of China, while giving people a renewed sense of pride in their city.New Bus System Makes PRC City of Yichang More Livable
A new bus rapid transport system is easing up traffic congestion and pollution in the city of Yichang, People’s Republic of China, making daily commutes an easier, more pleasant experience for local residents.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
PRC: Hubei-Yichang Sustainable Urban Transport Project | Advance Notice | Archived |
Contracts Awarded
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Hubei-Yichang Sustainable Urban Transport Project: Procurement Plan | Procurement Plans | Feb 2016 |