Pakistan: Preparing the Integrated Social Protection Development Program
The proposed program will be financed under the RBL modality which supports Government-owned sector programs, and links disbursements directly to the achievement of program results. The TRTA is required to conduct due diligence as required for the RBL modality, prepare the preliminary design of the program and assess the scope and scale for cofinancing and partnerships. The design and implementation of programs supported by the RBL include ex ante assessments of the program and its systems, ex post results verification, and systematic institutional development. The TRTA will assess the soundness of the government's social comprehensive protection and poverty alleviation program, Ehsaas, and its suitability as the basis for the proposed RBL program.
Project Details
-
Project Officer
Tora, Laisiasa Natakubu
Central and West Asia Department
Request for information -
Country/Economy
Pakistan -
Sector
- Public sector management
Related Projects
Project Name | Preparing the Integrated Social Protection Development Program | ||||||||
Project Number | 45233-004 | ||||||||
Country / Economy | Pakistan |
||||||||
Project Status | Active | ||||||||
Project Type / Modality of Assistance | Technical Assistance |
||||||||
Source of Funding / Amount |
|
||||||||
Strategic Agendas | Inclusive economic growth |
||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships |
||||||||
Sector / Subsector |
Education / Pre-primary and primary - social protection initiatives Health / Nutrition Public sector management / Public expenditure and fiscal management - Social protection initiatives |
||||||||
Gender Equity and Mainstreaming | Gender equity | ||||||||
Description | The proposed program will be financed under the RBL modality which supports Government-owned sector programs, and links disbursements directly to the achievement of program results. The TRTA is required to conduct due diligence as required for the RBL modality, prepare the preliminary design of the program and assess the scope and scale for cofinancing and partnerships. The design and implementation of programs supported by the RBL include ex ante assessments of the program and its systems, ex post results verification, and systematic institutional development. The TRTA will assess the soundness of the government's social comprehensive protection and poverty alleviation program, Ehsaas, and its suitability as the basis for the proposed RBL program. | ||||||||
Project Rationale and Linkage to Country/Regional Strategy | ADB will maintain support for social protection and poverty alleviation to build the resilience of vulnerable families and individuals in Pakistan. ADB is assessing the viability of a $300 million Results-Based Lending (RBL) program to provide further women-focused support to Ehsaas for system strengthening and improved governance, and human capital development. The indicative program scope will include: (i) institutional and organizational capacity for social protection under UCT and CCT strengthened, (ii) CCT for primary education expanded; and (iii) the design and implementation of pilot CCT for nutrition evaluated. | ||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Tora, Laisiasa Natakubu |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Public Management, Financial Sector and Trade Division, CWRD |
Executing Agencies |
Benazir Income Support Program F- Block, Pak Secretariat |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | 11 Dec 2020 |
Last Review Mission | - |
Last PDS Update | 14 Dec 2020 |
TA 6678-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
11 Dec 2020 | 29 Dec 2020 | 29 Dec 2020 | 31 Dec 2021 | 31 Dec 2023 | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
1,750,000.00 | 0.00 | 7,000.00 | 0.00 | 0.00 | 0.00 | 1,757,000.00 | 21 Jun 2022 | 466,450.63 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Preparing the Integrated Social Protection Development Program: Technical Assistance Report | Technical Assistance Reports | Dec 2020 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
National Procurement Specialist | Individual - Consulting | Closed | 18 Jun 2022 | 26 Jun 2022 |
Preparing the ISPDP - Int'l IT System and Data Management Specialist | Individual - Consulting | Closed | 25 May 2021 | 31 May 2021 |
International Procurement Specialist | Individual - Consulting | Closed | 01 Apr 2021 | 07 Apr 2021 |
National Economist | Individual - Consulting | Closed | 13 Mar 2021 | 18 Mar 2021 |
National Health & Nutrition Specialist | Individual - Consulting | Closed | 20 Feb 2021 | 05 Mar 2021 |
National Procurement Specialist | Individual - Consulting | Closed | 20 Feb 2021 | 26 Feb 2021 |
National Education Specialist | Individual - Consulting | Closed | 20 Feb 2021 | 05 Mar 2021 |
International Monitoring and Evaluation (M&E) Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 25 Feb 2021 |
ISPDP - Int'l Social Protection and Conditional Cash Transfer Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 04 Mar 2021 |
National Environmental Safeguards Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 25 Feb 2021 |
National Monitoring & Evaluation Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 25 Feb 2021 |
National Social Development and Gender Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 04 Mar 2021 |
National Financial Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 25 Feb 2021 |
International Education Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 04 Mar 2021 |
International Project Implementation and System Specialist and Team Leader | Individual - Consulting | Closed | 19 Feb 2021 | 25 Feb 2021 |
National Social Protection and Cash Transfer Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 04 Mar 2021 |
International Health and Nutrition Specialist | Individual - Consulting | Closed | 19 Feb 2021 | 04 Mar 2021 |
International Social Protection and Conditional Cash Transfer Specialist and Team Leader | Individual - Consulting | Closed | 14 Jan 2021 | 01 Feb 2021 |
International Financial Management and Risk Specialist | Individual - Consulting | Closed | 14 Jan 2021 | 01 Feb 2021 |
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.