fbpx 45507-003: Yunnan Chuxiong Urban Environment Improvement Project | Asian Development Bank

China, People's Republic of: Yunnan Chuxiong Urban Environment Improvement Project

Sovereign (Public) Project | 45507-003 Status: Active

ADB is helping the People’s Republic of China develop the three cities comprising the central Yunnan city cluster - Chuxiong Municipality, Lufeng County, and Wuding County. The project will reduce flood risks and enhance public amenities, improve sanitation and public health, expand urban road networks, and promote public participation in urban development.

Project Details

Project Officer
Chu, Chenglong East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Loan
Sector
  • Agriculture, natural resources and rural development
 
Project Name Yunnan Chuxiong Urban Environment Improvement Project
Project Number 45507-003
Country China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project
Ordinary capital resources US$ 150.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Sector / Subsector

Agriculture, natural resources and rural development / Water-based natural resources management

Transport / Urban roads and traffic management

Water and other urban infrastructure and services / Urban sanitation - Urban solid waste management

Gender Equity and Mainstreaming Effective gender mainstreaming
Description The project will support socially inclusive and environmentally sound development in three small and medium-sized cities in Chuxiong Municipality, Lufeng County, and Wuding County in Yunnan Province. It will (i) reduce flood risks and enhance public amenities, (ii) improve sanitation and public health, (iii) expand urban road networks, and (iv) promote public participation in urban development. By supporting the development of three cities comprising the central Yunnan city cluster, the project will contribute to regional economic integration between the PRC and the other countries of the Greater Mekong Subregion (GMS).
Project Rationale and Linkage to Country/Regional Strategy

Yunnan, one of the 12 less-developed municipality, provinces and autonomous regions targeted under the PRC's Western Development Strategy, is landlocked, mountainous, and hilly. Sharing 4,060 kilometers of border with the Lao People's Democratic Republic, Myanmar and Viet Nam, its location provides it with a particular geographical advantage of emerging as an important national transport and trade gateway for the western inland PRC to connect with the neighboring countries of the GMS. Because of this, Yunnan is endowed with an opportunity to support the PRC's greater geographical balance in social and economic development across the country. Since 2001, it has added 55,099 km of national roads and highways to expand the transportation links within Yunnan as well as with those neighboring GMS countries. Despite its development potential, Yunnan's economy has grown more slowly than those of the other Western inland provinces and autonomous regions. The provincial per capita gross domestic product in 2012 was $3,505, only 58% of the PRC average of $6,093. Although the provincial capital of Kunming is strategically located at the junction of three major GMS transport corridors, Yunnan's share in the PRC's trade with the other GMS countries declined steadily from 20% to 16% during 2001 2012.

A key constraint on Yunnan's socioeconomic growth and economic integration into the GMS is its low urbanization rate and the poor competitiveness of its second- and third-tier cities. Despite rapid development in the capital city of Kunming, many of the province's small and medium-sized cities suffer from inadequate basic infrastructure and remain isolated economically. Under its 12th five-year plan covering 2011 2015, Yunnan aims to stimulate its socioeconomic growth by developing clusters of cities with a variety of industries and commercial activities to create economic growth poles. Yunnan needs a strong support to develop economically and commercially competitive second- and third-tier cities and their city clusters to transform the regional transport corridors already established through the province'srapid highway expansion program into corridors of economic development.

The three project cities are key centers of the Chuxiong Yi autonomous prefecture, which lies 165 km west of Kunming. The prefecture is especially important to government efforts to (i) strengthen socioeconomic links between Kunming and the surrounding small and medium-sized cities and thereby enhance the overall economic competitiveness of the central Yunnan city cluster, and (ii) promote regional economic cooperation between Yunnan and the other GMS countries, since the prefecture is a western gateway to Myanmar. However, urban expansion has been limited in the three cities by their predominantly hilly and mountainous terrain. Like other small and medium-sized centers in the province, living conditions and their business and investment environments have been degraded by inadequate flood management and poor sanitation services. Their weak urban infrastructure is holding back not only socioeconomic development for their residents but also wider regional economic integration across the province.

The Yunnan Chuxiong Urban Environment Improvement Project will provide Asian Development Bank (ADB) lending for second- and third-tier city development of the province through various new approaches. It will include measures to address the frequent flooding in three cities and their surrounding agricultural lands that currently restricts their city expansion and economic development. Although the PRC generally relies heavily on engineering measures to contain flooding, the project will adopt an ecologically sound, climate resilient design that will balance engineering measures with river ecosystem conservation and the enhancement of public amenities. Based on international good practice, it will also introduce the use of storm water detention ponds in Yunnan to mitigate downstream impacts and pollution from storm water runoff. The poor sanitation in the project cities results from their inability to handle the growing amounts of solid waste and their inadequate sewage pipeline networks. The project will help each city develop comprehensive solid waste management plans and will raise public awareness of the need to reduce, reuse, and recycle waste. The project will also demonstrate how construction of city roads with added functions of harvesting rainwater and intercepting sewage from surrounding villages can improve the city environment. The roads will also be equipped with energy-saving streetlights. The project will strongly encourage the public to participate in river landscaping and city planning to reflect public priorities.

The project is in line with ADB's country partnership strategy, 2011 2015 for the PRC. It aligns with ADB's water operational plan by incorporating socially inclusive and integrated water resource management principles. It is also in line with the aims of ADB's urban operational plan to enhance the competitiveness and livability of cities through urban development.11 By promoting sustainable urbanization and a better balance in the currently uneven growth and development of the PRC's regions, the project also supports the PRC's 12th Five-Year Plan,2011 2015 for national economic and social development, as well as related provincial, prefecture, and municipal plans. The project will contribute to Yunnan's sustainable development strategy for 2008 2020, particularly its goal of promoting urban environmental management and expanding environmental infrastructure.

Impact More competitive, green, and inclusive city development in Chuxiong Municipality, Lufeng County, and Wuding County that will support the development of the central Yunnan city cluster
Project Outcome
Description of Outcome Urban infrastructure services and environment improved in cities of Chuxiong Municipality, Lufeng County, and Wuding County
Progress Toward Outcome No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road opened bidding on August 14th 2019 and the contract was awarded to Taiyuan Municipal Infrastructure Construction Group Co., Ltd with the contract signed on December 19th 2019. The contractor has established the project managmenet office, but failed to be mobilized under the influence of coronavirus epidemic.
Implementation Progress
Description of Project Outputs

Chuxiong urban infrastructure and environment improved

Lufeng urban infrastructure and environment improved

Wuding urban infrastructure and environment improved

Capacity and institutional strength of the executing and implementing agencies increased

Status of Implementation Progress (Outputs, Activities, and Issues)

completed

completed

completed

completed

will be included in the final workshop and the PCR.

has been completed and put into operation

has been completed and put into operation

No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road opened bidding on August 14th 2019 and the contract was awarded to Taiyuan Municipal Infrastructure Construction Group Co., Ltd with the contract signed on December 19th 2019. The contractor has established the project management office, but failed to be mobilized under the influence of coronavirus epidemic.

No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road opened bidding on August 14th 2019 and the contract was awarded to Taiyuan Municipal Infrastructure Construction Group Co., Ltd with the contract signed on December 19th 2019. The contractor has established the project management office, but failed to be mobilized under the influence of coronavirus epidemic.

No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road will be completed and put into operation by the year end but subject to the conditions of coronavirus epidemic.

has been completed and put into operation

has been completed and put into operation

has been completed and put into operation

has been completed and put into operation.

No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road opened bidding on August 14th 2019 and the contract was awarded to Taiyuan Municipal Infrastructure Construction Group Co., Ltd with the contract signed on December 19th 2019. The contractor has established the project management office, but failed to be mobilized under the influence of coronavirus epidemic.

achieved

No.17 road will be completed and put into operation within 1 month but subject to the conditions of coronavirus epidemic; The remaining works of No.11 road opened bidding on August 14th 2019 and the contract was awarded to Taiyuan Municipal Infrastructure Construction Group Co., Ltd with the contract signed on December 19th 2019. The contractor has established the project management office, but failed to be mobilized under the influence of coronavirus epidemic.

According to the original FSR, the project will carry out river rehabilitation of about 6.082km section of the East and West River for flood prevention and ecological landscaping. As the West River rehabilitation project was already carried out with domestic special fund from the water resources department before the project is commenced, the project will only cover the East River rehabilitation with the length of about 1.96km.

completed in September 2019 and delivered to the water resources bureau, in the defect liability period.

The north extension line of Zhuluoji Avenue was completed in June 2019; The north extension line of Century Avenue, No.2 and No.3 Road, Jinshan South Road North Extension, No.1 Road started construction in 2019. As of the year end of 2019, Century Avenue Extension has completed roadbed excavation and compression, accounting for 40% of the road works; No.2 road has completed roadbed excavation and compression, accounting for 40% of the road works; No.3 road has completed roadbed excavation and compression, accounting for 35% of the road works; Jinshan South Road has completed 79% of the roadbed excavation works; No.1 road has completed 90% of the roadbed works; It is expected that Lufeng ADB loan road works will be completed by June 2020.

The north extension line of Zhuluoji Avenue was completed in June 2019; The north extension line of Century Avenue, No.2 and No.3 Road, Jinshan South Road North Extension, No.1 Road started construction in 2019. As of the year end of 2019, Century Avenue Extension has completed 75% of the water supply and drainage works; No.2 road has completed 75% of the water supply and drainage works; No.3 road has completed 75% of the water supply and drainage works; Jinshan South Road has completed 20% of the water supply and drainage works; No.1 road has completed 10% of the water supply and drainage works; It is expected that Lufeng ADB loan road works will be completed by June 2020.

The north extension line of Zhuluoji Avenue was completed in June 2019; The north extension line of Century Avenue, No.2 and No.3 Road, Jinshan South Road North Extension, No.1 Road started construction in 2019. As of the year end of 2019, Century Avenue Extension has completed 75% of the water supply and drainage works; No.2 road has completed 75% of the water supply and drainage works; No.3 road has completed 75% of the water supply and drainage works; Jinshan South Road has completed 20% of the water supply and drainage works; No.1 road has completed 10% of the water supply and drainage works; It is expected that Lufeng ADB loan road works will be compelted by June 2020.

The north extension line of Zhuluoji Avenue was completed in June 2019; The north extension line of Century Avenue, No.2 and No.3 Road, Jinshan South Road North Extension, No.1 Road started construction in 2019. As of the year end of 2019, Century Avenue Extension has completed 75% of the water supply and drainage works; No.2 road has completed 75% of the water supply and drainage works; No.3 road has completed 75% of the water supply and drainage works; Jinshan South Road has completed 20% of the water supply and drainage works; No.1 road has completed 10% of the water supply and drainage works; It is expected that Lufeng ADB loan road works will be completed by June 2020.

completed in June 2019 and in the defect liability period.

completed in August 2019 and in the defect liability period.

completed in September 2017 and delivered to the urban management department.

completed in September 2017 and delivered to the urban management department.

delivered to the urban management department

completed procurement and delivered to Chuxiong Traffic Group in December 2019 and in the defect liability period.

The river embankment foundation, precast river embankment, flood control channel, pedestrian walkway, seedlings and hardscape pavement have all been completed; and the functional planning of landscaping, lighting and sprinkler irrigation will be completed in May 2020.

32% of equipment supply and installation have been completed, and it is planned to complete equipment commissioning and trial operation by August 2020.

The remaining 1.4km of Mudan Road and Binhe Road have completed the roadbed and lower subgrade, and will complete the pavement works by July 2020.

all completed and ready for project acceptance.

all completed and ready for project acceptance.

all completed and ready for project acceptance.

all completed.

All completed and ready for project acceptance. The landscaping project is planned to be upgraded.

in operation

in operation

in operation

achieved

in operation

Geographical Location
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects The project is classified category A for environment. An environmental impact assessment was drafted in compliance with ADB's Safeguard Policy Statement (2009) and posted on the ADB website on 18 July 2013. The environmental impact assessment concluded that the anticipated environmental impacts and risks can be mitigated to acceptable levels through the implementation of the environmental management plan. During construction, the focus will be on proper earthwork management, soil erosion and water resources protection, and sound construction site management. During operation, special attention will be paid to mitigating traffic noise at sensitive sites and strengthening the early warning system for floods, traffic safety, and solid waste management in Chuxiong Municipality, Lufeng County, and Wuding County. Monitoring of the project's environmental performance will be conducted during project construction and operation by contractors, construction supervision companies, and local environmental monitoring stations. The monitoring will be verified by an independent external monitor. The CPG and the project municipal and county governments are committed to managing the identified environmental risks and have agreed on a comprehensive set of environment-related loan covenants and a training program with a strong emphasis on environment safeguards. Environment safeguard documents were disclosed to the affected people. Potential environmental complaints or disputes will be handled in accordance with the grievance redress mechanism established for the project.
Involuntary Resettlement The project is classified category A for involuntary resettlement. Three resettlement plans and one resettlement and ethnic minority development plan were prepared in line with ADB's Safeguard Policy Statement and were approved by ADB and the government. The plans were disclosed to the affected persons and uploaded to the ADB website in October 2013. Overall, the project will affect 8,639 persons, including 652 who will be relocated. The project will permanently acquire 2,261 mu of collective and state-owned land, and demolish 40,814 square meters of residential and nonresidential buildings. The project municipal and county governments have assured ADB that funds for resettlement will be made available on a timely basis. The capacity development and institutional strengthening activities will include support for implementing resettlement. The implementation of the resettlement plans and the resettlement and ethnic minority development plan will be monitored and evaluated internally and externally. The three project municipal and county governments and PIUs have fulltime staff members responsible for land acquisition and resettlement who will regularly report implementation progress to the CPG and submit quarterly progress reports to ADB. The external monitor will review the progress and general welfare of affected persons to assess whether they have fully regained their standard of living. Monitoring and evaluation reports will be prepared semiannually during implementation and annually for 2 years after resettlement is complete. They will be submitted to ADB and publicly disclosed. The project has also established a transparent grievance mechanism that will provide meaningful consultation and trigger remedial action defined for the project.
Indigenous Peoples The project is classified category B for indigenous peoples. The majority of the population in Yunnan and in the project cities belong to more than 25 ethnic minorities. Ethnic minorities in Chuxiong Municipality and Lufeng County are well-integrated socially and economically in the cities and do not live in distinct communities in the project areas. In Wuding County, a minority ethnic Hui village will be affected by the subproject's road construction, primarily through land acquisition and the resettlement of three households. Aside from the land acquisition and concerns over noise during construction activities, no negative impacts have been identified in the village during extensive consultations. The village population supports the project, which it expects to provide it with improved mobility and access to the city center. The education and household income levels of the ethnic minority and majority populations are the same in these project cities, and ethnic minorities benefit from many preferential policies that provide them with representation in politics and access to schools and programs in rural areas for poverty alleviation. A resettlement and ethnic minority development plan that outlines the issues and actions for ethnic minority integration in the resettlement plan for the Wuding subproject was approved, disclosed to the affected persons, and uploaded to the ADB website in October 2013.
Stakeholder Communication, Participation, and Consultation
During Project Design Extensive consultations with project municipal and county government agencies took place during project design. A socioeconomic survey, an ethnic minority development survey, and focus group discussions covered 520 urban and rural households with 950 people in the project areas. During the preparation of resettlement and ethnic minority development plan, members of more than 460 affected households were interviewed, while 300 local affected people and more than 100 representatives from various institutions and local communities were consulted during the environmental monitoring plan preparation. Public participation during implementation will include such activities as (i) the public hearing process for tariff adjustments and urban design and planning; and (ii) advocacy on flood warning and evacuation, solid waste management and recycling, and road safety. These processes were reflected in the SAP, the gender action plan, the design and monitoring framework, and loan assurances.
During Project Implementation
Business Opportunities
Consulting Services

Individual consultant selection - 9 person-months - $0.16 million

Quality- and cost-based selection - 112 person-months - $1.84 million

Procurement

International competitive bidding - 7 contracts - $61.20 million

National competitive bidding - 22 contracts - $125.00 million

Shopping - 5 contracts - $0.05 million

Responsible ADB Officer Chu, Chenglong
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
Chuxiong Prefecture Government
[email protected]
No 91 of Huidong Road, Project Management
Office of ADB Chuxiong Project, Chuxiong
Municipality, 675000, Yunnan, P.R.China
Yunnan Provincial Finance Department Division of International Cooperation
[email protected]
Wuhuashan, Kunming Yunnan,
Peoples Republic of China
Timetable
Concept Clearance 17 Oct 2011
Fact Finding 25 Jun 2013 to 04 Jul 2013
MRM 06 Nov 2013
Approval 21 Mar 2014
Last Review Mission -
Last PDS Update 16 Mar 2020

Loan 3115-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
21 Mar 2014 22 Aug 2014 18 Nov 2014 30 Jun 2019 31 Dec 2020 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 410.40 Cumulative Contract Awards
ADB 150.00 21 Mar 2014 131.50 0.00 88%
Counterpart 260.40 Cumulative Disbursements
Cofinancing 0.00 21 Mar 2014 97.83 0.00 65%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Yunnan Chuxiong Urban Environment Improvement Project: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Jul 2020
Yunnan Chuxiong Urban Environment Improvement Project: Audited Project Financial Statements (January-December 2018) Audited Project Financial Statements Jul 2019
Yunnan Chuxiong Urban Environment Improvement Project: Procurement Plan Procurement Plans May 2019
Yunnan Chuxiong Urban Environment Improvement Project: Audited Project Financial Statements (January-December 2017) Audited Project Financial Statements Jun 2018
Yunnan Chuxiong Urban Environment Improvement Project: Audited Project Financial Statements (January - December 2016) Audited Project Financial Statements Jun 2017
Yunnan Chuxiong Urban Environment Improvement Project: Audited Project Financial Statements (18 November 2014-31 December 2015) Audited Project Financial Statements Jun 2016
Loan Agreement for Yunnan Chuxiong Urban Environment Improvement Project Loan Agreement (Ordinary Resources) Aug 2014
Project Agreement for Yunnan Chuxiong Urban Environment Improvement Project Project/Program Agreements Aug 2014
云南楚雄城市环境改善项目 : 项目数据表 Translated PDS Jun 2014
Yunnan Chuxiong Urban Environment Improvement Project Project/Program Administration Manual Feb 2014
Yunnan Chuxiong Urban Environment Improvement Project Reports and Recommendations of the President Feb 2014
Yunnan Chuxiong Urban Environment Improvement Project Gender Action Plans Feb 2014

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (July-December 2019) Environmental Monitoring Reports Feb 2020
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (January-June 2019) Environmental Monitoring Reports Sep 2019
Yunnan Chuxiong Urban Environment Improvement Project: Wuding County Resettlement External Monitoring Report No. 7 Social Monitoring Reports Mar 2019
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong Road Resettlement External Monitoring Report No. 7 Social Monitoring Reports Mar 2019
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Resettlement External Monitoring Report No. 7 Social Monitoring Reports Mar 2019
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng County Resettlement External Monitoring Report No. 7 Social Monitoring Reports Mar 2019
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (July-December 2018) Environmental Monitoring Reports Feb 2019
Yunnan Chuxiong Urban Environment Improvement Project: Addendum to Environmental Impact Assessment Environmental Impact Assessments Sep 2018
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Aug 2018
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong Road Resettlement External Monitoring Report No. 6 Social Monitoring Reports Mar 2018
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Resettlement External Monitoring Report No. 6 Social Monitoring Reports Mar 2018
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Resettlement External Monitoring Report No. 6 Social Monitoring Reports Mar 2018
Yunnan Chuxiong Urban Environment Improvement Project: Wuding External Monitoring Report on Resettlement and Ethnic Minority Development No. 6 Social Monitoring Reports Mar 2018
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (July-December 2017) Environmental Monitoring Reports Feb 2018
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Resettlement External Monitoring Report No. 5 Social Monitoring Reports Oct 2017
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Resettlement and and Ethnic Minority Development External Monitoring Report No. 5 Social Monitoring Reports Oct 2017
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong Road Resettlement External Monitoring Report No. 5 Social Monitoring Reports Oct 2017
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Resettlement External Monitoring Report No. 5 Social Monitoring Reports Oct 2017
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (January-June 2017) Environmental Monitoring Reports Oct 2017
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (July-December 2016) Environmental Monitoring Reports May 2017
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Resettlement External Monitoring Report No. 4 Social Monitoring Reports Mar 2017
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Resettlement External Monitoring Report No. 4 Social Monitoring Reports Mar 2017
Yunnan Chuxiong Urban Environment Improvement Project: Wuding External Social Monitoring Report No. 4 Social Monitoring Reports Mar 2017
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong Road Resettlement External Monitoring Report No. 4 Social Monitoring Reports Mar 2017
Yunnan Chuxiong Urban Environment Improvement Project: Upper Longchuan River Component Updated Resettlement Plan Resettlement Plans Dec 2016
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Social Monitoring Report No. 3 Social Monitoring Reports Jun 2016
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Social Monitoring Report No. 3 Social Monitoring Reports Jun 2016
Yunnan Chuxiong Urban Environment Improvement Project: Environmental Monitoring Report (July 2015-June 2016) Environmental Monitoring Reports Jun 2016
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Social Monitoring Report No. 3 Social Monitoring Reports Jun 2016
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Social Monitoring Report No. 2 Social Monitoring Reports Jan 2016
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Social Monitoring Report No. 2 Social Monitoring Reports Jan 2016
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Social Monitoring Report No. 2 Social Monitoring Reports Jan 2016
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng County Subproject Updated Resettlement Plan Resettlement Plans Jul 2015
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Subproject Updated Resettlement and Ethnic Minority Development Plan Combined Resettlement Plan and Indigenous Peoples Plans Jun 2015
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong City Road Component Updated Resettlement Plan Resettlement Plans May 2015
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Component - External Monitoring Report on Resettlement and Ethnic Minority Development (No. 1) Social Monitoring Reports Feb 2015
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong City Road Component - External Resettlement Monitoring Report No. 1 Social Monitoring Reports Feb 2015
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Component - External Resettlement Monitoring Report No. 1 Social Monitoring Reports Feb 2015
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Component - External Resettlement Monitoring Report No. 1 Social Monitoring Reports Feb 2015
Yunnan Chuxiong Urban Environment Improvement Project: Wuding Urban Infrastructure and Environment Improvement Subproject Combined Resettlement Plan and Indigenous Peoples Plans Oct 2013
Yunnan Chuxiong Urban Environment Improvement Project: Chuxiong City Road Component Resettlement Plans Aug 2013
Yunnan Chuxiong Urban Environment Improvement Project: Lufeng Urban Infrastructure and Environment Improvement Subproject Resettlement Plans Jul 2013
Yunnan Chuxiong Urban Environment Improvement Project: Longchuan River Component Resettlement Plans Jul 2013
Yunnan Chuxiong Urban Environment Improvement Project Environmental Impact Assessments Jul 2013

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
3115-PRC: Yunan Chuxiong Urban Environment Improvement Project (EWD4) Invitation for Bids Closed 08 Apr 2020 26 May 2020
3115 PRC: Yunnan Chuxiong Urban Environment Improvement Project (CWD6) Invitation for Bids Closed 19 Nov 2019 17 Dec 2019
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project (ELF2) Invitation for Bids Closed 17 Jul 2019 28 Aug 2019
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project Invitation for Bids Closed 18 Jun 2019 30 Jul 2019
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project Invitation for Bids Closed 18 Jun 2019 31 Jul 2019
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project [CLF2] Invitation for Bids Closed 18 Jul 2018 14 Aug 2018
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project [ECX2-2] Invitation for Bids Closed 23 Jan 2018 14 Mar 2018
L3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project [CLF3&4] Invitation for Bids Closed 13 Dec 2017 23 Jan 2018
3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project [EWD1] Invitation for Bids Closed 17 Nov 2017 29 Dec 2017
L3115-PRC: Yunnan Chuxiong Urban Environment Improvement Project [CLFR2: Landscaping] Invitation for Bids Closed 18 May 2017 20 Jun 2017

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
LANDSCAPING PHASE II FOR LUFENG COUNTY (CLFR3) Loan 3115 02 Jan 2020 YUNNAN EVERBROAD CONSTRUCTION BUILDING CO., YUNNAN PROVINCE CHINA,PEOPLE'SREP.OF CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 9,588,113.12 5,378,735.53
UPGRADE OF XINZHONG STREET FOR WUDING COUNTY CWD5 Loan 3115 26 Dec 2019 HUNAN JINKAI GARDEN GROUP CO., LTD HUNAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 2,786,359.99 2,134,003.51
REBIDDING FOR REMAINING CIVIL WORKS OF ROAD NO.11 FOR CHUXIONG CITY CCX1-R Loan 3115 26 Dec 2019 TAIYUAN MUNICIPAL CONSTRUCTION GROUP CO., LTD TAIYUAN CITY, SHANXI PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 7,856,932.65 6,018,288.04
PROCUREMENT OF GREEN BUS FOR LUFENG COUNTY (ELF3) Loan 3115 15 Oct 2019 ZHENGZHOU YUTONG BUS CO., LTD ZHENGZHOU CITY, HENAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government SUPPLY OF GOODS 3,611,997.09 3,611,997.09
PROCUREMENT OF GREEN BUS FOR CHUXIONG CITY (ECX4) Loan 3115 07 Oct 2019 XIAMEN KING LONG UNITED AUTOMOTIVE INDUSTRY XIAMEN, FUJIAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government SUPPLY OF GOODS 7,505,106.04 7,505,106.04
PROCUREMENT OF GREEN BUS FOR WUDING COUNTY (EWD3) Loan 3115 13 Aug 2019 ZHENGZHOU YUTONG BUS CO., LTD ZHENGZHOU CITY, HENAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government SUPPLY OF GOODS 2,808,985.58 2,762,501.74
NO. 1 ROAD AND JIN SHAN NAN ROAD AND RELATED INFRASTRUCTURES (3.1 KM) Loan 3115 26 Nov 2018 YUNNAN EVERBROAD CONSTRUCTION BUILDING CO., YUNNAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 12,638,640.00 9,643,791.00
SHIJI AVENUE EXTENSION, ROADS NO.2 AND NO.3 AND RELATED INFRASTRUCTURES FOR LUFENG COUNTY. Loan 3115 10 Jul 2018 YUNNAN EVERBROAD CONSTRUCTION BUILDING CO., YUNNAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 11,138,786.00 8,229,812.00
MUNICIPAL SOLID WASTE EQUIPMENT FOR CHUXIONG SUBPROJECT Loan 3115 29 Jun 2018 HUNAN FORWARD ECONOMY & TRADE DEVELOPMENT CHANGSHA CITY, HUNAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government SUPPLY OF GOODS 2,756,470.00 2,699,152.00
TRAFFIC SIGNALS AND EQUIPMENT FOR WUDING COUNTY Loan 3115 25 May 2018 GS-UNIS INTELLIGENT TRANSPORTATION & CONTROL NO.802, SUTAN VILLAGE, CHENGGUAN DISTRIC LANZHOU CITY, GANSU PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government SUPPLY OF GOODS 1,327,838.00 1,319,981.00
LANDSCAPING FOR CHUXIONG SUBPROJECT Loan 3115 16 Jan 2018 XI'AN CHINA SUNLIGHT GARDEN AFFORESTATION XI'AN CITY, SHAAN XI PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 4,742,061.00 3,750,433.00
PROCUREMENT OF CIVIL WORKS FOR STORMWATER DETENTIO N POND FOR LUFENG COUNTY Loan 3115 02 Nov 2017 JIANGXI ZHONGJIE ENGINEERING & CONSTRUCTION JIANGXI PROVINCE CHINA,PEOPLE'SREP.OF CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 2,324,904.00 1,775,612.00
PROCUREMENT OF CIVIL WORKS FOR LANDSCAPING FOR LUFENG COUNTY Loan 3115 31 Oct 2017 YUNNAN EVERBROAD CONSTRUCTION BUILDING CO., YUNNAN PROVINCE CHINA,PEOPLE'SREP.OF Chuxiong Prefecture Government CONSTRUCTION 5,937,043.00 4,511,813.00
Wulong River Rehabilitation and Stormwater Detention Pond Loan 3115 06 Jun 2017 Jiangsu Huaiyin Water Hydro Construction Co. Jiangsu Province, China, People's Rep. of Chuxiong Prefecture Government Construction 5,539,176.00 4,218,205.00
Longchuan River Rehabilitation Sections 1, 2 and 3 Loan 3115 05 Jun 2017 Sino-Hydro Bureau 6 Co., Ltd Shenyang City, Liaoning Province, China, People's Rep. of Chuxiong Prefecture Government Construction 2,780,172.00 2,137,513.00
Construction of Zhuluoji Avenue North Extension and Related Infrastructure for Lufeng County Loan 3115 25 May 2017 Henan Qiankun Road & Bridge Engineering Co. Henan Province, China, People's Rep. of Chuxiong Prefecture Government Construction 2,987,080.00 2,298,133.00
Workshops Loan 3115 03 Jan 2017 Xinzhou Holding Limited Nanchang City, Jiangxi Province China, People's Republic of Chuxiong Prefecture Government Construction 9,254,556.22 7,098,263.21

Procurement Plan