Armenia : Power Transmission Rehabilitation Project

Sovereign Project | 46416-001

The project aims at improving power system operational efficiency and power supply reliability in Armenia. The project comprises two main components: (i) expansion of supervisory control and data acquisition (SCADA) system; and (ii) rehabilitation of eight existing substations.

Armenia has limited fossil fuel resources as well as renewable resources such as water. The total installed generation capacity by the end of 2011 is 3,900 megawatt (MW). Power generation in 2011 comprises of 34% nuclear, 34% hydropower and 32% thermal power (using imported natural gas). Since the late 1990s, the power sector of Armenia has achieved remarkable results through reforms and restructuring. The distribution network and a large share of generation assets were privatized. There is a competent regulatory agency for the sector - Public Services Regulatory Commission. The country's energy sector is governed by the Energy Law (2001) and the Law on Energy Saving and Renewable Energy of the Republic of Armenia (2004).

Project Details

  • Project Officer
    Luo, Tianhua
    Central and West Asia Department
    Request for information
  • Country/Economy
    Armenia
  • Modality
  • Sector
    • Energy

Related Projects

Project Name Power Transmission Rehabilitation Project
Project Number 46416-001
Country / Economy Armenia
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8198-ARM: Power Transmission Rehabilitation Project
Technical Assistance Special Fund US$ 700,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Energy / Electricity transmission and distribution - Energy efficiency and conservation - Energy sector development and institutional reform

Gender No gender elements
Description

The project aims at improving power system operational efficiency and power supply reliability in Armenia. The project comprises two main components: (i) expansion of supervisory control and data acquisition (SCADA) system; and (ii) rehabilitation of eight existing substations.

Armenia has limited fossil fuel resources as well as renewable resources such as water. The total installed generation capacity by the end of 2011 is 3,900 megawatt (MW). Power generation in 2011 comprises of 34% nuclear, 34% hydropower and 32% thermal power (using imported natural gas). Since the late 1990s, the power sector of Armenia has achieved remarkable results through reforms and restructuring. The distribution network and a large share of generation assets were privatized. There is a competent regulatory agency for the sector - Public Services Regulatory Commission. The country's energy sector is governed by the Energy Law (2001) and the Law on Energy Saving and Renewable Energy of the Republic of Armenia (2004).

The project impact will be improved power system reliability and efficiency in Armenia. The expected project outcome will be enhanced power transmission capacity. Transmission and dispatching network will be enhanced to provide reliable and adequate power supply for domestic and export markets. The project outputs consist of the following components:

(i) Expansion of supervisory control and data acquisition (SCADA) system: SCADA system expansion with control and relay protection system to enable remote operation and automatic system control for efficient power dispatching operation;

(ii) Rehabilitation of eight 220 kV substations: replacement and modernization of existing aging transformers, breakers, and other equipments; and

(iii) Project Supervision and Management: project implementation support comprising project management and supervision, safeguards compliance, and capacity building for HVEN.

Project Rationale and Linkage to Country/Regional Strategy

Armenia is a small country facing an unfavorable environment with closed eastern and western borders and ensuring energy security is the government priority. The project will contribute to strengthening energy security through improved power system reliability and efficiency. The government recognized that upgrading and rehabilitation of transmission networks is one of the sector development priorities and requested ADB to provide financial support. Currently, ADB has no sovereign lending operation in Armenia energy sector, and this project provides a unique opportunity for ADB to enter the sector. The government funding is not sufficient on the investment needed for rehabilitating the aging power infrastructure. ADB's involvement will not only contribute to filling the funding gap but also enhance the confidence of the private sector in investing the power and other infrastructure sectors. The upgraded transmission network will increase the reliability of the power supply nationwide, benefiting the poor and neglected regions. In addition, the project will also contribute to enhancing the power export and regional integration.

ADB's Strategy 2020 commits ADB to support developing member countries in moving their economies into low-carbon growth paths by improving energy efficiency, expanding the use of clean energy sources, and reducing fugitive greenhouse gas (GHG) emission. ADB's Energy Policy 2009 prioritized promoting energy efficiency and renewable energy as one of the three pillars of ADB assistance in the energy sector. The Project is consistent with ADB's Strategy 2020 and Energy Policy (2009) by promoting inclusive growth, energy security, and supporting energy efficiency.

The government, in consultation with ADB, has identified the energy sector as a key pillar of ADB's upcoming Country Partnership Strategy (CPS) for Armenia . A project preparatory technical assistance (PPTA) for this project is included in the ADB's Country Operation Business Plan (COBP) Update 2012-2013.

Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholders' consultations through community meetings, discussions, and interviews will be conducted during the PPTA. Consultations with civil society organizations (CSOs) were held during the environmental and social due diligence for the ensuing ADB project.
During Project Implementation Meetings and discussions were held between ESPO, HVEN and PPTA Consultant. The sequence of substation rehabilitation was deeply analyzed and schedules for substation rehabilitation were agreed upon.
Business Opportunities
Consulting Services

A PPTA consultant (firm) was engaged on 11 March 2013. The PPTA consultant, among other tasks, will undertake necessary due diligence for processing the loan for the project, and assist the pre-implementation works. The PPTA consultant will also adequately address the following aspects relating to the ensuing loan project: (i) detailed loan executing agency capacity assessment, and suggested remedial action plan to build executing agency and implementing agency capacity to minimize procurement and financial management risks; (ii) proposed or indicative loan related procurement plan with suggested level of priority or, if applicable, post review based on executing agency and implementing agency capacity assessment; and (iii) indicative implementation schedule with proposed sequencing of consultant recruitment and procurement bidding and awarding.

An Inception Report was submitted in April 2013 while an Interim report was submitted in July 2013. Draft Final Report was submitted in October 2013. With the completion of due diligence reports for the ADB ensuing loan (Loan 3150-ARM), a Final Report was submitted in May 2015.

Responsible ADB Officer Luo, Tianhua
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Ministry of Energy and Natural Resources of the Republic of Armenia
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 22 Oct 2012
Last Review Mission -
Last PDS Update 23 Sep 2015

TA 8198-ARM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
22 Oct 2012 25 Feb 2013 25 Feb 2013 31 Dec 2013 30 Jun 2015 30 Sep 2015
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
700,000.00 0.00 0.00 0.00 0.00 0.00 700,000.00 17 Jun 2022 671,212.00

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.