China, People's Republic of: Shandong Groundwater Protection Project

Sovereign Project | 47047-002 Status: Active

Project Details

Project Officer
Radstake, Frank East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Loan
Sector
  • Agriculture, natural resources and rural development
 
Project Name Shandong Groundwater Protection Project
Project Number 47047-002
Country China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3400-PRC: Shandong Groundwater Protection Project
Ordinary capital resources US$ 150.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Knowledge solutions
Sector / Subsector

Agriculture, natural resources and rural development - Rural flood protection - Rural water policy, institutional and capacity development - Water-based natural resources management

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects Based on the preliminary assessments, the project is classified as category A for environment. Safeguard documents, including an environmental impact assessment, will be prepared following ADB's Safeguard Policy Statement (2009).
Involuntary Resettlement Based on the preliminary assessments, the project is classified as category A for involuntary resettlement. Safeguard documents, including resettlement plan, will be prepared following ADB's Safeguard Policy Statement (2009).
Indigenous Peoples Based on the preliminary assessments, the project is classified as category C for indigenous peoples. Safeguard documents will be prepared following ADB's Safeguard Policy Statement (2009).
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services

Consulting services will be required for (i) project management support, (ii) capacity development for water policy and conservation demonstration activities, and (iii) software development for the MIS in Huantai County. The outline terms of reference (TOR) for each of the three consulting services packages are described in section D.

The PMO will be responsible for engaging consultants. All consultants financed by ADB will be recruited according to ADB's Guidelines on the Use of Consultants (2013, as amended from time to time).

Procurement

All procurement of goods and works will be undertaken in accordance with ADB's Procurement Guidelines (2015, as amended from time to time). Except as ADB may otherwise agree, the following process thresholds shall apply to procurement of goods and works.

Civil works contracts estimated to cost $25 million and above, and contracts for goods estimated to cost $3 million and above will be procured using international competitive bidding (ICB) procedures. Contracts for works and goods estimated to cost less than the ICB values but equal to $100,001 and above will be procured through national competitive bidding (NCB). NCB will be conducted in accordance with the PRC Tendering and Bidding Law (2000), subject to modifications agreed with ADB. Contracts for goods and works estimated to cost less than the above NCB values will be procured using shopping procedures. The relevant sections of ADB's Anticorruption Policy (1998, as amended from time to time) will be included in all procurement documents and contracts.

For NCB, the first draft English language of the procurement documents (prequalification, bidding documents, and draft contract) should be submitted for ADB's approval regardless of the estimated contract amount. Subsequent procurements are subject to post review. All ICB contracts are subject to prior review and ADB's approval of the procurement documents (bidding and contract) is required.

A procurement plan over the life of the project including the first 18-month procurement contract packages starting from July 2015 has been prepared and agreed with the PMO and the implementing agencies, which indicates procurement method, estimated costs of contracts, threshold and review procedures, goods, works, and consulting service contract packages, and NCB guidelines.

Responsible Staff

Responsible ADB Officer Radstake, Frank
Responsible ADB Department East Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, EARD
Executing Agencies
Shandong Provincial Government
People's Republic of China

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 13 Mar 2017

Loan 3400-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
29 Jun 2016 13 Sep 2016 10 Jan 2017 30 Jun 2022 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 344.03 Cumulative Contract Awards
ADB 150.00 29 Jun 2016 56.29 0.00 38%
Counterpart 194.03 Cumulative Disbursements
Cofinancing 0.00 29 Jun 2016 0.11 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Shandong Groundwater Protection Project: Resettlement Monitoring Report Social Monitoring Reports Mar 2017
Shandong Groundwater Allocation and Protection Project: Huantai Subproject Resettlement Plan Resettlement Plans Jan 2017
Shandong Groundwater Allocation and Protection Project: Qingzhou Subproject Resettlement Plan Resettlement Plans Jan 2017
Shandong Groundwater Allocation and Protection Project: Shouguang Subproject Resettlement Plan Resettlement Plans Jan 2017
Shandong Groundwater Allocation and Protection Project: Gaomi Subproject Resettlement Plan Resettlement Plans Jan 2017
Shandong Groundwater Protection Project: Social Monitoring Report Social Monitoring Reports Oct 2016
Shandong Groundwater Allocation and Protection Project: Gaomi Reservoir Upgrade and Connection Construction - Resettlement Plan Resettlement Plans Feb 2016
Shandong Groundwater Allocation and Protection Project: Huantai Wetland Rehabilitation and Surface Water Allocation Improvement Construction - Resettlement Plan Resettlement Plans Feb 2016
Shandong Groundwater Allocation and Protection Project: Changle Nanzhai Reservoir Expansion - Resettlement Plan Resettlement Plans Feb 2016
Shandong Groundwater Protection Project: Draft Environmental Impact Assessment Environmental Impact Assessments Aug 2015
Shandong Groundwater Allocation and Protection Project: Qingzhou Surface Water Allocation Improvement Construction - Resettlement Plan Resettlement Plans Jul 2015
Shandong Groundwater Allocation and Protection Project: Shouguang Wetland and River Eco-rehabilitation - Resettlement Plan Resettlement Plans Jul 2015
Shandong Groundwater Allocation and Protection: Environmental Impact Assessment Environmental Impact Assessments Mar 2015

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan