China, People's Republic of : Hunan Dongjiang Lake Integrated Environmental Protection and Management Project

Sovereign Project | 47070-002

The proposed project will be implemented in the Dongjiang Lake basin in Zixing City, Chenzhou Municipality, Hunan Province. The project will introduce an integrated approach to address the current constraints in lake environmental protection and livelihood development.

The impact will be the achievement of sustainable economic development of the Xiang River basin in Hunan Province. The outcome will be the achievement of integrated environmental protection in Dongjiang Lake basin. The project will include five outputs: (i) improved pollution control, (ii) establishment of urban-rural water supply system, (iii) rehabilitated river course, (iv) establishment of integrated ecosystem rehabilitation and management established, and (v) strengthened environmental and project management capacity.

Project Details

  • Project Officer
    Kobayashi, Yoshiaki
    Sectors Group
    Request for information
  • Country/Economy
    China, People's Republic of
  • Modality
  • Sector
    • Agriculture, natural resources and rural development
Project Name Hunan Dongjiang Lake Integrated Environmental Protection and Management Project
Project Number 47070-002
Country / Economy China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3336-PRC: Hunan Dongjiang Lake Integrated Environmental Protection and Management Project
Ordinary capital resources US$ 130.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Knowledge solutions
Sector / Subsector

Agriculture, natural resources and rural development / Forestry - Land-based natural resources management - Rural flood protection - Rural solid waste management - Rural water supply services - Water-based natural resources management

Water and other urban infrastructure and services / Urban sewerage - Urban water supply

Gender Effective gender mainstreaming
Description The proposed project will be implemented in the Dongjiang Lake basin in Zixing City, Chenzhou Municipality, Hunan Province. The project will introduce an integrated approach to address the current constraints in lake environmental protection and livelihood development.

The impact will be the achievement of sustainable economic development of the Xiang River basin in Hunan Province. The outcome will be the achievement of integrated environmental protection in Dongjiang Lake basin. The project will include five outputs: (i) improved pollution control, (ii) establishment of urban-rural water supply system, (iii) rehabilitated river course, (iv) establishment of integrated ecosystem rehabilitation and management established, and (v) strengthened environmental and project management capacity.

Output 1 will include (i) construction of six township wastewater treatment plants with a total capacity of 2,000 cubic meters/day, and associated sewage collection pipes of 38.1 kilometers (km); (ii) construction of 2,856 small-scale wastewater treatment facilities for rural villages in 10 townships, and associated sewer pipes of about 330 km; (iii) procurement of solid waste collection and compaction equipment, and seven transfer facilities; and (iv) development of nonpoint source pollution management, including soil test and green fertilizer application; and green pest control measures application in 5,690 hectares (ha) of farmland. Output 2 will include (i) construction of Yangdongxia water supply plant with total water treatment capacity of 20,000 cubic meters/day for water supply of 128,688 residents in five townships, associated water delivery and supply pipelines with total length of about 700 km, and pressure regulating stations; (ii) construction of Chukou water supply plant with capacity of 620 cubic meters/day for supply of 3,200 residents and associated water delivery and supply pipelines of about 35 km; and (iii) procurement of operation and maintenance equipment. Output 3 will improve the flood protection standard and reduce soil erosion of five major rivers of Guangqiao, Lianping, Qingyao, Tian'eshan, and Xingning that flow into the lake, including block clearance and dredging of 653,692 cubic meters (14.7 km), green embankment of 13.7 km, and landscaping along the river banks. Output 4 will include (i) establishment of aquatic facilities and management; (ii) construction of three wetlands for about 167 ha, and management facilities; (iii) conduct of soil erosion control, including 1,000 ha of reforestation and revegetation, natural enhancement and management of 13,666-ha public forest, construction of 590-km fire breaks and procurement of fire-fighting facilities; (iv) improvement of 2,595 ha of bamboo forest; (v) conduct of alternative livelihood training for 30,000 rural residents; and (vi) carrying out of an eco-compensation pilot scheme. Output 5 will support (i) establishment of environmental, fishery, and forest fire-fighting monitoring centers; (ii) establishment of the Dongjiang Lake ecological and environmental protection research center; (iii) development of the Dongjiang Lake environmental monitoring and management information system; (iv) provision of project implementation consulting services, training, workshops, and study tours; and (v) establishment of a project monitoring and evaluation system.

The Zixing City Government (ZCG) will be the executing agency of the project. A project management office (PMO) has been established to be responsible for project coordination, guidance, and consolidated planning and reporting of the project implementation. The implementing agency will be the Zixing City Urban and Rural Environmental Protection Investment and Financing Center (ZIFC).
Project Rationale and Linkage to Country/Regional Strategy One of the greatest challenges facing water management in the PRC relates to freshwater lakes as many of them are severely polluted. Since the mid-1990s, the Government of the People's Republic of China (PRC) has taken substantial efforts to address the problem, with emphasis on three lakes--Chao, Dianchi, and Tai lakes; but these lakes are still without significant improvement. The national government realized the importance of pollution prevention in lakes by drawing lessons learned from the rehabilitation of polluted lakes, including the Chao, Dianchi, and Tai lakes, rehabilitation of which had been proven to be at very high cost. Experience has shown that it will be very difficult and ineffective in large lakes to restore water quality once they are polluted

Located in south Hunan Province, Dongjiang Lake is a reservoir formed after the construction of Dongjiang Dam in 1986 on the Leishui River, a tributary of Xiang River. Dongjiang is a multipurpose reservoir for hydropower, flood control, water supply, and irrigation. Dongjiang Lake has a surface area of 160 square kilometers and a total storage capacity of about 8.12 billion cubic meters. The catchment area of the Dongjiang Lake is 4,719 square kilometers.

It is the national government's priority to protect the water resources of Dongjiang Lake from pollution. Dongjiang Lake has been selected as one of the five river basins for nationwide pilot-testing of the national government's eco-compensation policy framework to which the Asian Development Bank (ADB) has provided continuous support in recent years. Dongjiang Lake has been included as priority of support in the national plan for relatively good-quality lake ecological and environmental protection (2013-2020) jointly released by the Ministry of Environmental Protection, the Ministry of Finance, and the National Development and Reform Commission.

Dongjiang Lake is a strategic water source to support resource-saving and environment-friendly social development of Hunan Province. Maintaining healthy environmental services of the Dongjiang Lake is vital to achieve sustainable development of the Xiang River basin, one of major regions of the national government''s Yangtze River Economic Belt initiative. Xiang River basin is a home for about 40 million population and accounts for over 70% of Hunan Province''s total gross domestic production. In addition to supplying water to Chenzhou Municipality and Zixing City, Dongjiang Lake serves as a back-up water source for Hunan Province''s major cities of Changsha, Xiangtan, and Zhuzhou in Xiang River basin to improve the water security of 13 million people in these cities. The lake's large storage capacity greatly improves flood and drought management for the downstream cities and navigation of the downstream Xiang River. It also helps dilute water pollution in the downstream of Xiang River by releasing water.

Dongjiang Lake's environmental protection has been given priority by the Hunan Provincial Government (HPG) and local governments. Protection zones have been established in the Dongjiang Lake basin in accordance with the provincial-approved Dongjiang Lake Basin Water Environmental Protection Regulation. The regulation imposes control on the development of the basin and restricts various activities in different protection zones which may cause adverse impact on the water environment. Since 2002, HPG and the local governments have invested nearly CNY1 billion in the lake protection, including closure of mines, removal of cage fishing, ship renovation and improvement, and job training for non-farming opportunities. The continued efforts by HPG, the local governments, and local people in implementing the regulation helped in maintaining the good water quality of Dongjiang Lake to meet the national standards for drinking water source.

The project is consistent with the national government''s goal of building a harmonious and prosperous society through regionally balanced and environmentally sustainable growth. The project supports the national government''s recently released Yangtze River Economic Belt Initiative to construct ecological ecosystem corridor along the river by improving watershed management, water pollution control and prevention, and ecological rehabilitation. It conforms to ADB''s strategic priorities of the Midterm Review of Strategy 2020, and the Water Operational Plan 20112020 to increase coverage and improved services for water supply and sanitation, and promote integrated water resources management (IWRM).

The project design has incorporated lessons from the previous ADB-financed projects and policy-oriented studies on IWRM, environmental and ecosystem improvement, wetland and lake management, and urbanrural integration in the PRC. Major lessons include (i) an integrated approach of structural and nonstructural measures to water resources management; (ii) wide community participation and increased public awareness for environmental improvement; (iii) linking environmental protection with livelihood opportunities; (iv) coordinated management of urbanrural planning, and management of resources and services to facilitate integration and linkage to infrastructure; (v) institutional and cost recovery mechanism for effective operation and maintenance of the facilities; and (vi) eco-compensation as effective tool for maintaining environmental services.

The project is expected to scale up and/or demonstrate the following good practices in the PRC: (i) IWRM and comprehensive monitoring, (ii) environmental protection linked with livelihood improvement, and (iii) eco-compensation. In addition, during project preparation, policy dialogue was conducted and recommendations provided for revising the Dongjiang Lake Basin Water Environmental Protection Regulation and the environmental protection plan. Under the IWRM framework, the project attempts to coordinate and integrate the structural and nonstructural measures in a manner that assures their consistency and resulting in synergies where the total impact is greater than the sum of the individual actions. To meet the water quality targets as requested in the national good water quality lake program, pollutants discharged into the lake have to be reduced. The project will take a holistic approach to tackle these challenges by preventing different types of pollution sources, and land degradation and soil erosion with a comprehensive environmental monitoring system to support integrated lake management. The project will not only maintain environmental and ecological services to the local residents and the downstream Changsha-Zhuzhou-Xiangtan city cluster;, but also improve local farmers' income by directly supporting livelihood opportunities, such as bamboo forest development, fish stocking, and technical and vocational education and training in alternative livelihood activities for 30,000 rural residents around the lake. Without such benefits, the willingness of local farmers to comply with environmental regulations around the lake would not be fully effective. Dongjiang Lake plays crucial watershed functions to Hunan Province. An eco-compensation pilot scheme will be tested under the project to compensate those who are responsible for collection and treatment of solid waste and sewage, and engagement of greener agricultural production by setting up an eco-compensation fund to be raised from tourist entry fees. HPG and the Zixing City Government also agreed to explore more eco-compensation schemes for better protection of Dongjiang Lake during project implementation.
Impact

Sustainable economic development of the Xiang River basin in Hunan Province achieved (Xiang River Basin Scientific Development Master Plan, 2011-2020)

Project Outcome
Description of Outcome

Integrated environmental protection in Dongjiang Lake basin achieved

Progress Toward Outcome
Implementation Progress
Description of Project Outputs

1. Pollution control improved

2. Urban-rural water supply system established

3. River course rehabilitated

4. Integrated ecosystem rehabilitation and management established

5. Environmental and project management capacity strengthened

Status of Implementation Progress (Outputs, Activities, and Issues)

As of 31 March 2022:

126,086 m3

As of 31 March 2022:

23,088 m

As of 31 March 2022:

1/10 years

As of 31 March 2022:

167 jobs

As of 31 March 2022:

Not yet operational

As of 31 March 2022:

515 km

As of 31 March 2022:

Operational

As of 31 March 2022:

9.5 km

As of 31 March 2022:

27 jobs

As of 31 March 2022:

117 jobs

As of 31 March 2022:

7,000 m3/day WWTP capacity

295 km associate sewer pipes

As of 31 March 2022:

4,308

As of 31 March 2022:

20,800 households

As of 31 March 2022:

220 tons/day

As of 31 March 2022:

12,174

As of 31 March 2022:

135 jobs

As of 31 March 2022:

120 jobs

As of 31 Dec 2021:

100% constructed

As of 31 Dec 2021:

175 ha

As of 31 Dec 2021:

1,916 ha

As of 31 Dec 2021:

590 km

As of 31 Dec 2021:

5,383 ha

611 woman participants

As of 31 Dec 2021:

31,633 rural residents

As of 31 Dec 2021:

84 jobs for women

As of 31 Dec 2021:

961 jobs for women

As of 31 Dec 2021:

Not yet operational

As of 31 Dec 2021:

Not yet setup

As of 31 Dec 2021:

28 trainings conducted; 629 project staff participated of which 244 are women

As of 31 Dec 2021:

Operational

Geographical Location Zixing Shi
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects Environment (category A). The environmental impact assessment (EIA) report, including an environmental management plan (EMP) follows ADBs Safeguard Policy Statement (SPS, 2009). The EIA is consistent with the domestic EIAs. The draft EIA report was publicly disclosed on the ADBs website on 27 April 2015. The project is expected to achieve environmental benefits, including improved long-term security of the high water quality in Dongjiang Lake; improved wetland habitats; soil erosion control; and improved institutional and community management of water, wetland, and forestry resources. Anticipated construction impacts are from dredging and embankment; construction-related air, dust, noise, vibration, and erosion impacts; and occupational and community health and safety. Potential operational risks include cumulative nutrient loading in Dongjiang Lake and the project rivers due to discharge of treated effluent; inadequate maintenance of the treatment plants, pipelines, and constructed wetlands; and/or air and noise emissions from the treatment plants. The risk of cumulative and/or induced impacts has been assessed. Mitigation measures are described in the EMP. These include the timing of dredging, on-site sediment sampling, control of sediment dispersion, and maintenance of project facilities. The EIA concludes that effective implementation of the EMP, together with the prescribed training, will result in residual impacts within the limits of the PRC standards defined in the EMP. Initial climate risk during project concept stage was medium, but the climate risk vulnerability assessment found the risk to be low. Adaptation measures were included in the project design.
Involuntary Resettlement Involuntary resettlement (category A). A total of 189.06 hectares (ha) of land will be occupied permanently, including 12.28 ha of collective land and 176.77 ha of state-owned land. Some 65.29 ha of land will be occupied temporarily. The project will demolish 1,539.1 square meters of housing. Land acquisition and resettlement will affect 573 people, of which 284 will lose more than 10% of their productive assets and/or be physically displaced. Seven households need to be relocated. Livelihood measures and training will be provided to households with significant land losses. The Zixing City Government (ZCG), with the assistance of consultants, prepared a resettlement plan in line with ADBs SPS and the governments related laws and regulations. The project management office (PMO) and relevant implementing agency have good experience and capacity to manage resettlement impacts. The draft resettlement plan was disclosed on the ADB website ion 2 July 2015.
Indigenous Peoples Ethnic minorities (category B). Yao people in four villages will benefit from several project activities, including bamboo upgrading, wastewater treatment, solid waste management, river rehabilitation, wetland development, livelihood training, and environmental awareness programs. A draft ethnic minority development plan has been prepared in line with ADBs SPS and related laws and regulations of the PRC and Hunan Province. Actions to be taken include community consultation and mobilization to ensure Yao people can participate in project design, construction, and benefits in a manner that supports culturally appropriate village development. The draft ethnic minority development plan was disclosed on the ADB website on 2 July 2015.
Stakeholder Communication, Participation, and Consultation
During Project Design

The main stakeholders of the project are the provincial and local governments, design institutes, rural households including rural households in reservoir protection zone. The stakeholders will be consulted during project preparation.

The project will develop ways to engage (i) with farmers and stakeholders to improve environmental and ecological farming in the reservoir protection area, and (ii) with households to assess their needs for and provide them with nonfarm capacities and skills to cope with rapidly changing and urbanizing social and economic environments.

During Project Implementation Stakeholder communication, participation, and consultation will continue during the project implementation.
Business Opportunities
Consulting Services All consulting services will be engaged in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time).
Procurement All ADB-financed procurement for the project will be conducted in accordance with ADB's Procurement Guidelines (2015, as amended from time to time). A procurement agent will be engaged by the Zixing City Government, the executing agency; and the Zixing City Urban and Rural Environmental Protection Investment and Financing Center (ZIFC), the implementing agency, to assist in procurement.
Responsible ADB Officer Kobayashi, Yoshiaki
Responsible ADB Department Sectors Group
Responsible ADB Division Agriculture, Food, Nature, and Rural Development Sector Office (SG-AFNR)
Executing Agencies
Zixing City Government
Timetable
Concept Clearance 04 Apr 2014
Fact Finding 11 Mar 2015 to 18 Mar 2015
MRM 03 Jul 2015
Approval 25 Nov 2015
Last Review Mission -
Last PDS Update 23 Sep 2022

Loan 3336-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Nov 2015 16 Mar 2016 14 Jun 2016 30 Jun 2021 30 Jun 2022 27 Jun 2023
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 152.46 Cumulative Contract Awards
ADB 130.00 04 Dec 2023 113.81 0.00 100%
Counterpart 22.46 Cumulative Disbursements
Cofinancing 0.00 04 Dec 2023 113.81 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory Satisfactory Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (January 2022-April 2023) Audited Project Financial Statements Jun 2023
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (January-December 2021) Audited Project Financial Statements Jun 2022
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Procurement Plan Procurement Plans Dec 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Jun 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Jun 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (January-December 2018) Audited Project Financial Statements Jun 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Audited Project Financial Statements (14 June 2016-31 December 2017) Audited Project Financial Statements Jun 2018
Project Agreement for Loan 3336-PRC: Hunan Dongjiang Lake Integrated Environmental Protection and Management Project Project/Program Agreements Mar 2016
Loan Agreement (Ordinary Operations) for Loan 3336-PRC: Hunan Dongjiang Lake Integrated Environmental Protection and Management Project Loan Agreement (Ordinary Resources) Mar 2016
Hunan Dongjiang Lake Environmental Protection and Management Project: Gender Action Plan Gender Action Plans Nov 2015
Hunan Dongjiang Lake Environmental Protection and Management Project: Report and Recommendation of the President Reports and Recommendations of the President Nov 2015
Hunan Dongjiang Lake Environmental Protection and Management Project: Project Administration Manual Project/Program Administration Manual Oct 2015
湖南东江湖生态环境保护与综合利用项目 : 项目数据表 Translated PDS Jun 2015
Hunan Dongjiang Lake Environmental Protection and Integrated Utilization Project: Project Preparatory Technical Assistance Report Project Preparatory Technical Assistance Reports Nov 2014

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (January-June 2022) Environmental Monitoring Reports Sep 2022
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Social Monitoring Report (July 2019-June 2022) Social Monitoring Reports Jul 2022
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 6 (July-December 2021) Social Monitoring Reports Feb 2022
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports Feb 2022
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Social Monitoring Report (January–June 2021) Social Monitoring Reports Oct 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (January-June 2021) Environmental Monitoring Reports Aug 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 5 (January–June 2021) Social Monitoring Reports Jul 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Mar 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 4 (July-December 2020) Social Monitoring Reports Feb 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Resettlement Monitoring Report (July-December 2020) Social Monitoring Reports Jan 2021
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Resettlement Monitoring and Evaluation Report (January-June 2020) Social Monitoring Reports Jul 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (January-June 2020) Environmental Monitoring Reports Jul 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 3 (January-June 2020) Social Monitoring Reports Jul 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Resettlement Monitoring and Evaluation Report (July-December 2019) Social Monitoring Reports Jul 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (July-December 2019) Environmental Monitoring Reports Feb 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 2 (As of December 2019) Social Monitoring Reports Feb 2020
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Internal Monitoring Report of Ethnic Minority Development Plan Implementation No. 1 (As of September 2019) Social Monitoring Reports Dec 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (January-June 2019) Environmental Monitoring Reports Aug 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Management Plan Environmental Management Plans Aug 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: External Resettlement Monitoring and Evaluation Report (January-June 2019) Social Monitoring Reports Aug 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (June-December 2018) Environmental Monitoring Reports Feb 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: External Resettlement Monitoring and Evaluation Report (July-December 2018) Social Monitoring Reports Jan 2019
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: External Resettlement Monitoring and Evaluation Report (January-June 2018) Social Monitoring Reports Oct 2018
Hunan Dongjiang Lake Integrated Environmental Protection and Management Project: Environmental Monitoring Report (July 2016-May 2018) Environmental Monitoring Reports Jul 2018
Hunan Dongjiang Lake Environmental Protection and Management Project: External Resettlement Monitoring and Evaluation Report (July-December 2017) Social Monitoring Reports Dec 2017
Hunan Dongjiang Lake Environmental Protection and Management Project: External Resettlement Monitoring and Evaluation Report Social Monitoring Reports Dec 2016
Hunan Dongjiang Lake Environmental Protection and Integrated Utilization Project: Resettlement Plan Resettlement Plans Jul 2015
Hunan Dongjiang Lake Environmental Protection and Integrated Utilization Project: Ethnic Minority Development Plan Indigenous Peoples Plans/Indigenous Peoples Development Plans Jun 2015
Hunan Dongjiang Lake Environmental Protection and Integrated Utilization Project: Updated Environmental Impact Assessment Environmental Impact Assessments Apr 2015
Hunan Dongjiang Lake Environmental Protection and Integrated Utilization Project: Environmental Impact Assessment Environmental Impact Assessments Apr 2015

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
47070-002- Hunan Dongjiang Lake Integrated Environmental Protection and Management Advance Notice Archived

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Reimbursement of operation and maintenance of operation and maintenance of completed WWTPs, small-scale wastewater treatment facilities, garbage collection and transfer facilities, breeding base, and wetlands Loan 3336 06 Oct 2022 Various | PRC Zixing City Government 11,175,735.97 11,175,735.97
EQUIPMENT FOR DRINKING WATER RESOURCES ONLINE MONI TORING Loan 3336 04 Nov 2020 FUZHOU FUGUANG WATER TECHNOLOGY CO., LTD. | JINYAN RD., JINSHAN INDUSTRIAL DISTRICT FUZHOU CITY, PRC CHINA,PEOPLE'SREP.OF Zixing City Government 1,503,278.91 1,503,278.91
CIVIL WORKS FOR YANGDONG WATER TREATMENT PLANT Loan 3336 27 Dec 2019 JIANGXI PROVINCIAL WATER RESOURCES AND HYDRO | NO. 312 HONGDUNAN RD. QINGYUNPU DISTRICT NANCHANG CITY, JIANGXI PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 2,502,824.22 2,502,824.22
ENVIRONMENTAL MONITORING STATIONS (12), ENVIRONMEN TAL MONITORING CENTER, FISHING MONITORING CENTER, FOREST RESOURCES (FIRE PREVENTION) MONITORING CTR Loan 3336 27 Dec 2019 JV OF LOUDI XINGCHENG CNSTRCTION ENG'G CO LTD | XIANGYANGDONG STREET, LOUXING DISTRICT, LOUDI CITY CHINA,PEOPLE'SREP.OF Zixing City Government 4,397,218.36 4,397,218.36
WATER TRANSMISSION AND DISTRIBUTION PIPELINES FOR YANGDONG WATER TREATMENT PLANT & PRESSURE REDUCING STATIONS Loan 3336 16 Dec 2019 JIANGXI PROVINCIAL WATER RESOURCES AND | NO. 312 HONGDUNAN RD., QINGYUNPU DISTRCT NANCHANG CITY, JIANGXI PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 10,396,722.36 10,396,722.36
GI-AG3 NEW AND GREEN CHEMICALS FOR PLANT DISEASE AND INSECT PEST PREVENTION Loan 3336 30 Jul 2019 LIUZHOU HUINONG CHEMICAL CO. LTD. | LIUZHOU CITY, GUANGXI PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 2,256,184.03 772,379.54
EQUIPMENT FOR YANGDONGXIA WATER TREATMENT PLANT Loan 3336 14 Nov 2019 HUAZI SCIENCE & TECHNOLOGY CO., LTD. | LUGULUSONG RD YUELU DISTR CHANGSHA CITY CHINA,PEOPLE'SREP.OF Zixing City Government 2,906,796.33 411,657.56
LIVELIHOOD SKILLS TRAINING FOR FARMERS SURROUNDING DONGJIANG LAKE Loan 3336 13 Aug 2018 ZIXING CITY VOCATIONAL EDUCATION CENTER | ZIXING CITY HUNAN CHINA,PEOPLE'SREP.OF Zixing City Government 3,087,794.00 3,071,485.00
CS1 PROJECT IMPLEMENTATION MANAGEMENT SUPPORT QCBS/FTP/80:20 Loan 3336 30 Apr 2018 HJI GROUP CORPORATION | 3200 PARK CENTER DRIVE, SUITE 1180,COSTA MESA, CA 92626, USA UNITED STATES Zixing City Government 1,387,240.00 1,387,240.00
W4-ER6 HUANGCAO LAKE WETLAND Loan 3336 17 Oct 2017 HUNAN JIANKE LANDSCAPE CO., LTD. | 16/F SHUIANTIANJI APARTMENT, NO. 153 JINNING RD., TANGDONG STREET, ZIXING CHINA,PEOPLE'SREP.OF Zixing City Government 1,061,915.00 663,540.00
G1-AG4 OTHER APPARATUS FOR PLANT DISEASE AND INSECT PEST PREVENTION Loan 3336 24 Sep 2017 JIANGSU XINTIAN ELECTRONIC TECHNOLOGY CO.,LTD | 79 ZHONGXING RD., JINTAN DISTRICT CHANGZHO CITY, SUZOU PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 1,198,412.00 1,198,412.00
G1-AG1 GREEN FERTILIZER (2016-2017) Loan 3336 24 Sep 2017 HUNAN LONGKE FERTILIZER CO., LTD. | DINGSHAN RD, SHIFENG DISTRICT, ZHUZHOU C ITY, HUNAN PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 1,327,447.00 463,689.00
G1-AG2 ORGANIC FERTILIZER (2018-2020) Loan 3336 24 Sep 2017 HUNAN TAIGU BIOTECHNOLOGY CO., LTD | ROOM 1402, 1403, BUILDING A.,BUSINESS CENTER, NO. 199 LUGULILON RD CHANGSHA CHINA,PEOPLE'SREP.OF Zixing City Government 2,163,413.00 755,699.00
CP4-ER3- COMMUNITY PARTICIPATION IN PROCUREMENT BIOLOGICAL FIRE PREVENTION BELT FOR PUBLIC-INTEREST FOREST Loan 3336 06 Aug 2017 VARIOUS | VARIOUS CHINA,PEOPLE'SREP.OF Zixing City Government 1,531,170.00 765,585.00
CP-5,CP-6,CP-7,CP-8,CP-9 COMMUNITY PARTICIPATION IN PROCUREMENT BAMBOO FOREST PACKAGES A TO E Loan 3336 06 Aug 2017 VARIOUS | VARIOUS CHINA,PEOPLE'SREP.OF Zixing City Government 8,324,815.00 4,162,408.00
CP4-ER1, CP4-ER2 COMMUNITY PARTICIPATION IN PROCUREMENT INTEGRATED ROCKY DESERTIFICATION CONTROL Loan 3336 06 Aug 2017 VARIOUS | VARIOUS CHINA,PEOPLE'SREP.OF Zixing City Government 20,140,580.00 10,070,290.00
CP4-ER4-COMMUNITY PARTICIPATION IN PROCUREMENT PEST BIOLOGICAL PREVENTION FOR PUBLIC-INTEREST FOREST Loan 3336 06 Aug 2017 VARIOUS | VARIOUS CHINA,PEOPLE'SREP.OF Zixing City Government 1,500,000.00 750,000.00
SOLID WASTE COLLECTION FACILITIES G1-SW2 Loan 3336 29 Jul 2017 ZHEJIANG KANGWEI INDUSTRY AND TRADE CO., LTD. | NO. 8 SHIJI RD., QIANCANG TOWN, YONGKANG CITY, ZHEJIANG PROVINCE CHINA,PEOPLE'SREP.OF Zixing City Government 1,670,139.00 1,670,139.00
SOLID WASTE TRANSPORT VEHICLE G1-SW3 Loan 3336 29 Jul 2017 HUNAN FENGDE ECONOMIC AND TRADE DEVELOPMENT | 21/F, CITY EXPRESS NO. 495 FURONGZHONGLU RD., CHANGSHA CITY CHINA,PEOPLE'SREP.OF Zixing City Government 2,795,441.00 2,795,441.00
XINGNING RIVER WETLAND W4-ER4 Loan 3336 29 Jul 2017 HUNAN JIAYUAN CONSTRUCTION CO., LTD. | PRC CHINA,PEOPLE'SREP.OF Zixing City Government 3,314,799.00 2,115,584.00
W3-RR2 Rehabilitation for Xingning River Loan 3336 23 Jun 2017 Chenzhou City Xianghue Hydropower | No. 46 Nanling Rd. Beihu District, Chenzhou Municipality, China, People's Rep. of Zixing City Government 2,056,069.00 1,317,299.00
G5-EM1 Environmental Monitoring Equipment, One Monitoring Center and One Ecological Research Center Loan 3336 23 Jun 2017 Yuxing Technology Development (Shenzhen) Co. | Room 401, Bldg. A, International Enterprise Center, No. 188, Huanbaozhong, China, People's Rep. of Zixing City Government 2,362,056.00 2,362,056.00
W3-RR3 Rehabilitation for Lianping and Qinya Rivers Loan 3336 14 May 2017 Changde Tianheng Construction and Devt | 2/F Times Square, No. 666, Binhu Road Wuling District, Changde City, China, People's Rep. of Zixing City Government 2,136,737.00 1,370,779.00
W4-ER1 Fish Proliferation and Fish-Breeding Base Loan 3336 31 Mar 2017 Hunan Gaoling Construction Group Ltd. | 468 Pengjiaxiang, Kaifuqu, Changsha China, People's Republic of Zixing City Government 5,776,799.98 3,636,432.46
G4-ER5 Fire Prevention Equipment for Public-Interest Forest Loan 3336 31 Mar 2017 Hunan Provincial Hydropower The First | China, People's Republic of Zixing City Government 7,884,635.38 4,963,291.82
Procurement of Bio-Digester at Aizawl Loan 3336 11 Apr 2017 The JV of Gk International Enterprises Ltd. | 28F Pinghu Tang Trade Bldg. Tianxin District, Changsha City China, People's Republic of Zixing City Government 250,817.64 157,699.34
W4-ER5 Hangxi River Wetland Loan 3336 31 Mar 2017 Chenzhou City Xiangyue | 46 Nanling Rd., Beihu District, Chenzhou Municipality China, People's Republic of Zixing City Government 1,952,260.14 1,228,926.43
W4-ER3 Riverbank Greening and Passway Wetland Loan 3336 31 Mar 2017 Hunan Jianke Landscape Co. Ltd. | China, People's Republic of Zixing City Government 2,748,332.28 1,730,045.14

Procurement Plan