India : Madhya Pradesh Power Transmission and Distribution System Improvement Project
Madhya Pradesh power transmission and distribution system served a peak demand of 8,505 megawatt (MW) and delivered 41,392 gigawatt hours (GWh) in 2012. However, the estimated peak demand was 9,151 MW, resulting in an unmet energy demand of 8,393 GWh (20% of the requirement). There are 8.21 million electricity customers in the state, of which 6.1 million were household customers with a legal power connection, representing about 60% of all households. New power connections are provided to households under a number of programs, and consumption per customer is also expected to increase in the face of robust economic growth in the state. Therefore, the demand for electricity is expected to increase and meeting this growing demand requires upgrading and expansion of the transmission and distribution network in the state.
Project Details
-
Project Officer
Banerjee, Jyotirmoy
South Asia Department
Request for information -
Country/Economy
India -
Modality
-
Sector
- Energy
Project Name | Madhya Pradesh Power Transmission and Distribution System Improvement Project | ||||
Project Number | 47100-004 | ||||
Country / Economy | India |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development |
||||
Sector / Subsector | Energy / Electricity transmission and distribution |
||||
Gender | No gender elements | ||||
Description | Madhya Pradesh power transmission and distribution system served a peak demand of 8,505 megawatt (MW) and delivered 41,392 gigawatt hours (GWh) in 2012. However, the estimated peak demand was 9,151 MW, resulting in an unmet energy demand of 8,393 GWh (20% of the requirement). There are 8.21 million electricity customers in the state, of which 6.1 million were household customers with a legal power connection, representing about 60% of all households. New power connections are provided to households under a number of programs, and consumption per customer is also expected to increase in the face of robust economic growth in the state. Therefore, the demand for electricity is expected to increase and meeting this growing demand requires upgrading and expansion of the transmission and distribution network in the state. Quality of power supply and reliability of service in MP used to be substantially below the standards expected of a modern public electricity network. The Asian Development Bank (ADB), other development partners, and the government undertook a series of investments for expansion, upgrading and reconfiguration of the transmission and distribution networks since 2001. The ADB alone has approved about $1.37 billion worth of investment projects since 2001, mainly for transmission and distribution improvements. The government's own programs includes: (i) Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) program for rural electrification; (ii) the Restructured Accelerated Power Development Reforms Program (R-APDRP), to improve electricity distribution infrastructure in urban areas; and (iii) Feeder Separation Program to limit agricultural supply to 8 hours and to provide rural households with 24-hour power supply. While the RGGVY and R-APDRP programs are nearing their completion, the feeder separation program is half way through its implementation. |
||||
Project Rationale and Linkage to Country/Regional Strategy | The proposed project undertakes transmission and distribution improvements, critical for meeting the growing demand for power in Madhya Pradesh (MP) in India. As a follow up to the previous investments in MP, the project will undertake selected transmission system improvement, distribution system improvement and capacity building. The main objectives of the project are to provide adequate transmission and distribution capacity to supply growing power demand; and reduce the system losses to ensure financial sustainability of the MP power distribution companies. | ||||
Impact | Adequate and reliable power supply in Madhya Pradesh |
Project Outcome | |
---|---|
Description of Outcome | Increased capacity and operational efficiency in the electricity transmission and distribution system in Madhya Pradesh |
Progress Toward Outcome | Implementation is in progress. |
Implementation Progress | |
Description of Project Outputs | 1. Transmission system upgraded and expanded 2. Distribution system upgraded and expanded 3. Built capacity of executing agency staff 4. Project management system in place |
Status of Implementation Progress (Outputs, Activities, and Issues) | All contracts have been awarded, implementation is ongoing. |
Geographical Location | Madhya Pradesh |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | The Environmental Monitoring reports submitted by EAs have been uploaded on ADB website. |
Involuntary Resettlement | Compliance is in line with policies and procedures. |
Indigenous Peoples | Compliance is in line with policies and procedures. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | During Project preparation, consultations were held. |
During Project Implementation | Compliance is in line with policies and procedures. |
Business Opportunities | |
---|---|
Consulting Services | The consultants will be engaged in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). |
Procurement | All procurement of goods and works shall be undertaken in accordance with ADB's Procurement Guidelines. International competitive bidding procedures shall be followed for all the packages. |
Responsible ADB Officer | Banerjee, Jyotirmoy |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | India Resident Mission (INRM) |
Executing Agencies |
Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited Madhya Pradesh Poorv Kshetra Vidyut Vitaran Co Ltd Madhya Pradesh Power Transmission Company Limited Ministry of Finance (Aid Accounts & Audit Division) |
Timetable | |
---|---|
Concept Clearance | 29 May 2013 |
Fact Finding | 05 Aug 2013 to 16 Aug 2013 |
MRM | 05 Sep 2013 |
Approval | 27 Nov 2013 |
Last Review Mission | - |
Last PDS Update | 13 Mar 2020 |
Loan 3066-IND
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
27 Nov 2013 | 17 Feb 2014 | 21 Mar 2014 | 31 Dec 2018 | 30 Sep 2020 | 03 Feb 2021 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 500.00 | Cumulative Contract Awards | |||
ADB | 350.00 | 29 Jun 2023 | 255.36 | 0.00 | 100% |
Counterpart | 150.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 29 Jun 2023 | 255.36 | 0.00 | 100% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
SUPPLY OF 100 KVA DISTRIBUTION TRANSFORMERS | Loan 3066 | 29 Oct 2019 | TOSHIBA TRANSMISSION & DISTRIBUTION SYSTEMS ( | RUDRARAM VILLAGE,PATANCHERU MANDAL, SANGAREDDY DISTRICT,TELANGANA INDIA | Madhya Pradesh Power Transmission Company Limited | 1,269,185.03 | 1,079,320.65 |
TURNKEY EXECUTION OF NEW 220KV SUB-STATIONS, TRANS MISSION LINES AND AUGMENTATION WORK/FEEDER BAY WOR K (TR 511) | Loan 3066 | 17 May 2018 | BAJAJ ELECTRICALS LTD., MUMBAI | P1 FLOOR,RUSTOMJEE ASPIREE,BHANU SHANKAR YAGNIK MARG,SION EAST,MUMBAI-400022 INDIA | Madhya Pradesh Power Transmission Company Limited | 23,747,794.00 | 20,335,391.00 |
CONSTRUCTION OF NEW 132KV SUB-STATIONS, TRANSMISSI ON LINES AND AUGMENTATION WORK/FEEDER BAY WORKS IN JABALPUR CIRCLE (TR 510) | Loan 3066 | 17 May 2018 | BAJAJ ELECTRICALS LTD., MUMBAI | P1 FLOOR,RUSTOMJEE ASPIREE,BHANU SHANKAR YAGNIK MARG,SION EAST,MUMBAI-400022 INDIA | Madhya Pradesh Power Transmission Company Limited | 16,424,207.00 | 14,082,134.00 |
TURNKEY EXECUTION OF NEW 132KV SUB-STATIONS, TRANS MISSION LINES AND AUGMENTATION WORK/FEEDER BAY WOR K IN INDORE CIRCLE (TR 512) | Loan 3066 | 17 May 2018 | BAJAJ ELECTRICALS LTD., MUMBAI | P1 FLOOR,RUSTOMJEE ASPIREE,BHANU SHANKAR YAGNIK MARG,SION EAST,MUMBAI-400022 INDIA | Madhya Pradesh Power Transmission Company Limited | 11,645,880.00 | 9,960,998.00 |
TURNKEY EXECUTION OF NEW 132KV SUB-STATIONS, TRANS MISSION LINES AND AUGMENTATION WORK/FEEDER BAY WOR K IN BHOPAL CIRCLE (TR-513) | Loan 3066 | 11 May 2018 | BAJAJ ELECTRICALS LTD., MUMBAI | P1 FLOOR,RUSTOMJEE ASPIREE,BHANU SHANKAR YAGNIK MARG,SION EAST,MUMBAI-400022 INDIA | Madhya Pradesh Power Transmission Company Limited | 11,643,031.00 | 9,878,401.00 |
SUPPLY OF 25 KVA 11/0.433 KV DISTRIBUTION TRANSFOR MER BIS LEVEL-II (D 28/LOT 1) | Loan 3066 | 04 May 2018 | MANGAL ELECTRICAL INDUSTRIAL PVT LTD, JAIPUR | C-61, ROAD NO.1C VKI AREA JAIPUR-302013 INDIA | Madhya Pradesh Power Transmission Company Limited | 1,336,309.00 | 1,126,651.00 |
SUPPLY OF 1100 VOLTS GRADE AERIAL BUNCHED XLPE CAB LE 3 X 35 1 X 16 1 X 25 SQ. MM (D-27/LOT-1) | Loan 3066 | 01 May 2018 | M/S VENKATESWAR WIRE PVT. LTD., JAIPUR | E-55 ROAD NO.5 VKI AREA JAIPUR-302015 INDIA | Madhya Pradesh Power Transmission Company Limited | 1,193,884.00 | 1,009,074.00 |
SUPPLY OF 1100 VOLTS GRADE AERIAL BUNCHED XLPE CAB LE 3 X 35 1 X 16 1 X 25 SQ. MM (D-27/LOT-II) | Loan 3066 | 01 May 2018 | RAJASTHAN CABLES & CONDUCTORS PVT LTD,JAIPUR | A-190 ROAD NO.1-D VKI AREA, JAIPUR-302013 INDIA | Madhya Pradesh Power Transmission Company Limited | 1,044,920.00 | 883,170.00 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Procurement Plan | Procurement Plans | Dec 2019 |