The Asian Development Bank is working with Afghanistan to finance investments in energy trade and regional cooperation; energy infrastructure; and energy supply to accelerate the electrification rate. The project is improving access to sustainable energy supplies across the country.
Project Name | Energy Supply Improvement Investment Program -Tranche 1 | ||||||||||||
Project Number | 47282-003 | ||||||||||||
Country | Afghanistan |
||||||||||||
Project Status | Active | ||||||||||||
Project Type / Modality of Assistance | Grant |
||||||||||||
Source of Funding / Amount |
|
||||||||||||
Strategic Agendas | Inclusive economic growth Regional integration |
||||||||||||
Drivers of Change | Partnerships |
||||||||||||
Sector / Subsector | Energy / Electricity transmission and distribution - Energy utility services |
||||||||||||
Gender Equity and Mainstreaming | No gender elements | ||||||||||||
Description | The subprojects proposed for financing under the requested PFR are: 1) 500 kV transmission line from Sheberghan to Dashte Alwan, 2) 220 kV transmission line from Andkhoy to Sheberghan, 3) project preparation facility for future energy projects and provision of analytical consulting services, and 4) program supervision and implementation consultancy. | ||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | Tranche 1 will allow expanded power imports by constructing the last missing links to forge Turkmenistan-Afghanistan interconnector. | ||||||||||||
Impact | increase in electrification rate and energy security across Afghanistan (project-defined). |
Project Outcome | |
---|---|
Description of Outcome | increased supply of imported power from Turkmenistan. |
Progress Toward Outcome | The contract was awarded in December 2019. However, there is a delay with the contract effectiveness given that the contractor refused from the advance payment. The contract will be amended to reflect the change in the effectiveness conditions. It is expected that the contract becomes effective by Q4-2020. |
Implementation Progress | |
Description of Project Outputs | 306 kilometers (approximately) of 500 kV Transmission Line from Sheberghan to Dashte Alwan operational 66 kilometers (approximately) of 220 kV Transmission Line from Sheberghan to Andkhoy completed. Future projects designed and prepared for financing by ADB and other development partners Business plan and tariff model and framework developed for DABS. 12 kilometers (approximately) of 220 kV transmission line from Mazar independent power plant (IPP) to 220 kV Mazar-e-Sharif - Sheberghan transmission line including one switchyard completed. |
Status of Implementation Progress (Outputs, Activities, and Issues) | The contract was awarded in December 2019. However, there is a delay with the contract effectiveness given that the contractor refused from the advance payment. The contract will be amended to reflect the change in the effectiveness conditions. It is expected that the contract becomes effective by Q4-2020. The 500-kV transmission line from Sherberghan to Dash-e-Alwan project contractor has been mobilized. The contractor has been commenced the preliminary activities in the project site. the overall progress of preliminary works, mobilization and survey and design works as per progress of the month of September 2020 is 65.99%. The EPC contract for 220-kV transmission line from Andkhoy to Shberghan was signed on 19 November 2017 and mobilization advance payment disbursed in December 2017. The contractor mobilized and has commenced the project survey and design works. The overall project progress is about 99.21% as of end of September 2020. The analytical studies consultancy packages for preparation of the generation and transmission projects were announced through CSRN on 22 June 2016. The original submission date of EoIs was 21 July 2016. The deadline was extended till 3 August 2016. ADB issued its no-objection to Submission 3 on 13 June 2018 and Submission 4 on 16 July 2018. The contracts award was expected by Q1 2019. The analytical studies package was rejected by NPC in December 2018. Based on the additional analysis conducted by the ADB team jointly with the Ministry of Finance and DABS, it was agreed to split the analytical studies consulting package into 5 packages: (i) update of Power Sector Master Plan, (ii) restructuring of DABS, (iii) distribution network development plan, (iv) evaluation of hydropower dams; and (v) preparation of Solar Energy Generation Project 2. The engagement of the consulting firms to: (a) update the Power Master Plan; (b) prepare distribution system development plan; (c) restructure DABS to make it efficient and operational; and (d) evaluate hydropower dams are at the procurement stage. The contract for the solar energy generation project 2 was signed in May 2020. The results of the above-listed technical assistance will serve the basis to prepare a policy-based operation to foster the energy sector reforms to make the sector financially viable and attractive to the private sector. There are delays in engaging the consultants to provide technical assistance to DABS to (i) update the Power Sector Master Plan; (ii) develop distribution network development plan; (iii) evaluate of hydropower dams; and (iv) restructure DABS. The outcomes of this technical assistance will help DABS to establish its investment, financing and operating costs requirements. The technical assistance is expected to be implemented in Q42020 subject to expeditious approval of the procurement documents by the relevant government authorities including the NPA and NPC. |
Geographical Location | Baghlan, Balkh, Faryab, Samangan, Wilayat-e Jowzjan |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | MFF-II Tranche 1 is categorized as category B in terms of its negative environmental impacts. An updated Initial Environmental Examination (IEE) report for the two turnkey projects is updated biannually and disclosed. LARP has been updated and disclosed. The revised version IDEE for IPP Mazar was reviewed and disclosed. Projects have no adverse environmental impact. Initial IEE was posted on ADB's website in October 2015. It is being implemented as project implementation and physical construction is in progress. |
Involuntary Resettlement | A resettlement plan has been updated and posted on ADB's website in Feb (Q1) 2019. It is being updated periodically as project implementation and physical construction is in progress. The social safeguards due diligence reports for the 500kV Sheberghan-Dasht-e-Alwan Transmission Line (Faryab, Samangan, Jawzjan, and Balk provinces) were disclosed in May 2020. The social safeguards due diligence report for the 500kV Sheberghan-Dasht-e-Alwan Transmission Line (Baghlan province) was disclosed in July 2020. The Resettlement Plan for the 220kV Sheberghan to Andkhoy Transmission Line project was disclosed in August 2020. |
Indigenous Peoples | No impact on indigenous peoples. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | ADB project team and the project implementation consultant consulted the stakeholders during project design and preparation. This is reflected in project documentation |
During Project Implementation | Periodic consultative meetings are being scheduled starting from June 2018. The project consultative meeting is held bimonthly to update the progress and discuss the project issues accordingly. |
Business Opportunities | |
---|---|
Consulting Services | Consultants to be recruited using Quality-Based Selection (QBS) method following ADB Guidelines on the Use of Consultants (2013, as amended from time to time) |
Procurement | Project works to be carried out under turnkey contracts procured through international competitive bidding following ADB's Procurement Guidelines (2013, as amended from time to time) |
Responsible ADB Officer | Mukhamedova, Takhmina |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Energy Division, CWRD |
Executing Agencies |
Da Afghanistan Breshna Sherkat [email protected] Chaman Houzouri, Kabul, Islamic Republic of Afghanistan |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | 27 Oct 2015 |
Approval | 08 Dec 2015 |
Last Review Mission | - |
Last PDS Update | 28 Oct 2020 |
Grant 0464-AFG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
08 Dec 2015 | 19 Dec 2015 | 07 Apr 2016 | 31 Dec 2020 | 31 Dec 2023 | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 230.00 | Cumulative Contract Awards | |||
ADB | 220.00 | 08 Dec 2015 | 64.47 | 0.00 | 59% |
Counterpart | 10.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 08 Dec 2015 | 32.85 | 0.00 | 30% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | - | - | - | Partly satisfactory | Partly satisfactory | Partly satisfactory |
Grant 0465-AFG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
08 Dec 2015 | 19 Dec 2015 | 07 Apr 2016 | 31 Dec 2020 | 31 Dec 2023 | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 70.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 08 Dec 2015 | 0.00 | 34.28 | 98% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 70.00 | 08 Dec 2015 | 0.00 | 25.04 | 72% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
ADB $1.2 Billion Grant to Support Afghanistan’s Energy Security
ADB has approved $1.2 billion in grants to reinforce ongoing energy projects in Afghanistan and to provide new funds to boost energy supply, improve power sector efficiency, and promote cross border trade in energy.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Senior Accountant | Individual - Consulting | Closed | 22 Jan 2021 | 28 Jan 2021 |
Accountant | Individual - Consulting | Closed | 22 Jan 2021 | 28 Jan 2021 |
Electrical Design Engineers | Individual - Consulting | Closed | 25 Nov 2020 | 01 Dec 2020 |
Surveyors civil engineers 4 | Individual - Consulting | Closed | 25 Nov 2020 | 01 Dec 2020 |
Surveyors civil engineers 2 | Individual - Consulting | Closed | 25 Nov 2020 | 01 Dec 2020 |
Team Leader / Transmission Line design Engineer | Individual - Consulting | Closed | 25 Oct 2020 | 31 Oct 2020 |
Recruitment of Civil/Structural Design Engineer | Individual - Consulting | Closed | 25 Oct 2020 | 31 Oct 2020 |
Electrical Design Engineer | Individual - Consulting | Closed | 25 Oct 2020 | 31 Oct 2020 |
Surveyors Electrical engineers 3 | Individual - Consulting | Closed | 25 Oct 2020 | 31 Oct 2020 |
Contract Management Specialist | Individual - Consulting | Closed | 19 Oct 2020 | 01 Nov 2020 |
Civil/Structural Design Engineer | Individual - Consulting | Closed | 17 Aug 2020 | 23 Aug 2020 |
Surveyors civil engineers 3 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Surveyors Electrical engineers 4 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Surveyors electrical engineers 2 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Surveyors electrical engineers 3 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Team Leader (Distribution Network Design Expert) | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Electrical Design Engineer 2 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Surveyors civil engineers 1 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Surveyors Electrical engineers 1 | Individual - Consulting | Closed | 16 Aug 2020 | 22 Aug 2020 |
Portfolio Management Advisor | Individual - Consulting | Closed | 17 Jul 2020 | 23 Jul 2020 |
Team Leader/Substation Design Engineer (1 Expert for 8-Person Months - International) | Individual - Consulting | Closed | 14 Jul 2020 | 28 Jul 2020 |
Surveyors site civil engineers 2 | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Surveyors Electrical engineers 1 | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Geotechnical Expert | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Surveyors site civil engineers 1 | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Surveyors Electrical engineers 2 | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Surveyors site civil engineers 3 | Individual - Consulting | Closed | 02 Jun 2020 | 24 Jun 2020 |
Consultancy package for project preparation consulting services NPA/DABS/99/CS-5900/QCBS | Firm - Consulting | Closed | 01 Jun 2020 | 15 Jul 2020 |
Substation Protection System Design Engineer – International | Individual - Consulting | Closed | 14 Nov 2019 | 05 Dec 2019 |
Electrical Design Engineer – National | Individual - Consulting | Closed | 14 Nov 2019 | 05 Dec 2019 |
Civil/Structural Design Engineer – International | Individual - Consulting | Closed | 14 Nov 2019 | 05 Dec 2019 |
Surveyor (Civil) – National | Individual - Consulting | Closed | 14 Nov 2019 | 05 Dec 2019 |
Procurement Expert | Individual - Consulting | Closed | 12 May 2019 | 18 May 2019 |
Legal Expert | Individual - Consulting | Closed | 12 May 2019 | 18 May 2019 |
Transmission Line Engineer | Individual - Consulting | Closed | 12 May 2019 | 18 May 2019 |
Power Economist/Financial Expert/Team Leader | Individual - Consulting | Closed | 12 May 2019 | 18 May 2019 |
Grant Nos. 0464/0465-AFG: Energy Supply Improvement Investment Program -Tranche 1 [NPA/DABS/97/W-2199/ICB] | Invitation for Bids | Closed | 23 Apr 2019 | 01 Jul 2019 |
Consultancy services of project preparatory consultant for Solar Energy Generation project 2 | Firm - Consulting | Closed | 03 Mar 2019 | 17 Mar 2019 |
Grant-0464/0465 AFG: MMF-2 Tranche 1 – Request for Recruitment of Individual Consultants for Herat City Gas Utilization and Market Study | Individual - Consulting | Closed | 27 Nov 2018 | 03 Dec 2018 |
Topographic, Geo technical and Hydro logical Investigations Expert (National) -2 Person- Months / 3 Different Tasks | Individual - Consulting | Closed | 27 Oct 2018 | 02 Nov 2018 |
Energy Supply Improvement Investment Program- T 1: Request for Recruitment of Individual Consultants for Pule Hashimi to Shindand 188 KM 220 kV Transmission Line (TL, Shindand to Farah 200 KM 220 kV TL, 2x16 MVA Substat | Individual - Consulting | Closed | 27 Sep 2018 | 03 Oct 2018 |
Economic and Financial 2 Experts for 6 Months Each - National | Individual - Consulting | Closed | 27 Sep 2018 | 03 Oct 2018 |
Environmental Specialist 2 Experts for 6 Person Month Each - National | Individual - Consulting | Closed | 27 Sep 2018 | 03 Oct 2018 |
Recruitment of Power System 2 Experts for 6-Person Months Each - National) | Individual - Consulting | Closed | 27 Sep 2018 | 03 Oct 2018 |
Gas Sector Business Planning Specialist | Individual - Consulting | Closed | 24 Jun 2018 | 28 Jun 2018 |
Downstream Gas Development Specialist | Individual - Consulting | Closed | 24 Jun 2018 | 28 Jun 2018 |
Senior Solar Energy Specialist | Individual - Consulting | Closed | 31 May 2018 | 04 Jun 2018 |
Solar Photo-voltaic Power Specialist | Individual - Consulting | Closed | 15 May 2018 | 21 May 2018 |
Senior Regulatory Management Support and Legal Specialist | Individual - Consulting | Closed | 13 May 2018 | 19 May 2018 |
Team Leader Regulatory Specialist | Individual - Consulting | Closed | 13 May 2018 | 19 May 2018 |
Senior Gas Development Specialist (Team Leader) | Individual - Consulting | Closed | 09 May 2018 | 20 May 2018 |
Regulatory Specialist - Team Leader | Individual - Consulting | Closed | 15 Mar 2018 | 21 Mar 2018 |
Senior Energy Specialist (National) | Individual - Consulting | Closed | 15 Mar 2018 | 21 Mar 2018 |
Senior Regulatory Management Support and Legal Specialist | Individual - Consulting | Closed | 05 Feb 2018 | 11 Feb 2018 |
Financial Manager for Electric Power Utility (International) | Individual - Consulting | Closed | 27 Dec 2017 | 02 Jan 2018 |
Senior Regulatory Specialist (International) | Individual - Consulting | Closed | 27 Dec 2017 | 02 Jan 2018 |
Electric Power Utility Regulatory Expert | Individual - Consulting | Closed | 27 Dec 2017 | 02 Jan 2018 |
Financial Accountant for Electric Power Utility | Individual - Consulting | Closed | 27 Dec 2017 | 02 Jan 2018 |
Senior Energy Specialist | Individual - Consulting | Closed | 27 Dec 2017 | 02 Jan 2018 |
Senior procurement/ Contract Specialist | Individual - Consulting | Closed | 25 Oct 2017 | 31 Oct 2017 |
Senior Solar Specialist | Individual - Consulting | Closed | 25 Oct 2017 | 31 Oct 2017 |
Preparation of Future projects and Analytical Studies | Individual - Consulting | Closed | 14 Aug 2017 | 21 Aug 2017 |
Preparation of Future projects and Analytical Studies | Individual - Consulting | Closed | 14 Aug 2017 | 21 Aug 2017 |
Preparation of Future projects and Analytical Studies | Individual - Consulting | Closed | 14 Aug 2017 | 21 Aug 2017 |
Preparation of Future projects and Analytical Studies | Individual - Consulting | Closed | 14 Aug 2017 | 21 Aug 2017 |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
PROJECT PREPARATORY CONSULTANT FOR SOLAR ENERGY GENERATION PROJECT 2 (ADB/97/CS-1) | Grant 0464 | 31 May 2020 | AF-CONSULT SWITZERLAND LTD. IN ASSOCIATION W/ | TAFERSTRASSE 26 CH-5401 BADEN/DATTWIL SWITZERLAND | Da Afghanistan Breshna Sherkat | 634,454.00 | — | |
PROCUREMENT OF PLANT DESIGN SUPPLY INSTALLATION TESTING AND COMMISSIONING OF 12KM 220KM TRANSMIS | Grant 0464 | 14 Dec 2019 | JOINT STOCK COMPANY TOJIKGIDORELECTROMONTAJ | MR. SAFAROV IBBOL GENERAL DIRECTOR N.NUVAYDULLAEV STREET 377/1 DUSHANBE TAJIKISTAN REP. OF | Da Afghanistan Breshna Sherkat | 5,080,278.65 | — | |
POWER ECONOMIST AND FINANCIAL EXPERT/TEAM LEADER | Grant 0464 | 15 Jul 2019 | DON JOSEPH TILAK SIYAMBALAPITIYA | 110 KATTUWA NEGOMBO SRI LANKA SRI LANKA 11500 SRI LANKA | Da Afghanistan Breshna Sherkat | CONSULTANCY | 115,000.00 | — |
PROC OF PLANT DESIGN SUPPLY INSTLLN TESTNG & COMMSING OF 500KV TRANSMISSION LINE FR SHEBERGHAN | Grant 0464 | 19 Nov 2017 | KEC INTERNATIONAL LIMITED | CEAT MAHAL 1ST FLR DR ANNIE BESANT RD WORLI MUMBAI 400 030 INDIA INDIA | Da Afghanistan Breshna Sherkat | 4,952,780.00 | — | |
PROC OF PLANT DESIGN SUPPLY INSTLLN TESTING & COMMSNG OF 220KV TRANSMISSION LINE FROM SHEBERGHAN | Grant 0464 | 19 Nov 2017 | KALPATARU POWER TRANSMISSION LTD. | 101 PART III GIDC ESTATE SECTOR 28 GANDHINAGAR-380 028 GUJARAT INDIA INDIA | Da Afghanistan Breshna Sherkat | 14,961,219.00 | — | |
PROC OF PLANT DESIGN SUPPLY INSTALLN TESTING & COMMSNG OF 500KV TRANSMISSION LINE FR SHEBERGHAN | Grant 0465 | 19 Nov 2017 | KEC INTERNATIONAL LIMITED | CEAT MAHAL 1ST FLR DR ANNIE BESANT ROAD WORLI MUMBAI 400 030 INDIA INDIA | Da Afghanistan Breshna Sherkat | 55,000,000.00 | — |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Energy Supply Improvement Investment Program -Tranche 1: Procurement Plan | Procurement Plans | Apr 2020 |