Afghanistan: Energy Supply Improvement Investment Program Tranche 5
Project Details
-
Project Officer
ADB Disclosure
Central and West Asia Department
Request for information -
Country/Economy
Afghanistan -
Sector
- Energy
Related Projects
Project Name | Energy Supply Improvement Investment Program Tranche 5 | ||||
Project Number | 47282-008 | ||||
Country / Economy | Afghanistan |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Grant |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Private sector development |
||||
Sector / Subsector | Energy / Electricity transmission and distribution |
||||
Gender Equity and Mainstreaming | Some gender elements | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | For 220/20 kV substation at Kunar, the notice to proceed was issued on 27 June 2020 and mobilization of contractor is in process. As for the turnkey package for 220/20 kV substation at Sharana and 220 kV line bay extension at Ghazni substation, advance payment for mobilization of contractor was disbursed on 4 August 2020 and the contractor is still to be mobilized. |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | ADB issued no objection on draft bid documents for 220/20 kV substation at Kunar on 18 February 2019, IFB was published on 13 March 2019, and bids were opened on 2 June 2019. ADB issued no objection for contract award on 18 December 2019, and contract was signed on 31 December 2019 with Turkey Firm, Best Elektrik. The notice to proceed was issued on 27 June 2020. Mobilization of contractor is in process. ADB issued the no objection letter on draft bid documents for 220/20-kV substation at Sharana and 220 kV line bay at Ghazni Station on 21 May 2019, IFB was published on 27 May 2019, and bids were opened on 25 September 2019. ADB issued no objection for contract award on 29 January 2020 and contract was signed on 8 March 2020 with VICC-Metro Elektrik JV. Advance payment for mobilization of contractor was disbursed on 4 August 2020. The contractor is still to be mobilized. Activities ongoing. Activities ongoing. Activities ongoing. ADB issued no objection letter on draft bid documents for 220-kV double circuit transmission line from Jalalabad to Kunar on 18 February 2019, IFB was published on 13 March 2019, and bids were opened on 1 June 2019. ADB issued no objection letter for contract award on 23 January 2020. Contract signing was on 9 May 2020. ADB issued Commitment Letter for L/C. Advance payment for mobilization of contractor was disbursed on 7 August 2020. The L/C was already established. ADB issued the no objection letter on draft bid documents for 220-kV transmission line from Ghazni to Sharana on 20 May 2019, IFB was published on 27 May 2019, and bids were opened on 24 September 2019. ADB issued the no objection letter on the Financial Bid Evaluation report on 3 August 2020. |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | The environmental impacts are envisaged as site-specific and temporary. Those impacts can be mitigated through careful line routing, resilient design and by EMP implementation. |
Involuntary Resettlement | No civil works will start until the LARP is fully implemented by DABS. The LARP implementation will be monitored semiannually with reports submitted for ADB's review. |
Indigenous Peoples | The field survey found that no ethnic minority, as defined by SPS, is involved or affected. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Being undertaken at project survey and preparatory phase. |
During Project Implementation | Additional consultative meetings will be scheduled once detailed design of the project is completed. |
Business Opportunities | |
---|---|
Procurement | Procurement of works and goods will follow ADB's Procurement Policy (2017, as amended from time to time) using open competitive bidding for the turnkey contract packages. |
Responsible ADB Officer | ADB Disclosure |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Energy Division, CWRD |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | 25 Oct 2018 |
Approval | 06 Dec 2018 |
Last Review Mission | - |
Last PDS Update | 30 Sep 2020 |
Grant 0634-AFG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
06 Dec 2018 | 09 Dec 2018 | 14 Mar 2019 | 31 Dec 2023 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 148.00 | Cumulative Contract Awards | |||
ADB | 143.42 | 30 Sep 2020 | 64.09 | 0.00 | 53% |
Counterpart | 4.58 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 30 Sep 2020 | 11.36 | 0.00 | 9% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | - | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.