Kiribati: Strengthening Economic Management Reform Program (Subprogram 1)
Project Details
-
Project Officer
Wyatt, Pamela
Pacific Department
Request for information -
Country/Economy
Kiribati -
Sector
- Public sector management
Related Projects
Project Name | Strengthening Economic Management Reform Program (Subprogram 1) | ||||||||||||
Project Number | 47322-001 | ||||||||||||
Country / Economy | Kiribati |
||||||||||||
Project Status | Closed | ||||||||||||
Project Type / Modality of Assistance | Grant |
||||||||||||
Source of Funding / Amount |
|
||||||||||||
Strategic Agendas | Inclusive economic growth Regional integration |
||||||||||||
Drivers of Change | Governance and capacity development Partnerships |
||||||||||||
Sector / Subsector | Public sector management / Public expenditure and fiscal management |
||||||||||||
Gender Equity and Mainstreaming | No gender elements | ||||||||||||
Description | |||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||||
Impact | Stable macroeconomic framework achieved (Kiribati Development Plan, 2016 2019) |
Project Outcome | |
---|---|
Description of Outcome | Overall economic management improved |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Public finances, public assets and liabilities improved Environment for the private sector improved |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Wyatt, Pamela |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | PASP |
Executing Agencies |
Ministry of Finance and Economic Development [email protected] P.O. Box 67 Bairiki, Tarawa Kiribati Ministry of Finance and Economic Development P.O. Box 67 Bairiki, Tarawa Kiribati Republic of Kiribati * |
Timetable | |
---|---|
Concept Clearance | 09 Oct 2017 |
Fact Finding | 19 Jun 2017 to 26 Jun 2017 |
MRM | 26 Oct 2017 |
Approval | 14 Dec 2017 |
Last Review Mission | - |
Last PDS Update | 12 Jun 2019 |
Grant 0560-KIR
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
14 Dec 2017 | 15 Dec 2017 | 15 Dec 2017 | 31 May 2018 | - | 19 Feb 2018 |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 12.40 | Cumulative Contract Awards | |||
ADB | 5.00 | 17 Jun 2022 | 5.00 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 7.40 | 17 Jun 2022 | 5.00 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Strengthening Economic Management Reform Program: Subprograms 1 and 2 Completion Report | Project/Program Completion Reports | Mar 2021 |
Grant Agreement (Special Operations) for Grant 0560-KIR: Strengthening Economic Management Reform Program, Subprogram 1 | Agreements | Dec 2017 |
Strengthening Economic Management Reform Program, Subprogram 1: Report and Recommendation of the President | Reports and Recommendations of the President | Nov 2017 |
Strengthening Economic Management Reform Program, Subprogram 1: Concept Paper | Concept Papers | Oct 2017 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Kiribati: Strengthening Economic Management Reform Program (Subprograms 1 and 2) | Validations of Project Completion Reports | Jul 2021 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.