Pakistan : Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing)
The additional financing will widen the 42 km road section between Mardan and Swabi. The additional financing will further strengthen the capacity of the CWD by supporting the government to develop a Khyber Pakhtunkhwa road network master plan for the next 20 years, and by building a central laboratory for the PKHA and providing training to CWD staff.
Project Details
-
Project Officer
Ghafoor, Khurram
Central and West Asia Department
Request for information -
Country/Economy
Pakistan -
Sector
- Transport
Project Name | Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing) | ||||
Project Number | 47360-003 | ||||
Country / Economy | Pakistan |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||
Gender | Some gender elements | ||||
Description | The additional financing will widen the 42 km road section between Mardan and Swabi. The additional financing will further strengthen the capacity of the CWD by supporting the government to develop a Khyber Pakhtunkhwa road network master plan for the next 20 years, and by building a central laboratory for the PKHA and providing training to CWD staff. | ||||
Project Rationale and Linkage to Country/Regional Strategy | Pakistan's economy is largely driven by strong growth in domestic consumption, recovery in agricultural production, and a marginal recovery in foreign direct investments. However, it is constrained by an inefficient transport system with poor levels of service. Road transport dominates Pakistan's transport system, accounting for almost 96% of freight traffic in ton-km and 92% of passenger traffic in passenger-km. Khyber Pakhtunkhwa is even more reliant on road transport. Khyber Pakhtunkhwa has the third-largest provincial economy in Pakistan. Despite major challenges such as waging war on terrorism (with huge spending on law and order), confronting power load shedding, and having the highest population growth rate, Khyber Pakhtunkhwa recorded the highest economic growth rate in the country. Outperforming the other four provinces in 2013- 2017, Khyber Pakhtunkhwa registered an average growth of 5.1% against a national average of 4.5% for the same period. The growth rate could have been higher if road transport connectivity had been better, especially between major cities, because it would have reduced the transport cost of products and improved transport efficiency. The existing provincial roads are much below the desired standard both in terms of length and pavement condition. Of Khyber Pakhtunkhwa's total road network of 15,102 km, 1,878 km is classified as provincial roads. These play a vital role in the economic development of the province by connecting district centers to the national highway network and the provincial capital, Peshawar, with commercial centers, district headquarters, and market towns. Provincial roads support intraprovincial trade and commerce as well as access to health, education, and other public services; and reduce poverty by creating jobs and business opportunities. The damaging effects of heavy axle loads, vulnerability to natural disasters, and limited financial resources for road maintenance are putting tremendous strain on the road network in Khyber Pakhtunkhwa. Its performance is fast deteriorating because of high traffic accident rates, reduced pavement life, increased vehicle operating costs, and, crucially, a backlog in road maintenance and rehabilitation. In fact, only 27% of the provincial roads maintained by the Pakhtunkhwa Highways Authority (PKHA) are in fair to good condition; the rest is in poor condition. The Asian Development Bank (ADB) approved a loan of $140.0 million, including a concessional loan of $18.5 million, on 28 November 2017 for the Khyber Pakhtunkhwa Provincial Road Improvement Project to rehabilitate eight key road sections of provincial roads over a total length of 214 km, and improve transport efficiency and road safety. In May 2018, the Government of Khyber Pakhtunkhwa requested additional financing to dualize most of the existing two-lane road between Mardan and Swabi. Although most of that section is in fair condition, the dualization serves to efficiently and effectively accommodate an increase in goods vehicles: trucks carrying locally quarried stone and other construction materials, and trucks and tractor-trailers carrying agricultural and forestry products. The Mardan-Swabi road runs for 53.9 km through Khyber Pakhtunkhwa's agricultural heartland between the Indus and Kabul rivers. It connects Mardan, the second-largest city in Khyber Pakhtunkhwa, and Swabi, a college city and the capital of the fourth most populated district in Khyber Pakhtunkhwa. The road is a two-lane single carriageway with urbanized sections (strip development) and suffers from chronic traffic congestion and unsafe operating conditions. The current mix of fast- and slow-moving traffic, dominated by motorcycles and rickshaws, imposes constraints on speed and increases the risk of collisions. The average daily traffic between Mardan and Swabi is about 7,000 vehicles (excluding motorcycles and rickshaws), of which about 15% are heavy trucks, and traffic has been growing at an average 3.4% annually. The highway supports various agricultural, industrial, commercial, and educational activities. Most notable from a traffic generation point of view are the Premier Sugar Mill and Distillery in Mardan; several textile and edible-oil mills; quarries; public universities, Mishal Medical Complex, and numerous private colleges and academies; a police training school; Shewa Adda Camp for internally displaced persons; and markets that serve the surrounding rural areas. Nearby Rashakai, on the M-1 motorway, was dubbed the _Technology City_ and is expected to develop into a high-tech industrial zone as part of the China-Pakistan Economic Corridor initiative. However, traffic surveys along the Mardan Swabi road clearly indicate that the current peak traffic volumes already exceed the road's capacity. Accordingly, the proposed dualization of 42 km of the road into a dual-carriageway, four-lane highway has high public investment priority. |
||||
Impact | An efficient and integrated transportation network established |
Project Outcome | |
---|---|
Description of Outcome | Efficiency and safety along key sections of the Khyber Pakhtunkhwa provincial road network improved |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Provincial roads rehabilitated The CWD's institutional capacity for road maintenance strengthened |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Khyber Pakhtunkhwa |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | The consultants for construction supervision and development of KP master plan will be recruited in accordance with ADB's Guidelines on the Use of Consultants (March 2013, as amended from time to time). |
Procurement | Goods and civil works will be procured in accordance with ADB's Procurement Guidelines (April 2015, as amended from time to time). |
Responsible ADB Officer | Ghafoor, Khurram |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Pakistan Resident Mission |
Executing Agencies |
Communication and Works Department, KP [email protected] Civil Secretariat, Peshawar, KPK Government of Khyber Pakhtunkhwa (KP) [email protected] Sarhad Hydel Development Organization, 372-WAPDA House, Shami Road, Peshawar, NWFP, PAKISTAN Pakhtunkhwa Highways Authority, Peshawar [email protected] Block B, Attached Department Complex Near Treasury Office Khyber Road Peshawar |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | 07 May 2018 to 18 May 2018 |
MRM | 23 Oct 2018 |
Approval | 07 Dec 2018 |
Last Review Mission | - |
Last PDS Update | 12 Jun 2019 |
Loan 3756-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
07 Dec 2018 | 26 Feb 2019 | 25 Jun 2019 | 30 Jun 2024 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 85.00 | Cumulative Contract Awards | |||
ADB | 75.00 | 07 Dec 2018 | 43.26 | 0.00 | 58% |
Counterpart | 10.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 07 Dec 2018 | 14.43 | 0.00 | 19% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Unsatisfactory | Partly satisfactory | Partly satisfactory | Unsatisfactory | - | Unsatisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Project Agreement for Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing) | Project/Program Agreements | Feb 2019 |
Loan Agreement (Ordinary Operations) for Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing) | Loan Agreement (Ordinary Resources) | Feb 2019 |
Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project: Report and Recommendation of the President | Reports and Recommendations of the President | Nov 2018 |
Khyber Pakhtunkhwa Provincial Roads Improvement Project: Project Administration Manual | Project/Program Administration Manual | Nov 2018 |
Khyber Pakhtunkhwa Provincial Roads Improvement Project: Procurement Plan | Procurement Plans | Apr 2018 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB Provides $75 Million to Upgrade Mardan–Swabi Road in Khyber Pakhtunkhwa
ADB and the Government of Pakistan today signed a loan agreement for $75 million to widen and upgrade 42 kilometers (km) of the busy Mardan–Swabi road in the Khyber Pakhtunkhwa province in Pakistan.ADB Provides Additional Financing to Improve Roads in Khyber Pakhtunkhwa
ADB has approved a $75 million loan as additional financing for a project that aims to improve road conditions, capacity, and road safety on provincial roads in Khyber Pakhtunkhwa in Pakistan. The additional funding will widen...
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing) [ADB/NCB/KPPRIP(AF)/CW-02] | Invitation for Bids | Closed | ||
Construction Supervision | Firm - Consulting | Closed | ||
Loan No. 47360-PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project [ADB/ICB/PRIP] | Invitation for Bids | Closed |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
LOT 1 - MARDAN-SWABI ROAD (KM00 TO KM22 ) | Loan 3756 | 09 Jul 2019 | METALLURGICAL CORP. OF CHINA | MAIN SHIKARPUR ROAD, NARA STOP, SUKKUR PAKISTAN CHINA,PEOPLE'SREP.OF | Government of Khyber Pakhtunkhwa(KP) | 21,867,336.18 | 19,694,428.78 |
LOT 2 - DUALIZATION OF MARDAN-SWABI ROAD (KM22 TO END) | Loan 3756 | 09 Jul 2019 | METALLURGICAL CORP. OF CHINA | MAIN SHIKARPUR ROAD, NARA STOP, SUKKUR, PAKISTAN CHINA,PEOPLE'SREP.OF | Government of Khyber Pakhtunkhwa(KP) | 20,878,764.78 | 18,804,089.47 |
CONSTRUCTION SUPERVISION CONSULTANT FOR DUALIZATION OF MARDAN-SWABI ROAD | Loan 3756 | 18 Jul 2019 | ASSOCIATED CONSULTANCY CENTER JV CREATIVE | PLAZA 1-B, STREET NO. 57, SECTOR G-9/4 ISLAMABAD PAKISTAN | Government of Khyber Pakhtunkhwa(KP) | 1,658,001.98 | 1,658,001.98 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Khyber Pakhtunkhwa Provincial Roads Improvement Project: Procurement Plan | Procurement Plans | Apr 2018 |