Timor-Leste : Urban Services Improvement Sector Project
The project preparatory TA will: (i) conduct assessments of existing water supply and solid waste management systems, including surveys and stakeholder consultations; (ii) develop water supply and solid waste investment strategies for Dili to help identify and prioritize project components for the ensuing loan project; (iii) determine the feasibility of the proposed investments for priority infrastructure and systems improvements, (iv) ensure that detailed design work supervised by DNSA is carried out to the required quality, and (v) identify appropriate project management arrangements to ensure that MOP and Estatal have adequate capacity to implement the project.
Project Details
-
Project Officer
Ribeiro, Tiago
Southeast Asia Department
Request for information -
Country/Economy
Timor-Leste -
Modality
-
Sector
- Water and other urban infrastructure and services
Project Name | Urban Services Improvement Sector Project | ||||||||||
Project Number | 47364-001 | ||||||||||
Country / Economy | Timor-Leste |
||||||||||
Project Status | Closed | ||||||||||
Project Type / Modality of Assistance | Technical Assistance |
||||||||||
Source of Funding / Amount |
|
||||||||||
Strategic Agendas | Inclusive economic growth |
||||||||||
Drivers of Change | Governance and capacity development Knowledge solutions Partnerships |
||||||||||
Sector / Subsector | Water and other urban infrastructure and services / Urban solid waste management - Urban water supply |
||||||||||
Gender | No gender elements | ||||||||||
Description | The project preparatory TA will: (i) conduct assessments of existing water supply and solid waste management systems, including surveys and stakeholder consultations; (ii) develop water supply and solid waste investment strategies for Dili to help identify and prioritize project components for the ensuing loan project; (iii) determine the feasibility of the proposed investments for priority infrastructure and systems improvements, (iv) ensure that detailed design work supervised by DNSA is carried out to the required quality, and (v) identify appropriate project management arrangements to ensure that MOP and Estatal have adequate capacity to implement the project. | ||||||||||
Project Rationale and Linkage to Country/Regional Strategy | The Government of the Democratic Republic of Timor-Leste has requested the Asian Development Bank (ADB) a project preparatory technical assistance (TA) to prepare the Urban Water Supply and Solid Waste Improvement Sector Project. The TA is required to: (i) assist DNSA to plan and prioritize investments to improve water supply services in Dili, (ii) assist DNSB and Dili District Administration to identify and prioritize investments to improve solid waste management in Dili, (iii) assess technical suitability, economic and financial viability, capacity and institutional issues, and environmental and social soundness of the project, and (v) identify measures to strengthen project implementation capacity of DNSA and DNSB. | ||||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Household surveys, focus groups, and formal and informal consultations were carried out during project preparation into order to inform the project design, and to develop the stakeholder consultant and participation plan. |
During Project Implementation | The stakeholder consultation and participation plan will provide the basis for stakeholder outreach activities during project implementation. Further engagement with the newly established directorate responsible for Urban Organization under Ministry of State Administration has been strengthened and to present the output on Solid Waste Management in Dili |
Business Opportunities | |
---|---|
Consulting Services | An international water supply specialist and a national water supply specialist will be engaged as individual consultants. The remaining consultants will be recruited through a firm using the quality-and cost-based selection method. A quality-cost ratio of 80:20 will be applied, and simplified technical proposal procedures will be followed to engage the firm. ADB will select and engage consultants in accordance with ADB's Guidelines on Use of Consultants (2013, as amended from time to time). |
Responsible ADB Officer | Ribeiro, Tiago |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Urban Development and Water Division, SERD |
Executing Agencies |
Ministry of Public Works |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | 07 Nov 2014 |
Last Review Mission | - |
Last PDS Update | 28 Mar 2018 |
TA 8750-TIM
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
07 Nov 2014 | 02 Dec 2014 | 02 Dec 2014 | 30 Jun 2016 | 30 Jun 2018 | 27 Aug 2018 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
1,300,000.00 | 180,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,480,000.00 | 11 Aug 2022 | 1,449,352.69 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Urban Services Improvement Sector Project: Technical Assistance Completion Report | TA Completion Reports | Aug 2022 |
Urban Services Improvement Sector Project: Project Preparatory Technical Assistance Report | Project Preparatory Technical Assistance Reports | Oct 2015 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Timor-Leste: Urban Services Improvement Sector Project | Validation of Technical Assistance Completion Reports | Dec 2023 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Project Preparatory | Technical Assistance 8750 | 18 May 2016 | Seureca (France) | 36 RUE DE LIEGE PARIS 75008 FRANCE | Ministry of Public Works, Transport and Communications | 443,318.00 | — |
Procurement Plan
None currently available.