Georgia : Improving Domestic Resource Mobilization for Inclusive Growth Program (Subprogram 3)

Sovereign Project | 48044-005

Project Name
Improving Domestic Resource Mobilization for Inclusive Growth Program (Subprogram 3)
Project Number
48044-005
Country / Economy
  • Georgia
Project Status
Closed
Project Type / Modality of Assistance
  • Loan
Source of Funding / Amount
Loan 3417-GEO: Improving Domestic Resource Mobilization for Inclusive Growth Program, Subprogram 3
Source Amount
Ordinary capital resources US$ 50.00 million
Loan 3418-GEO: Improving Domestic Resource Mobilization for Inclusive Growth Program, Subprogram 3
Source Amount
Asian Development Fund US$ 50.00 million
Strategic Agendas
  • Inclusive economic growth
Drivers of Change
  • Gender Equity and Mainstreaming
  • Governance and capacity development
  • Knowledge solutions
  • Partnerships
  • Private sector development
Sector / Subsector
  • Finance / Finance sector development - Insurance and contractual savings - Money and capital markets

  • Public sector management / Public expenditure and fiscal management

Gender
Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Citizens, particularly women, benefit from higher living standards and more employment opportunities

Project Outcome

Description of Outcome

Effective mobilization of domestic resources for increased public and private investment

Progress Toward Outcome

Implementation Progress

Description of Project Outputs

1.Improved treasury management of debt, cash, and fiscal risk

2.Strengthened public revenue and expenditure management

3.Enhanced generation of domestic savings

4.Increased mobilization of private resources for investment

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Nation-wide

Safeguard Categories

Environment
C
Involuntary Resettlement
C
Indigenous Peoples
C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Tariq Niazi
Responsible ADB Department
Central and West Asia Department
Responsible ADB Division
Public Management, Financial Sector and Trade Division, CWRD
Executing Agencies
Ministry of Finance

Timetable

Concept Clearance
-
Fact Finding
02 Jun 2016 to 11 Jun 2016
MRM
29 Jun 2016
Approval
31 Aug 2016
Last Review Mission
-
Last PDS Update
14 Sep 2016

Funding

Loan 3417-GEO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
31 Aug 2016 01 Sep 2016 06 Dec 2016 31 Dec 2016 - 30 Dec 2016
Financing Plan
  Total (Amount in US$ million)
Project Cost 50.00
ADB 50.00
Counterpart 0.00
Cofinancing 0.00
Loan Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 17 Jun 2022 50.00 0.00 100%
Cumulative Disbursements 17 Jun 2022 50.00 0.00 100%

Loan 3418-GEO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
31 Aug 2016 01 Sep 2016 06 Dec 2016 31 Dec 2016 - 30 Dec 2016
Financing Plan
  Total (Amount in US$ million)
Project Cost 50.00
ADB 50.00
Counterpart 0.00
Cofinancing 0.00
Loan Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 17 Jun 2022 48.70 0.00 100%
Cumulative Disbursements 17 Jun 2022 48.70 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Georgia: Improving Domestic Resource Mobilization for Inclusive Growth Program Validations of Project Completion Reports Dec 2018

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.