Georgia : Improving Domestic Resource Mobilization for Inclusive Growth Program (Subprogram 3)
Project Details
-
Project Officer
Tariq Niazi
Central and West Asia Department
Request for information -
Country/Economy
Georgia -
Modality
-
Sector
- Public sector management
| Project Name | Improving Domestic Resource Mobilization for Inclusive Growth Program (Subprogram 3) | ||||||||
| Project Number | 48044-005 | ||||||||
| Country / Economy | Georgia |
||||||||
| Project Status | Closed | ||||||||
| Project Type / Modality of Assistance | Loan |
||||||||
| Source of Funding / Amount |
|
||||||||
| Strategic Agendas | Inclusive economic growth |
||||||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||||||
| Sector / Subsector |
Finance / Finance sector development - Insurance and contractual savings - Money and capital markets Public sector management / Public expenditure and fiscal management |
||||||||
| Gender | Effective gender mainstreaming | ||||||||
| Description | |||||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||||
| Impact | Citizens, particularly women, benefit from higher living standards and more employment opportunities | ||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | Effective mobilization of domestic resources for increased public and private investment |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | 1. Improved treasury management of debt, cash, and fiscal risk 2. Strengthened public revenue and expenditure management 3. Enhanced generation of domestic savings 4. Increased mobilization of private resources for investment |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Nation-wide |
| Safeguard Categories | |
|---|---|
| Environment | C |
| Involuntary Resettlement | C |
| Indigenous Peoples | C |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Tariq Niazi |
| Responsible ADB Department | Central and West Asia Department |
| Responsible ADB Division | Public Management, Financial Sector and Trade Division, CWRD |
| Executing Agencies |
Ministry of Finance Nodar Khaduri 16 Gorgasali St., 0114 Tbilisi Georgia |
| Timetable | |
|---|---|
| Concept Clearance | - |
| Fact Finding | 02 Jun 2016 to 11 Jun 2016 |
| MRM | 29 Jun 2016 |
| Approval | 31 Aug 2016 |
| Last Review Mission | - |
| Last PDS Update | 14 Sep 2016 |
Loan 3417-GEO
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 31 Aug 2016 | 01 Sep 2016 | 06 Dec 2016 | 31 Dec 2016 | - | 30 Dec 2016 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 50.00 | Cumulative Contract Awards | |||
| ADB | 50.00 | 17 Jun 2022 | 50.00 | 0.00 | 100% |
| Counterpart | 0.00 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Jun 2022 | 50.00 | 0.00 | 100% |
Loan 3418-GEO
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 31 Aug 2016 | 01 Sep 2016 | 06 Dec 2016 | 31 Dec 2016 | - | 30 Dec 2016 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 50.00 | Cumulative Contract Awards | |||
| ADB | 50.00 | 17 Jun 2022 | 48.70 | 0.00 | 100% |
| Counterpart | 0.00 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Jun 2022 | 48.70 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
| Title | Document Type | Document Date |
|---|---|---|
| Georgia: Improving Domestic Resource Mobilization for Inclusive Growth Program | Validations of Project Completion Reports | Dec 2018 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB to Help Georgia Boost Domestic Resources for Inclusive Growth
ADB has approved a $100 million loan to help the government better mobilize domestic resources to address limited availability of finance for small businesses and increase access to long term finance.
Tenders
Contracts Awarded
Procurement Plan