China, People's Republic of : Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project

Sovereign Project | 48055-002

The project will demonstrate harmonization of development and flood and environmental management in the river basin that is a manageable size for project level intervention, using an integrated river basin model. One demonstration will be an introduction of innovative storm water management systems. Urban development increases storm water runoff by cutting trees and covering grounds with concrete or asphalt. Innovative storm water management systems reduce peak storm water runoff by promoting storm water infiltration into soil and increasing storm water retention. The demonstration and the river basin model can be replicated in other many similar-sized river basins, particularly where development is anticipated. Potential climate change impact assessment and sensitivity analysis of flood control structures' capacities will be conducted based on climate change modeling.

Project Details

  • Project Officer
    Zheng, Baochang
    East Asia Department
    Request for information
  • Country/Economy
    China, People's Republic of
  • Modality
  • Sector
    • Agriculture, natural resources and rural development
Project Name Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project
Project Number 48055-002
Country / Economy China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3485-PRC: Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project
Ordinary capital resources US$ 150.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Partnerships
Sector / Subsector

Agriculture, natural resources and rural development / Rural flood protection - Water-based natural resources management

Water and other urban infrastructure and services / Urban flood protection - Urban sanitation - Urban solid waste management

Gender Effective gender mainstreaming
Description

The project will demonstrate harmonization of development and flood and environmental management in the river basin that is a manageable size for project level intervention, using an integrated river basin model. One demonstration will be an introduction of innovative storm water management systems. Urban development increases storm water runoff by cutting trees and covering grounds with concrete or asphalt. Innovative storm water management systems reduce peak storm water runoff by promoting storm water infiltration into soil and increasing storm water retention. The demonstration and the river basin model can be replicated in other many similar-sized river basins, particularly where development is anticipated. Potential climate change impact assessment and sensitivity analysis of flood control structures' capacities will be conducted based on climate change modeling. The use of sensitivity analysis to examine potential climate change impacts and risks of flood control structures can be also replicated to other projects. The project will help XCG review Xinyu City Master Plan for 2008 6 2030 and revisit city's infrastructure planning, which will be another ADB's value addition.



The project is consistent with (i) a decision of the Third Plenary Session of the 18th Central Committee of the Communist Party of China held in Beijing in November 2013, which supports construction of eco-civilization and establishment of a system to protect ecological environment; (ii) ADB's recommendations for preparation of the Thirteenth Five-Year Plan of the People's Republic of China (PRC), 20162020, and ADB's upcoming Country Partnership Strategy for the PRC, 20162020, which supports or seems to support improvement of water security; (iii) ADB's strategy 2020 and the midterm review of the strategy that prioritize natural resource management; ,_and (iv) ADB's Water Operational Plan, 20112020 which prioritizes integrated water resources management and efficiency and productivity in the delivery of water services.



ADB has been supporting projects on flood, waterlogging, and environmental management in the PRC and other countries. Lessons learned from those projects, such as international best practices for flood and waterlogging management, and nonstructural measures for flood and environmental management will be reflected in the project design.

Project Rationale and Linkage to Country/Regional Strategy

Xinyu City is located in Jiangxi Province, 135 kilometer (km) southwest of Nanchang Municipality, the provincial capital. The total area of Xinyu is 3,178 square kilometers (km2), and the total population is 1.16 million. Xinyu is a new industrial city with fast urbanization. Kongmu River is a 49.5 km river which flows in Xinyu including the main city center into Yuanhe River. Yuanhe River is a tributary of Ganjiang River which flows into Yangtze River through Poyang Lake. All Kongmu River watersheds of 597 km2 are in Xinyu. Kongmu River is a source of water supply for Xinyu. The river includes a wetland park which is a major recreational asset.



Various locations along Kongmu River experience floods every year due to low flood control capacity of Kongmu River and low flood retention capacity in the upper watershed._Temperatures and precipitation in Xinyu are increasing due to climate change and flood events appear to be occurring more frequently._Ongoing development in the upper watershed will increase storm water runoff and cause waterlogging in the area if storm water management is not conducted, and will increase frequency and severity of floods along Kongmu River.



Water quality in Kongmu River is class IIIII._However, wastewater and solid waste increased by population growth accompanied by the ongoing development in the upper watershed will result in water quality deterioration in the developed area and Kongmu River, if wastewater and solid waste management is not conducted. In addition, basic amenities for increasing population such as a water supply facility are inadequate in the area.



The anticipated more frequent and severer flooding and waterlogging along Kongmu River, anticipated deterioration of water quality in the Kongmu River basin, and inadequate basic amenities for increasing population will deteriorate living and working environment and will adversely impact economic activities and life quality in Xinyu.

Impact

Quality of the living environment in Xinyu City improved (Xinyu City Master Plan, 20082030)

Project Outcome
Description of Outcome

Flood and environmental management in the upper Kongmu River watershed improved

Progress Toward Outcome As of August 2022, the cumulative CAs and cumulative disbursement reached $24.9 million (16.6% of the loan amount) and $11.1 million (7.4% of the loan amount). The overall project implementation progress was assessed as 15.0% against the project implementation period elapsed 80.0%. The delays in project implementation were affected by the ongoing project scope adjustment and delayed land approval. A physical loan review mission for the project was undertaken on 22-26 August 2022 to expedite resolving these issues.
Implementation Progress
Description of Project Outputs

Integrated rural and urban flood management infrastructure constructed

Solid waste and wastewater management systems improved

Flood and environmental risk management capacity enhanced

Status of Implementation Progress (Outputs, Activities, and Issues) Two contracts of phase I subproject were closed. The construction of three contracts of phase II subproject is not commenced due to the delayed land approval.
Geographical Location Xinyu
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The project is expected to achieve environmental benefits through a comprehensive green planning approach. Design targets include (i) capturing 75% of annual runoff (to improve flood control), (ii) a 40% reduction in stormwater pollutant loads, (iii) provision of sanitary sewer connections for over 57,000 people, (iv) almost 100% coverage for solid waste collection in two settlements, (v) new public green spaces, (iv) improved quality of life, and (vii) improved water resources management.
Involuntary Resettlement The project will permanently acquire 2,290.48 mu of collective land and demolish 24,657.06 square meters of housing in two towns, one subdistrict, and five villages with 13 village groups. Land acquisition will affect 1,078 households and 3,693 persons. House demolition will affect 56 households, with 287 persons requiring relocation of their houses.
Indigenous Peoples The project is classified category C for indigenous peoples. The project does not involve any distinct ethnic minority community and thus does not trigger requirements under ADB's Safeguard Policy Statement.
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation The IEE and EMP are based on the approved domestic feasibility study report and environmental assessments,site visits, and consultations with stakeholders, including with affected persons.
Business Opportunities
Consulting Services All ADB-financed consultants will be hired following ADB's Guidelines on the Use of Consultants (2013, as amended from time to time).
Procurement All ADB-financed procurement will be conducted following ADB's Procurement Guidelines (2015, as amended from time to time).
Responsible ADB Officer Zheng, Baochang
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
Xinyu City Government
Timetable
Concept Clearance 15 Jul 2015
Fact Finding 17 Aug 2016 to 22 Aug 2016
MRM 06 Oct 2016
Approval 06 Dec 2016
Last Review Mission -
Last PDS Update 23 Sep 2022

Loan 3485-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
06 Dec 2016 02 Mar 2017 09 May 2017 31 Dec 2023 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 300.39 Cumulative Contract Awards
ADB 150.00 25 Sep 2022 23.61 0.00 16%
Counterpart 150.39 Cumulative Disbursements
Cofinancing 0.00 25 Sep 2022 11.46 0.00 8%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Audited Project Financial Statements (January-December 2021) Audited Project Financial Statements Jun 2022
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Jun 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Procurement Plan Procurement Plans Jul 2020
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Jul 2020
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Audited Project Financial Statements (June 2014-December 2018) Audited Project Financial Statements Jun 2019
Amendment to the Loan Agreement for Loan 3485-PRC: Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project Loan Agreement (Ordinary Resources) Aug 2018
Amendment to the Project Agreement for Loan 3485-PRC: Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project Project/Program Agreements Aug 2018
江西新余孔目江流域洪水防控及环境治理项目 : 项目数据表 Translated PDS Mar 2017
Loan Agreement (Ordinary Operations) for Loan 3485-PRC: Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project Loan Agreement (Ordinary Resources) Mar 2017
Project Agreement for Loan 3485-PRC: Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project Project/Program Agreements Mar 2017
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Gender Action Plan Gender Action Plans Nov 2016
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Project Administration Manual Project/Program Administration Manual Nov 2016
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Report and Recommendation of the President Reports and Recommendations of the President Nov 2016
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement: Initial Poverty and Social Analysis Initial Poverty and Social Analysis Jul 2015

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Social Monitoring Report (January-December 2022) Social Monitoring Reports Mar 2023
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (July-December 2022) Environmental Monitoring Reports Jan 2023
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (January-June 2022) Environmental Monitoring Reports Sep 2022
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Social Monitoring Report (July-December 2021) Social Monitoring Reports Apr 2022
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports Feb 2022
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Social Monitoring Report (January-June 2021) Social Monitoring Reports Sep 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (January-June 2021) Environmental Monitoring Reports Sep 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Resettlement Due Diligence Report Safeguards Due Diligence Reports Apr 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Social Monitoring Report (July-December 2020) Social Monitoring Reports Mar 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Mar 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Updated Resettlement Plan Resettlement Plans Jan 2021
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Environmental Monitoring Report (May 2017-June 2020) Environmental Monitoring Reports Sep 2020
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement Project: Resettlement Monitoring and Evaluation Report (July 2019-June 2020) Social Monitoring Reports Jul 2020
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement: Social Monitoring Report (January - September 2019) Social Monitoring Reports Dec 2019
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement: Initial Environmental Examination Initial Environmental Examination Sep 2016
Jiangxi Xinyu Kongmu River Watershed Flood Control and Environmental Improvement: Resettlement Plan Resettlement Plans Sep 2016

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
External Resettlement Monitoring Services Firm - Consulting Closed
Integrated Capacity Building for Kongmu River Flood Control and Environment Improvement Firm - Consulting Closed

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Equipment supply for solid waste collection and transportation, and transfer station in Highspeed Railway New City Loan 3485 06 Feb 2023 Anshan Senyuan Road and Bridge Co., Ltd. | NO. 281, Anshan Road, Anshan City Xinyu City Government 1,427,925.19 1,386,428.77
Civil works for the other sewers, stormwater pipelines, permeable pavement, and road landscaping Loan 3485 15 Mar 2022 CHEUROPE International Construction Engineering Group Co., Ltd | PRC Xinyu City Government 12,501,337.59 9,599,811.34
CIVIL WORKS FOR FLOOD CONTROL, CONSTRUCTED WETLANDS, AND LANDSCAPE (SHEN LAKE AND SHIN HA) Loan 3485 28 Jun 2021 JV OF BJ XINDAYU WATER CONSERVANCY CONSTRUCTION | CHINA, PEOPLE'S REP. OF Xinyu City Government 2,580,551.63 1,982,849.64
CIVIL WORKS FLOOD CONTROL, CONSTRUCTED WETLANDS, A ND LANDSCAPE Loan 3485 30 Dec 2020 ZHEJIANG WANLI CONSTRUCTION ENGINEERING CO. | A/S CHINA,PEOPLE'SREP.OF CHINA,PEOPLE'SREP.OF Xinyu City Government 3,894,436.53 3,041,909.32
FLOOD CONTROL, CONSTRUCTED WETLANDS AND LANDSCAPE OF JIANGXI XIANGLONG LAKE AND XIANGLONG RIVER Loan 3485 11 Dec 2019 ZHONGDI YINGANG CONSTRUCTION GROUP CO., LTD. | XINYU JIANGXI CHINA,PEOPLE'SREP.OF Xinyu City Government 2,588,627.89 2,021,287.46
FLOOD CONTROL, CONSTRUCTED WETLANDS & LANDSCAPE Loan 3485 27 Nov 2019 TENGWANGGE CONSTRUCTION GROUP CO., LTD. | XINYU JIANGXI CHINA,PEOPLE'SREP.OF Xinyu City Government 8,325,207.26 6,398,736.48
CS4 INTEGRATED CAPACITY BUILDING FOR KONGMU RIVER FLOOD CONTROL AND ENVIRONMENT IMPROVEMENT Loan 3485 13 Jun 2019 HJI GROUP CORPORATION IN ASSOCIATION WITH | 3200 PARK CENTER DRIVE, SUITE 1180 COSTA MESA, CA 92626 UNITED STATES Xinyu City Government 1,178,617.00 1,178,617.00
CS2 EXTERNAL RESETTLEMENT MONITORING SERVICES Loan 3485 13 Jun 2019 BEIJING HAOHAN ENGINEERING CONSULTING CO. LTD | FUXING ROAD, HAIDIAN DISTRICT BEIJING CHINA,PEOPLE'SREP.OF Xinyu City Government 189,860.00 189,860.00
CS-1- POJECT MANAGEMENT SUPPORT Loan 3485 24 Mar 2018 HALCROW (CHONGQING) ENGINEERING CONSULTING CO | 1502 CHONGZI BLDG, NO. 2 WUJIAN RD. JIANGBEI DISTRICT CHONGQING, CHINA CHINA,PEOPLE'SREP.OF Xinyu City Government 828,699.00 828,699.00

Procurement Plan