The impact of the project will be improved quality of life and environmental sustainability in Zuoquan County. The outcome of the project will be improved and integrated river basin management in Zuoquan County. The project will include four outputs: (i) water source protection of the Qingzhang headwaters, (ii) Qingzhang River rehabilitation and integrated low-impact facilities, (iii) inclusive water supply and wastewater collection services, and (iv) strengthened institutional capacity.

Output 1 will support (i) re-vegetation around the Shixia Reservoir and planting of forest belt along two headwaters for about 12,800 hectares (ha); (ii) installation of the Shixia Reservoir spillway gates; (iii) construction of a flood-discharging and washout tunnel; and (iv) construction of five hydrological and water quality monitoring stations with telecommunication system in the Shixia Reservoir catchment.

Project Details

Project Officer
Radstake, Frank East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Loan
Sector
  • Agriculture, natural resources and rural development
 
Project Name Shanxi Urban-Rural Water Source Protection and Environmental Demonstration Project
Project Number 48274-002
Country China, People's Republic of
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3557-PRC: Shanxi Urban-Rural Water Source Protection and Environmental Demonstration Project
Ordinary capital resources US$ 100.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Sector / Subsector

Agriculture, natural resources and rural development / Forestry - Rural flood protection - Rural water supply services

Transport / Urban roads and traffic management

Water and other urban infrastructure and services / Urban flood protection - Urban sewerage

Gender Equity and Mainstreaming Effective gender mainstreaming
Description

The impact of the project will be improved quality of life and environmental sustainability in Zuoquan County. The outcome of the project will be improved and integrated river basin management in Zuoquan County. The project will include four outputs: (i) water source protection of the Qingzhang headwaters, (ii) Qingzhang River rehabilitation and integrated low-impact facilities, (iii) inclusive water supply and wastewater collection services, and (iv) strengthened institutional capacity.

Output 1 will support (i) re-vegetation around the Shixia Reservoir and planting of forest belt along two headwaters for about 12,800 hectares (ha); (ii) installation of the Shixia Reservoir spillway gates; (iii) construction of a flood-discharging and washout tunnel; and (iv) construction of five hydrological and water quality monitoring stations with telecommunication system in the Shixia Reservoir catchment.

Output 2 will support (i) dredging of selected sections of the Qingzhang River which are heavily silted (about 11.6 kilometers [km]); (ii) rehabilitation of the Qingzhang River, and construction of embankment (about 8.9 km); (iii) construction of wetland of about 35.35 ha and associated river amenity facilities; and (iv) low-impact design (sponge city concept) for Binhe road expansion and stormwater drain installation.

Output 3 will support (i) construction of 45.3-km raw water transmission pipelines and expansion of a pumping station; (ii) construction of 48.3-km water distribution pipelines and expansion of four pumping stations; (iii) replacement of 36.5-km existing water supply pipelines and construction of two rural domestic water treatment stations; (iv) expansion of the Zuoquan County wastewater treatment plant from 10,000 m3 per day to 15,000 m3 per day, with improvement of treatment technologies and renovation of some equipment; (v) construction of 4.97-km trunk sewers; (vi) replacement of 1.29-km existing main sewer pipelines; and reconstruction of four overflow manholes.

Output 4 will support institutional and capacity development for (i) project management; (ii) improvement of existing flood warning system; (iii) integrated urban rural water supply, and (iv) action plan for sponge city design for new city district development.

Project Rationale and Linkage to Country/Regional Strategy

The proposed project will be implemented in Zuoquan County, Jinzhong Municipality of Shanxi Province. The project will address key water resources management and related issues in Zuoquan County in an integrated manner, including water quality and quantity, flood mitigation, soil erosion prevention, land use planning, and related capacity building activities. The proposed project is expected to demonstrate the ability and merits of working at county level to advance the government's goal of ecological civilization and poverty reduction. Special features and value addition. The project is expected to demonstrate the following innovations/value additions:

(i) Integrated river basin management by implementing structural and nonstructural measures in pollution prevention, flood management, ecological conservation and rehabilitation, water demand management, and institutional reform support from upstream to downstream of Qingzhang River. This approach will have good demonstration effect to other regions as the PRC increasingly need to improve management of its many small river basins facing similar issues as Zuoquan County;

(ii) Integrated urban-rural land use planning and protection. The project area has been analyzed and classified into different zones according to their land use types. From reservoir to downstream township, the Qingzhang River passes through four types of predominant land use areas within the project boundary. Protection measures have been identified according to the characteristics of each land use zone, including vegetation for the areas upstream of the Shixia reservoir to reduce soil erosion; safety inspection of the reservoir and replacement of aged facilities; improvement of flood protection standard of the Qingzhang river and enhancement of ecological values along the river banks; provision of low impact facilities such as wetland park and enhanced road design; improvement of urban stormwater drainage system, and sewage collection and treatment; and provision of reliable water supply to rural and urban area including commercial and industry;

(iii) Sponge city is an important concept from an integrated urban land and water management perspective. The important sponge city concept is applied to implement the Binhe Road as a pilot scheme which incorporates permeable pavement, low-impact-development (LID) tree pits and bio-retention swales. The LID facilities not only retard surface runoff, but also reduce non-point source pollution from urban runoff. The scale will be further extended to prepare an action plan to identify LID technologies and practices for Zuoquan's new district development; and

(iv) Inclusive Zuoquan County's urbanization and poverty reduction. Zuoquan is a national designated poverty county which lags behind the average in terms of social economic development due partially to uncoordinated development and inadequate infrastructure. People are exposed to natural disaster of floods and droughts, as well as polluted environment. The project will create enabling environment for future city's development and poverty reduction by providing improved infrastructure, flood risk reduction measures, water security and effective wastewater collection and treatment system.

Impact Quality of life and environmental sustainability in Zuoquan County improved
Project Outcome
Description of Outcome Living and environmental conditions for urban and rural residents of Zuoquan County improved
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Shixia Reservoir operation and its watershed vegetation improved

Qingzhang River and Binhe Road rehabilitated

Inclusive water supply and wastewater collection services achieved

Institutional capacity strengthened

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Zuoquan Xian
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects Environmental safeguards (Category B): Domestic environmental impact assessment (EIA) has been approved by Jinzhong Municipality Environment Protection Bureau.
Involuntary Resettlement Resettlement (Category A): Land accquisition and resettlement report has been completed.
Indigenous Peoples Ethnic minorities (Category C): Category C was confirmed during PPTA stage.
Stakeholder Communication, Participation, and Consultation
During Project Design Consultations with local government agencies, farmer communities, and other stakeholders were conducted during project preparation. Social dimensions: Gender action plan, social action plan, and participation and stakeholder communication strategy have been prepared.
During Project Implementation
Business Opportunities
Consulting Services It is expected that consultants will be required for conducting capacity development and institutional strengthening activities, including project management support. All consulting services will be engaged in accordance with the ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). Consulting services will be selected by (i) inviting simplified technical proposals and (ii) using the quality- and cost-based selection method, with a quality cost ratio of 90:10.
Procurement Procurement will be done in accordance with ADB's Procurement Guidelines (2013, as amended from time to time).
Responsible ADB Officer Radstake, Frank
Responsible ADB Department East Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, EARD
Executing Agencies
Zuoquan County Government
[email protected]
Zuoquan COunty, Shanxi Province
People's Republic of China
Timetable
Concept Clearance 19 Dec 2014
Fact Finding 25 Oct 2016 to 01 Nov 2016
MRM 03 Mar 2017
Approval 22 Aug 2017
Last Review Mission -
Last PDS Update 26 Sep 2017

Loan 3557-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
22 Aug 2017 - - 30 Jun 2023 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 152.10 Cumulative Contract Awards
ADB 100.00 22 Aug 2017 0.00 0.00 0%
Counterpart 52.10 Cumulative Disbursements
Cofinancing 0.00 22 Aug 2017 0.00 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found