Pakistan : National Motorway M-4 Gojra–Shorkot Section Project
The proposed project will construct a 62-kilometer (km) four-lane, access-controlled motorway connecting Gojra and Shorkot in Punjab Province, and improve the institutional capacity of the National Highway Authority (NHA), particularly for managing safeguards and contracts. The project will facilitate northsouth connectivity, improve quality and efficiency of road transport services, and promote inclusive economic growth.
Project Details
-
Project Officer
Ghafoor, Khurram
Central and West Asia Department
Request for information -
Country/Economy
Pakistan -
Modality
-
Sector
- Transport
Project Name | National Motorway M-4 Gojra–Shorkot Section Project | ||||||||||||||||||||
Project Number | 48402-001 | ||||||||||||||||||||
Country / Economy | Pakistan |
||||||||||||||||||||
Project Status | Closed | ||||||||||||||||||||
Project Type / Modality of Assistance | Grant Loan |
||||||||||||||||||||
Source of Funding / Amount |
|
||||||||||||||||||||
Strategic Agendas | Inclusive economic growth Regional integration |
||||||||||||||||||||
Drivers of Change | Governance and capacity development Partnerships |
||||||||||||||||||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||||||||||||||||||
Gender | No gender elements | ||||||||||||||||||||
Description | The proposed project will construct a 62-kilometer (km) four-lane, access-controlled motorway connecting Gojra and Shorkot in Punjab Province, and improve the institutional capacity of the National Highway Authority (NHA), particularly for managing safeguards and contracts. The project will facilitate northsouth connectivity, improve quality and efficiency of road transport services, and promote inclusive economic growth. | ||||||||||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | In Pakistan, the transport sector contributes about 10% to the gross domestic product (GDP). It is estimated that 2.3 million people (about 6% of the total employed labor force of Pakistan) earn their livelihoods from this sector. Road transport dominates Pakistan's transport system, accounting for almost 96% of freight traffic in ton-kilometers and 92% of passenger traffic in passenger-kilometers. Much of the country's 12,500 km national highway network was built before the 1950s. About 75% of it consists of two-lane undivided roads of 67 meters (m) in width. With a growing economy fueled mainly by growth in manufacturing and a relatively high population growth, traffic demand is on the rise. However, slow-moving trucks and nonmotorized traffic, poor road conditions, and frequent truck overloading are impeding the efficiency and safety of road transport. To reduce the traffic load on the heavily used national highways, the government began in the 1990s to build high-speed, fully access-controlled national motorways with four or more lanes. To date, around 900 km of the planned 2,800 km are operational. Pakistan's domestic investment and trade flows concentrate on one major northsouth transport corridor, which connects the key centers of economic activity. Comprising national highways and motorways with a total length of about 1,800 km, the corridor runs from the port city of Karachi in the south, passes through primary production and population centers such as Khanewal, Multan, Muzaffargarh, Lahore, Faisalabad, Islamabad, and Peshawar, before reaching Torkham, on the northern border with Afghanistan. The economy of the area served by the corridor accounts for 80%85% of Pakistan's GDP. As a result of Pakistan's accession to the Central Asia Regional Economic Cooperation (CAREC) Program in 2010, this transport corridor now forms an integral part of the CAREC corridors 5 and 6, opening a vital trading link between landlocked Central Asian nations and the country's warm-water ports of Gwadar, Karachi, and Port Qasim on the Arabian Sea. The motorway M-4, connecting Faisalabad with Multan, will be a part of the northsouth transport corridor. Its area of influence, which includes Faisalabad, Multan, and the entire Punjab Province, accounts for about 56% of the country's population and for 59% of the country's GDP. The M-4 will extend the already completed M-1, M-2, and M-3 motorways southward and shorten the distance between Multan and the twin cities of Islamabad and Rawalpindi in the north. The FaisalabadGojra section (58 km) of the M-4 was completed in 2014 under Asian Development Bank (ADB) financing, and the KhanewalMultan section (57 km) will be completed in 2015 under financing from the Islamic Development Bank. The proposed project will finance the construction of the 62 km GojraShorkot section. Achievement of its full benefits will depend on the completion of the remaining 64 km ShorkotKhanewal section, which is currently anticipated to be financed through additional financing of the project in 2016. Upon completion, the new M-4 will provide a four-lane, access-controlled alternative to the existing narrow and congested routes, notably in the heavily trafficked Faisalabad and KhanewalMultanMuzaffargarh areas. The national highway N-5 is part of the northsouth transport corridor, and Pakistan's longest and most important highway. Its section between Lahore and Multan is a four-lane road through highly urbanized areas carrying an average daily traffic volume of 20,000 vehicles. Currently, the majority of long-distance traffic from Karachi to Islamabad and onward leaves the N-5 after Multan to use the local road network before reaching the M-2. These two-lane roads are unsafe, having at-grade access points from local dwellings and businesses throughout. The completed M-4 will attract most of this long-distance traffic and also divert traffic from the N-5, which will help alleviate congestion on that road. Overall, the M-4 will provide an efficient international link between the north of Pakistan and beyond, and southern Punjab, Sindh, and the ports of Karachi and Gwadar in southern Pakistan. Vision 2025 envisages modernization of transport infrastructure and greater regional connectivity as one of the seven pillars to achieve its stated medium-term goals. The project is consistent with the strategic goals and government priorities. An enhanced northsouth corridor will reduce the time and cost of moving goods and people along the entire logistic and supply chain, removing one of the key constraints to raising competitiveness, attracting private sector investment, increasing productivity, as well as deepening and diversifying the industrial base, all of which are essential for providing sustainable jobs to a growing population. The project is also consistent with ADB's country partnership strategy, 20152019 for Pakistan and fits with ADB's Midterm Review of Strategy 2020, supports the CAREC Transport and Trade Facilitation Strategy 2020, and is included in ADB's country operations business plan, 20152017 for Pakistan. The investment demand to bring Pakistan transport infrastructure on a sustained growth trajectory is huge. ADB is mobilizing additional resources to complement its own and, in June 2015, secured a grant contribution of 262 million over 20152020 from the Government of the United Kingdom to the development of the Pakistan Economic Corridors Program. The main focus of the program is to finance strategic sections of the CAREC corridors in Pakistan, which is fully aligned with Pakistan's Vision 2025, the CAREC Transport and Trade Facilitation Strategy 2020, and ADB's strategic objectives. ADB's leading role in Pakistan's road sector development has yielded lessons: keep project designs simple; limit the number of components and implementing agencies to a manageable level; make sure that cost estimates are realistic and that sufficient counterpart funds are made available; and adopt realistic timeframes for land acquisition and resettlement of affected people. These lessons are adequately incorporated in the design of this project. |
||||||||||||||||||||
Impact | Modernization of transport infrastructure and greater regional connectivity to support a vibrant and growing economy (Pakistan Vision 2025) |
Project Outcome | |
---|---|
Description of Outcome | An efficient and safer transport corridor between Islamabad, Faisalabad, and Multan that enhances connectivity between the various parts of the country |
Progress Toward Outcome | Compliance to safeguards monitoring and reporting are being monitored. ADB safeguards team is also assisting the EA on safeguards matters. The EA is regularly submitting environment impact assessments and social monitoring reports. |
Implementation Progress | |
Description of Project Outputs | 1. 62 km of four-lane, access-controlled motorway connecting Gojra and Shorkot constructed and operational 2. Safeguard and contract administration capacity of the NHA strengthened. |
Status of Implementation Progress (Outputs, Activities, and Issues) | This is being monitored through safeguards monitoring reports. Achievements will be assessed upon project completion. This is being monitored and assessed. Contractors commenced road civil works in April 2016. Road construction is underway. |
Geographical Location | Gojra, Shorkot |
Safeguard Categories | |
---|---|
Environment | A |
Involuntary Resettlement | A |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | The M-4 alignment passes through undisturbed agricultural land. In 2007, as required by ADB's Environment Policy (2002), an environmental impact assessment (EIA) report was prepared and approved for the entire M-4. Subsequently, the EIA report was updated to meet the requirements of ADB's Safeguard Policy Statement (2009) and new national legal requirements, and disclosed on ADB's website in July 2014. The revised EIA incorporates environmental management costs, new public consultations, and also includes an assessment of the cumulative impacts of the complete M-4 motorway project. This updated EIA was posted on ADB's website in August 2015. The project design has factored in climate change risks and mitigation measures as well as community concerns. The environmental impacts identified are largely concentrated in the construction phase. Soil erosion, dust, and noise impacts are likely to be significant. Noise impacts will persist into the operational phase. The environmental management plan (EMP) includes measures to minimize anticipated impacts during construction and operation. Prior to construction, contractors will update the EMP into a site-specific environmental management plan (SSEMP). The SSEMP will be based on a risk assessment approach to select impact- and site-appropriate mitigation measures such as barriers for construction and operational noise. The construction supervision consultant, the EALS Division of the NHA, and ADB will closely monitor the implementation of the SSEMP. The NHA will submit semiannual environmental monitoring reports to ADB for disclosure on the ADB website. The Environment, Afforestation, Land, and Social (EALS) Division is headed by a General Manager and supported by the Director (Environment) who is in charge of EMP implementation, and three Deputy Directors. The Deputy Director for this project will make sure that the provisions of the SSEMP are implemented. Capacity building at the EALS environment subdivision, and of the contractors and supervision consultants will also be conducted by ADB's Central and West Asia Department, through its ongoing TA for Sustainable Environmental Management of Projects in Central and West Asia. |
Involuntary Resettlement | The project will affect 36 villages and 3,674 households by displacing 26,762 people. Of these, 213 people in 29 households will either be physically displaced or lose 10% or more of productive assets. Land acquisition and resettlement activities have been substantially completed. The NHA has prepared and submitted to ADB the final land acquisition and resettlement plan (LARP) based on the detailed design and an external land valuation study. The LARP was disclosed on ADB's website on 15 July 2015. Public consultation and information disclosure were undertaken while preparing the LARP, including displaced people and the communities along the project road. Consultation and information sharing will continue throughout project implementation. Resettlement activities will be managed and implemented by the NHA, through PIU, and supported by the EALS Division and the social safeguard management consultant. The PIU has demonstrated capacity for implementing involuntary resettlement. A functioning grievance redress mechanism has been established. Internal monitoring reports will be prepared by the PIU and social safeguard management consultant, and included in the quarterly progress reports of the supervision consultant. A qualified and experienced external monitoring agency will verify the executing agency's monitoring reports, monitor LARP implementation, identify issues, and recommend corrective measures. |
Indigenous Peoples | The project road is located in the settled areas of Punjab Province, where no indigenous peoples as defined under ADBs Safeguard Policy Statement reside. No indigenous communities will be affected by the project and, accordingly, no indigenous peoples planning documents are required. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Meetings and focus groups discussions with community and displaced persons (DPs) have been conducted as part of the poverty and social analysis. These involved all relevant stakeholders including representatives of the poor and other socially excluded groups such as elderly and other vulnerable women to disseminate the information as well as obtain their feedback on issues related with project design and potential social impacts. Other key stakeholders such as the relevant line departments and local government representatives were also consulted. In addition to normal cash compensation for land and assets, vulnerability and livelihood restoration support has also been provided in the LARP for poor and vulnerable groups. More consultation meetings, where and when required, will also be undertaken with the affected households and communities during the course of LARP updating work including updating of census survey, inventory of losses and socioeconomic survey, etc. |
During Project Implementation | NHA, the consultants, and ADB will continue to conduct needed stakeholder consultations during project implementation. |
Business Opportunities | |
---|---|
Consulting Services | Consulting services are in accordance to ADB's Guidelines on the Use of Consultants. An estimated 699 person-months (66 for international, 633 for national) of consulting services are required for construction supervision. The construction supervision firm was engaged using the single source selection. |
Procurement | The project procurement classification is Category B. All procurement of works were undertaken in accordance with ADB's Procurement Guidelines. International competitive bidding procedures were used for civil works contracts. |
Responsible ADB Officer | Ghafoor, Khurram |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Pakistan Resident Mission |
Executing Agencies |
National Highway Authority |
Timetable | |
---|---|
Concept Clearance | 06 Apr 2015 |
Fact Finding | 16 Jun 2015 to 26 Jun 2015 |
MRM | 31 Jul 2015 |
Approval | 30 Sep 2015 |
Last Review Mission | - |
Last PDS Update | 24 Sep 2018 |
Grant 0440-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2015 | 22 Oct 2015 | 17 Dec 2015 | 31 May 2020 | - | 06 Nov 2020 |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 92.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 23 Jan 2023 | 0.00 | 67.73 | 74% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 92.00 | 23 Jan 2023 | 0.00 | 67.73 | 74% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Partly satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Grant 0482-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
10 Jun 2016 | 20 Jun 2016 | 01 Sep 2016 | 31 Mar 2020 | - | 01 Aug 2020 |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 34.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 23 Jan 2023 | 0.00 | 30.12 | 89% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 34.00 | 23 Jan 2023 | 0.00 | 30.12 | 89% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Partly satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Loan 3300-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2015 | 22 Oct 2015 | 17 Dec 2015 | 31 May 2020 | - | 24 Aug 2021 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 225.00 | Cumulative Contract Awards | |||
ADB | 178.00 | 23 Jan 2023 | 106.07 | 0.00 | 100% |
Counterpart | 47.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 23 Jan 2023 | 106.07 | 0.00 | 100% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Partly satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Loan 3395-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
10 Jun 2016 | 20 Jun 2016 | 01 Sep 2016 | 31 Dec 2020 | - | 06 Jan 2022 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 139.00 | Cumulative Contract Awards | |||
ADB | 100.00 | 23 Jan 2023 | 53.92 | 0.00 | 100% |
Counterpart | 39.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 23 Jan 2023 | 53.92 | 0.00 | 100% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Partly satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Loan 8308-PAK
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
24 Jun 2016 | 25 Jun 2016 | 02 Sep 2016 | 31 Dec 2020 | - | 31 Dec 2020 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 100.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 23 Jan 2023 | 0.00 | 74.05 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 100.00 | 23 Jan 2023 | 0.00 | 74.05 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Pakistan Highway Promotes Growth and Connectivity
A four-lane road linking Faisalabad to Multan is under construction. One complete, this part of the National Trade Corridor will help connect Pakistan's deep seaports with landlocked Afghanistan and Central Asia.ADB, Pakistan Sign Loan Agreement For New Section of M-4 Motorway
ADB signed a loan agreement with the Government of Pakistan today in Islamabad to fund the section of the M-4 motorway connecting Gojra to Shorkot in Pakistan’s Punjab province.ADB, UK to Fund M-4 Motorway Link From Gojra to Shorkot in Punjab
ADB and the UK have agreed to fund a key section of the M-4 motorway in Punjab province, which will cut travel times and support improved investment and trade flows along the country’s vital north-south corridor route.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
PAK: National Motorway M-4 Gojra– Shorkot Section Project | Advance Notice | Archived |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
THIS CONTRACT IS BEING ISSUED AFTER MAJOR CHANGE I N SCOPE FOR LOAN 3300 APPROVED BY ADB'S BOARD ON 2 3 MAY 2018 FOR BAL. WORKS OF E35,P3 INCL. CS. | Loan 3300 | 24 Oct 2018 | M/S. DOHWA ENGINEERING CO. LTD | 438-SAMSEONG RO, GANGNAM-GU, SEOUL REBULIC OF KOREA KOREA, REPUBLIC OF | National Highway Authority | 1,135,125.00 | 1,135,125.00 |
CONSTRUCTION OF HASSANABDAL - HAVELIAN EXPRESSWAY SECTION OF E-35 - SARAI SALEH TO HAVELIAN | Loan 3300 | 31 Jul 2018 | M/S. LIMAK ZKB JV | PLOT NO 44, ST 11, SECTOR I -9/2, ISLAMA BAD, PAKISTAN TURKEY AS JV PARTNER PAKISTAN | National Highway Authority | 16,129,755.00 | 9,338,293.00 |
CONSTRUCTION OF HASSANABDAL - HAVELIAN EXPRESSWAY SECTION OF E-35 - SARAI SALEH TO HAVELIAN | Grant 0440 | 13 Jul 2018 | M/S. LIMAK - ZKB JV | PLOT NO. 44 ST 11 SECTOR I-9/2 ISLAM ABAD PAKISTAN TURKEY PAKISTAN | National Highway Authority | 5,796,182.00 | — |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
National Motorway M-4 Gojra-Shorkot Section Project: Procurement Plan | Procurement Plans | Jul 2018 |
National Motorway M-4 Gojra–Shorkot– Khanewal Section Project - Additional Financing: Procurement Plan | Procurement Plans | Jul 2018 |