Pakistan : Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1

Sovereign Project | 48404-003

The project proposed for financing under the requested PFR is:

(i) building an additional 2-lane carriageway of 66 km along the existing 2-lane carriageway of Petaro-Sehwan road;

(ii) building an additional 2-lane carriageway of 43 km along the existing 2-lane carriageway of Ratodero-Shikarpur road;

(iii) rehabilitating the existing 34 km 4-lane carriageway of Dara Adamkhel-Peshawar road; and

(iv) developing NHA's capacity through due diligence advisory services and assistance with project implementation.

Project Name Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
Project Number 48404-003
Country / Economy Pakistan
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3574-PAK: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
Ordinary capital resources US$ 120.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Knowledge solutions
Sector / Subsector

Transport / Road transport (non-urban)

Gender No gender elements
Description

The project proposed for financing under the requested PFR is:

(i) building an additional 2-lane carriageway of 66 km along the existing 2-lane carriageway of Petaro-Sehwan road;

(ii) building an additional 2-lane carriageway of 43 km along the existing 2-lane carriageway of Ratodero-Shikarpur road;

(iii) rehabilitating the existing 34 km 4-lane carriageway of Dara Adamkhel-Peshawar road; and

(iv) developing NHA's capacity through due diligence advisory services and assistance with project implementation.

Project Rationale and Linkage to Country/Regional Strategy

Located at the crossroads of Afghanistan, Central Asia, the People's Republic of China (PRC), India, and Iran, Pakistan has huge potential to become a regional transport and trade hub. It can maximize its national capabilities and resources to support trade-based economic growth mainly by playing the role of a transit trade hub. However, transit trade through Pakistan is still limited while trade remains maritime-centric, aligned with the southern gateway port of Karachi, and focused on major global developed markets like North America, Europe, and the Middle East. Poor transport and border cross-point infrastructure and costly transport and cross-border services pose an obstacle to exploiting the untapped potential.

Pakistan is putting its effort toward more land-based regional trade with neighboring countries through participation in regional programs. In 2011, Pakistan joined the CAREC Program. Pakistan's transport corridors offer the shortest route to the sea for landlocked Afghanistan, Central Asia, and the PRC's Xinjiang province. Pakistan's accession to CAREC enables subregions in Asia and Europe to be virtually integrated and seamlessly connected from East Asia through South Asia and Central Asia to Europe. In 2013, the CAREC transport corridors were extended to Pakistan to provide Afghanistan, Central Asia, and the PRC with connection to the ports of Gwadar and Karachi on the Arabian Sea. CAREC Corridor 5, extended to Pakistan along N55, links PRC and Afghanistan to the Arabian Sea and provides the PRC's Xinjiang province and landlocked countries in Central Asia the shortest trade route through the Karachi Port. Improving CAREC Corridor 5 along N55 in Pakistan will enable Pakistan to realize potential economic benefits from accelerated trade with surrounding countries. The CAREC Transport and Trade Facilitation Strategy (TTFS) 2020 endorsed by the CAREC ministers at the 12th ministerial conference in 2013 proposes investment projects to build the CAREC corridors in Pakistan.

The country partnership strategy 2015-2019 for Pakistan highlights the focus on strengthening regional connectivity in transport and energy through ADB support for (i) the extension of CAREC corridors to the ports of Gwadar and Karachi, (ii) the Turkmenistan-Afghanistan-Pakistan-India natural gas pipeline project, and (iii) transport and trade facilitation with emphasis on developing economic corridors to expand economic opportunities for communities in surrounding areas. This strategic direction is in line with ADB's Regional Cooperation and Integration Strategy (2006) and the Operational Plan for Regional Cooperation and Integration (2016), which aim to strengthen connectivity between economies and raise competitiveness in connected markets.

ADB, as the CAREC Secretariat, played an instrumental role in defining CAREC corridors in Pakistan in 2013. From its experience in road network development in Pakistan, ADB knows transit traffic flow patterns and the network effects the CAREC corridors will create. ADB's sector road map in Pakistan will help the country become a regional transport and transit hub in line with the development of the CAREC corridors. ADB's active involvement in CAREC corridor development through the proposed MFF will encourage the government to accord high priority in terms of allocating national resources to build a seamless regional connectivity among CAREC countries.

Impact

Regional connectivity and trade enhanced in CAREC corridors defined by project

Project Outcome
Description of Outcome

Efficiency for road traffic along the CAREC Corridors improved

Progress Toward Outcome For the Ratodero-Shikarpur section, ADB project team has been closely monitoring the implementation of the updated land acquisition and resettlement plan.
Implementation Progress
Description of Project Outputs

CAREC Corridor along N55 constructed or rehabilitated

NHA capacity strengthened

Status of Implementation Progress (Outputs, Activities, and Issues) Contract for Peshawar to Dara Adam Khel was awarded on 3 October 2018. Delays occurred due to mixed reasons, including the recent lockdown and the contractor's inadequate resource mobilization. Contract for Petaro to Sehwan was awarded on 6 December 2018. Delays occurred due to mixed reasons, including the delays in LARP implementation. 8.4 km still remains withheld, which requires an addendum of LARP once the land title is confirmed as private. Contract for Ratodero to Shikarpur was awarded on 23 September 2020 and the contractor mobilized its resources in February 2021. About 20 km of the section was handed over to the contractor after EMR validation. LARP implementation for the remaining section is ongoing.
Geographical Location Nation-wide, Dara, Peshawar, Petaro, Ratodero, Sehwan, Shikarpur
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects Project 1 is classified category B for environment. An environmental assessment and review framework and draft initial environmental examinations were prepared and disclosed on the ADB website. The project roads do not cross or are not located near protected areas. The environmental assessment established that the project can have site-specific environmental impacts related to air and water pollution, noise and vibration, loss of roadside trees, and traffic disruptions during construction. Because of construction of additional lanes and increase in traffic, the project can split communities and disrupt farming patterns. Adequate mitigation measures will be included in and implemented through an environmental management plan. The project design will incorporate measures for preserving community cohesion such as improved crossings (underpasses and overpasses) and access to public facilities. Public consultations were conducted in October-November 2016. Overall responsibility for the implementation of the plan will rest with contractors. NHA's project implementation unit will hire an environmental and social officer to supervise the implementation of the project's environmental safeguards.
Involuntary Resettlement Project 1 will acquire 512,737.1 sqm of land (189,393.0 sqm for Petaro-Sehwan section and 323,344.1 sqm for Ratodero-Shikarpur section) and permanently affect 140 structures (59 residential structures and 71 commercial structures) located within the right-of-way. About 356 households (with 2,411 members) will be affected. Of these, 548 persons will experience significant resettlement impacts, of which 412 persons will be physically displaced while 136 persons will lose 10% or more of their productive assets.
Indigenous Peoples The project road sections traverses through settled areas of Sindh and Khyber Pakhtunkhwa provinces and tribal group with secluded cultural, socioeconomic, and administrative institutions different than mainstream population were not identified.
Stakeholder Communication, Participation, and Consultation
During Project Design Multiple rounds of public consultations were held by technical assistance consultants during project preparation. Local authorities and relevant government departments, traders, freight forwarders, transporters, and commuters were engaged to design the investment facility and packaging of tranche projects. Sessions were held with potentially displaced persons including poor and vulnerable households between January-April 2017. Mitigations were incorporated in the preliminary design to avoid or minimize involuntary resettlement impacts, as well as LAR impacts; eligibility and entitlements were explained. Consultation, participation and information disclosure strategy were designed and incorporated in the LARPs for continued consultation process with affected persons and communities and other stakeholders, including poor and vulnerable people. There is limited scope for civil society organizations to participate and contribute in project design. However, NHA will collaborate and consult with civil society organizations during detailed design and assess their role and level of participation in the planning, implementation, and monitoring of LARPs. A project communication strategy on consultation, participation, and information disclosure is designed and included in draft LARPs to ensure stakeholders, particularly poor and vulnerable people, are engaged during the consultative process and are informed on resettlement planning, implementation, monitoring, and resolving grievances.
During Project Implementation The project safeguard team in project implementation unit assisted by resettlement specialists under the supervision consultants will liaise with local communities and civil society organizations for the consultation, participation, and information disclosure on project design and LAR progress, recording and redress of grievances, LARP implementation, monitoring and execution of project works, etc.
Business Opportunities
Consulting Services The consultants under the project will be recruited in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time).
Procurement Procurement of goods, civil works, and related services financed from the ADB loan will be done in accordance with ADB's Guidelines for Procurement (2015, as amended from time to time).
Responsible ADB Officer Ghafoor, Khurram
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Pakistan Resident Mission (PRM)
Executing Agencies
National Highway Authority
Timetable
Concept Clearance -
Fact Finding -
MRM 26 Jul 2017
Approval 28 Sep 2017
Last Review Mission -
Last PDS Update 07 Dec 2021

Loan 3574-PAK

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
28 Sep 2017 18 Dec 2017 31 Jan 2018 31 Dec 2022 30 Jun 2024 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 135.00 Cumulative Contract Awards
ADB 120.00 25 Jan 2024 63.71 0.00 71%
Counterpart 15.00 Cumulative Disbursements
Cofinancing 0.00 25 Jan 2024 48.51 0.00 54%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Partly satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Central Asia Regional Economic Cooperation Corridor Development Investment Program (Tranche 3): Updated Facility Administration Manual Facility Administration Manual Dec 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Audited Project Financial Statements (July 2021-June 2022) Audited Project Financial Statements Dec 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Audited Project Financial Statements (July 2020-June 2021) Audited Project Financial Statements Mar 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program: Updated Facility Administration Manual Facility Administration Manual Aug 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Audited Project Financial Statements (July 2019-June 2020) Audited Project Financial Statements Jun 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Feb 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Procurement Plan Procurement Plans Feb 2018
Loan Agreement for Loan 3574-PAK: CAREC Corridor Development Investment Program - Tranche 1 Loan Agreement (Ordinary Resources) Dec 2017
Project Agreement for Loan 3574-PAK: CAREC Corridor Development Investment Program - Tranche 1 Project/Program Agreements Dec 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Framework Financing Agreement Framework Financing Agreement Sep 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program: Report and Recommendation of the President Reports and Recommendations of the President Sep 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program: Facility Administration Manual (As of Board Approval) Facility Administration Manual Aug 2017

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Social Monitoring Report (January-December 2023) Social Monitoring Reports Jan 2024
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Environmental Monitoring Report (January-June 2023) Environmental Monitoring Reports Oct 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (December 2022-May 2023) Social Monitoring Reports Oct 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Social Monitoring Report (December 2022-May 2023) Social Monitoring Reports Oct 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Social Monitoring Report (September-November 2022) Social Monitoring Reports Feb 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: CAREC 1 Projects External Social Monitoring Report (December 2021-December 2022) Social Monitoring Reports Feb 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Dakhan Bypass Land Acquisition and Resettlement Plan Addendum Resettlement Plans Jan 2023
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Environmental Monitoring Report (July-December 2022) Environmental Monitoring Reports Dec 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (September-November 2022) Social Monitoring Reports Dec 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Social Monitoring Report (June-August 2022) Social Monitoring Reports Dec 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (June-August 2022) Social Monitoring Reports Oct 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Environmental Monitoring Report (January-June 2022) Environmental Monitoring Reports Sep 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Social Monitoring Report (March-May 2022) Social Monitoring Reports Aug 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (December 2021-May 2022) Social Monitoring Reports Aug 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Petaro-Sehwan Additional Carriageway Section I Addendum to Land Acquisition and Resettlement Plan Resettlement Plans Jul 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports May 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: External Environmental Monitoring Report (June-November 2021) Environmental Monitoring Reports Mar 2022
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Ratodero-Shikarpur Additional Carriageway Section II Land Acquisition and Resettlement Plan Resettlement Plans Nov 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: External Environmental Monitoring Report (December 2020-May 2021) Environmental Monitoring Reports Oct 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Ratodero–Shikarpur Additional Carriageway Section II Social Monitoring Report (December 2020-May 2021) Social Monitoring Reports Aug 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (December 2020-May 2021) Social Monitoring Reports Aug 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports May 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Ratodero–Shikarpur Additional Carriageway Section II Social Monitoring Report (May-October 2020) Social Monitoring Reports Mar 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (September-November 2020) Social Monitoring Reports Mar 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Feb 2021
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (June-August 2020) Social Monitoring Reports Oct 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Environmental Monitoring Report (January-June 2020) Environmental Monitoring Reports Oct 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Social Monitoring Report (December 2019-May 2020) Social Monitoring Reports Sep 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Ratodero–Shikarpur Additional Carriageway Section II Social Monitoring Report (February-April 2020) Social Monitoring Reports Aug 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (March-May 2020) Social Monitoring Reports Aug 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program –Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (December 2019-February 2020) Social Monitoring Reports Jul 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Ratodero–Shikarpur Additional Carriageway Section II Social Monitoring Report (November 2019-January 2020) Social Monitoring Reports Apr 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Updated Initial Environmental Examination Initial Environmental Examination Apr 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Environmental Monitoring Report (July-December 2019) Environmental Monitoring Reports Mar 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway Section I Social Monitoring Report (September-November 2019) Social Monitoring Reports Feb 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Social Monitoring Report (June-November 2019) Social Monitoring Reports Jan 2020
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway, Section I Social Monitoring Report (October 2019) Social Monitoring Reports Oct 2019
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway, Section I Social Monitoring Report (June-August 2019) Social Monitoring Reports Oct 2019
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Ratodero–Shikarpur Additional Carriageway Section II, Updated Land Acquisition and Resettlement Plan Resettlement Plans Oct 2019
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Social Monitoring Report (June 2019) Social Monitoring Reports Jul 2019
Central Asia Regional Economic Cooperation Corridor Development Investment Program – Tranche 1: Petaro–Sehwan Additional Carriageway, Section I Social Monitoring Report (March-May 2019) Social Monitoring Reports Jul 2019
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Petaro–Sehwan Additional Carriageway, Section I Updated Land Acquisition and Resettlement Plan Resettlement Plans Nov 2018
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Dara Adamkhel–Peshawar, Section III Social Due Diligence Report Safeguards Due Diligence Reports Aug 2018
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Initial Environmental Examination Initial Environmental Examination Jul 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Petaro-Sehwan Additional Carriageway Section I Resettlement Plan Resettlement Plans Jul 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program - Tranche 1: Dara Adamkhel-Peshawar, Section III Due Diligence Report Safeguards Due Diligence Reports Jul 2017
Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1: Ratodero-Shikarpur Section II Resettlement Plan Resettlement Plans Jul 2017

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders


Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
RATODERO-SHIKARPUR N-55 SECTION 1 - KM0-1000 TO KM 43 400 (43.4KM) - CONSTRUCTION OF ADD'L 2-LANE CARRIGEWAY Loan 3574 02 Oct 2020 TOP INTERNATIONAL ENGINEERING CORPORATION | PLOT NO.B-39 SINDH COOP. SOCIETY MAIN AIRPORT ROAD, SUKKUR PAKISTAN National Highway Authority 29,794,803.37 28,402,560.13
CONSTRUCTION OF ADDITIONAL 2-LANE CARRIAGEWAY FROM PETARO-SEHWAN N-55 (SECTION 2) KM64 000-KM130 370 (66.37 KM) Loan 3574 10 Dec 2018 XINJIANG BEIXIN ROAD & BRIDGE GROUP CO. LTD. | ST.NO.217,HIGH-TECH ST.,HIGH-TECH INDUSTRIAL DEVT ZONE,URUMQI,XINJIANG CHINA,PEOPLE'SREP.OF National Highway Authority 51,674,742.66 47,408,976.56
REHABILITATION AND IMPROVEMENT OF EXISTING CARRIAGEWAY FROM PESHAWAR-DARA ADAM KHEL (SECTION 3) KM0 000-KM34 350 (34.35 KM) Loan 3574 24 Oct 2018 NASRULLAH JAN INAMULLAH KHAN & CO. JV KARCON | 112 NIC HOUSE, LSLAMIA COLLEGE COLONY CANAL TOWN, PESHAWAR PAKISTAN National Highway Authority 13,729,931.00 12,746,022.00
DESIGN REVIEW AND CONSTRUCTION SUPERVISION CONSULTANTS FOR CARECCORRIDOR DEVELOPMENT INVESTMENT PROGRAM (T-1 PROJECTS) Loan 3574 01 Oct 2018 DONG IL ENGINEERING CONSULTANTS CO., LTD. | 7, 30-GIL, SONGI-RO, SONGPA-GU SEOUL, 05800 KOREA, REPUBLIC OF National Highway Authority 3,766,649.00 3,007,866.00

Procurement Plan