fbpx 49029-002: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project | Asian Development Bank

China, People's Republic of: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project

Sovereign (Public) Project | 49029-002 Status: Active

Xinjiang Uygur Autonomous Region (Xinjiang) is located on the northwestern frontier of the PRC. It shares borders with eight countries and lies on the ancient Silk Road. Xinjiang''s rapid rate of economic growth (9.8%) and urbanization since the early 1990s has improved the overall economic well-being of its residents. Urumqi, the capital city of Xinjiang, serves as a regional transportation and logistics hub between the PRC and Central Asia. The value of Xinjiang''s international trade increased during 2001 -2013 at an average annual rate of 25.7%. However, Xinjiang remains one of the PRC''s least developed regions, and as such has been a beneficiary of the National Strategy for Development of the Western Region. The region also suffers from poor industrial performance and low educational attainment among workers.

Project Details

Project Officer
Liu, Xinjian East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Loan
Sector
  • Water and other urban infrastructure and services
 
Project Name Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project
Project Number 49029-002
Country China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration
Ordinary capital resources US$ 150.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Private sector development
Sector / Subsector

Agriculture, natural resources and rural development / Forestry - Land-based natural resources management

Education / Technical and vocational education and training

Energy / Energy utility services

Transport / Urban roads and traffic management

Water and other urban infrastructure and services / Other urban services - Urban policy, institutional and capacity development - Urban sewerage - Urban solid waste management - Urban water supply

Gender Equity and Mainstreaming Effective gender mainstreaming
Description

Xinjiang Uygur Autonomous Region (Xinjiang) is located on the northwestern frontier of the PRC. It shares borders with eight countries and lies on the ancient Silk Road. Xinjiang''s rapid rate of economic growth (9.8%) and urbanization since the early 1990s has improved the overall economic well-being of its residents. Urumqi, the capital city of Xinjiang, serves as a regional transportation and logistics hub between the PRC and Central Asia. The value of Xinjiang''s international trade increased during 2001 -2013 at an average annual rate of 25.7%. However, Xinjiang remains one of the PRC''s least developed regions, and as such has been a beneficiary of the National Strategy for Development of the Western Region. The region also suffers from poor industrial performance and low educational attainment among workers.

Changji Hui Autonomous Prefecture (Changji) covers an area of 73,140 square kilometers, and is situated on a narrow piedmont plain between the Tianshan mountain ranges in the south and the Gurbantunggut Desert in the north; the corridor (40 -80 kilometers [km] in width) contains settlements, agriculture, and industries. Changji surrounds Urumqi; Changji City (seat of the prefecture) is located 30 km from Urumqi. Changji is located at the center of the Northern Tianshan economic zone, the Urumqi -Changji -Shihezi city cluster, and the Urumqi -Changji economic corridor. This location gives Changji an important role, and some key service activities provided by Urumqi have been relocated to Changji. It is urbanizing rapidly reflecting the PRC''s strategy to accelerate the development of the western regions and its policy to promote regional economic cooperation with neighboring countries, but the Prefecture''s economic development is constrained by significant deficiencies in urban infrastructure and environmental management, including (i) inadequate connectivity of Changji''s cities and towns to the major corridor, (ii) poor service-level solid waste management, (iii) rapid depletion of groundwater supplies, (iv) soil erosion caused by geologic and severe climatic conditions, and (v) weak urban management capacity. Changji''s favorable location and its potential for economic growth encourages companies and industries to locate there, and has resulted in increased pressure on the environment and the inadequate, poorly performing urban infrastructure.

Project Rationale and Linkage to Country/Regional Strategy

Fukang City and Hutubi and Qitai counties of Changji, located in the Urumqi -Changji economic corridor, have experienced significant economic growth during 1994 -2 014, driven mainly by growth in urban-based secondary and tertiary sectors, and rural-based primary sector. Consequently, an appropriate urbanization process - involving both physical and social aspects of urbanization - is needed to accommodate the rural urban shift of economic activities. An industrial demand analysis conducted during project preparation projected significant demand for employees and industrial land in Fukang, Hutubi, and Qitai. However, the current business environment and urban infrastructure facilities in Fukang, Hutubi, and Qitai are relatively weak. Many people living in the urban center, peripheries, and villages within the urban area - a large number of whom are rural migrants - still lack access to safe and reliable basic urban infrastructure services. Establishment of a sound economic base and livable environment requires that Fukang, Hutubi, and Qitai respond to economic and social development challenges, and take advantage of the economic growth opportunities available to cities and towns in the Urumqi -Changji economic corridor.

Development prospects in the project areas are attracting rural migrants to industrial centers in search of employment opportunities. In line with the PRC''s National New-type Urbanization Plan, 2014-2020, the project aims to demonstrate a modern, innovative approach to urban rural development that creates integrated, livable, green, and economically sustainable communities. In addition to physical infrastructure, the project's integrated social infrastructure components seek to facilitate the transition of rural migrants to the urban environment by providing them with skills to take advantage of employment and income opportunities in emerging communities around the industrial zones. High economic growth together with improved business and living environments resulting from project investments could attract additional private sector investments, with spillover effects on small cities and county towns along the strategic economic corridor, including Fukang, Hutubi, and Qitai. The experience in Changji could serve as a demonstration project for other small cities and towns in Xinjiang and the PRC.

Impact

Changji's cities and counties' urbanization and business environment enhanced

People's living conditions in small cities and towns improved

Project Outcome
Description of Outcome Services provided by urban rural infrastructure and environmental features improved
Progress Toward Outcome Being achieved. Project implementation is on track.
Implementation Progress
Description of Project Outputs

Roads and road ancillary facilities (including utility pipes) constructed or rehabilitated

Water supply and solid waste management facilities in Qitai improved

Ecological protection shelterbelts in Fukang created

Capacity of technical and vocational education and training (TVET) enhanced

Capacity of project management and urban planning enhanced

Status of Implementation Progress (Outputs, Activities, and Issues) As of 17 March 2021, cumulative contract award achieved $108.54 million and cumulative disbursement achieved $60.25 million. 22 packages have been awarded. For the remaining six civil work packages, five packages (QT-W3, QT-W5, QT-W6, HTB-W1, and HTB-W2) are subject to scope change and are scheduled to be procured in later 2021. The civil work package of QT-W4 is scheduled to be procured in 2022.
Geographical Location Fukang Shi, Hutubi Xian, Qitai Xian
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects An initial environmental examination (IEE), including an environmental management plan (EMP), was prepared and disclosed on the ADB website in April 2017. The IEE incorporated findings of the domestic feasibility studies and environmental impact assessments, climate risk and vulnerability assessment, and technical assessments. The IEE concluded that the anticipated environmental impacts and risks can be mitigated to acceptable levels through effective implementation of the EMP. Construction dust, noise, soil erosion, and local disruption to traffic and communities will be temporary and localized. During operation, special attention will be given to sustainable use of irrigation water, operational control of the proposed new sanitary landfill, and proper closure and rehabilitation of the current Qitai landfill site. The EMP defined a monitoring plan to verify the project's environmental performance. The executing and implementing agencies are committed to managing the identified environmental risks. The climate risk and vulnerability assessment concluded that the project area is characterized by (i) low rainfall, which will increase by between 2% and 3% by 2040 with high yearly variability; and (ii) very low average temperatures, which will increase by between 10% and 20%. It recommended adaptation measures for the design of bridges, culverts, landfill leachate treatment, and shelterbelts to address these impacts. Reductions in greenhouse gas emissions through design and management of roads, irrigation, solid waste recycling plus the carbon sequestration of the project's forests have been estimated at 68,934 tons of carbon dioxide equivalent per year in 2030. Environmental management is supported by a comprehensive set of loan covenants and capacity development and institutional strengthening activities under the project. Environment safeguards documents were disclosed to the affected people. Potential environmental complaints or disputes will be handled in accordance with the grievance redress mechanism established for the project.
Involuntary Resettlement Three resettlement plans were agreed to by ADB and the government and will be updated during project implementation. The key information in the resettlement plans was disclosed to the affected people and uploaded on the ADB website in March 2017. The project will permanently acquire an estimated 10,193 mu of land, consisting primarily (9,575.44 mu) of collective cultivated land, with the remainder residential, woodland, grassland, and construction land. Of the estimated 590 affected households (2,529 persons), about 304 households (1,557 persons) belong to ethnic minority groups (Kazak, Hui, and Uygur), accounting for 62% of the total affected population. About 199 households (724 persons) will be required to relocate; 58 of these households (254 persons) belong to ethnic minority groups, while 20 households have residential shops. In addition, there were 21 house renters identified. The project will affect the structures of one enterprise with six workers. During resettlement planning, the affected households, villages and communities, village or community leaders, and town and township and county or city governments actively participated in the meaningful consultations, risk assessment, and disclosure activities. A grievance redress mechanism has been established, internal and external monitoring will be carried out, and the required resettlement staff in each PMO has been identified and will be provided with the necessary training on resettlement implementation. The resettlement budget will be made available on a timely basis. All monitoring reports will be disclosed and uploaded on the ADB website.
Indigenous Peoples In 2015, Changji had an ethnic minority population of about 437,800 accounting for 27.4% of the total residents, including Hui (8.8%), Kazakh (10.7%), and Uygur (5.8%). Within the direct project areas, ethnic minorities comprise over 27% of the population. Although the urban communities are ethnically mixed, some differences-e.g., relating to culture, religion, and language-are maintained. Ethnic minorities will not be adversely affected, except for 1,557 persons who belong to ethnic minority groups affected by land acquisition and resettlement impacts. All households in the urban areas will benefit from the new and upgraded infrastructure services. An ethnic minority development plan (EMDP) has been prepared and endorsed by the PMOs. The EMDP focuses on measures to facilitate the inclusion of ethnic minorities in all project activities, and to ensure that their customs and beliefs are respected throughout project implementation. The EMDP was disclosed to ethnic minorities in the areas targeted by the project in their respective local languages, and uploaded on the ADB website in April 2017. EMDP implementation and monitoring is supported under output 5. Monitoring and reporting arrangements for the ethnic minority safeguard are included in the PAM and the project arrangement.
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Liu, Xinjian
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
XUAR Finance Bureau
[email protected]
No 16 Mingde Road, Urumqi, Xinjiang Uygur Autonomous Region, P.R.C.
Xinjiang Uygur Autonomous Region Government
XUAR Housing & Urban-Rural Dev't Bureau
No. 462 Zhongshan Road,
Urumqi, Xinjiang, PRC
Timetable
Concept Clearance 06 Jul 2015
Fact Finding 09 Jan 2017 to 20 Jan 2017
MRM 11 Apr 2017
Approval 25 Sep 2017
Last Review Mission -
Last PDS Update 18 Mar 2021

Loan 3568-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Sep 2017 04 Jan 2018 21 Mar 2018 30 Sep 2023 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 255.42 Cumulative Contract Awards
ADB 150.00 25 Sep 2017 108.96 0.00 73%
Counterpart 105.42 Cumulative Disbursements
Cofinancing 0.00 25 Sep 2017 60.25 0.00 40%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Jun 2021
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Procurement Plan Procurement Plans May 2021
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Audited Project Financial Statements (January-December 2019) Audited Project Financial Statements Jun 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Updated Project Administration Manual Project/Program Administration Manual Dec 2019
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Audited Project Financial Statements (January-December 2018) Audited Project Financial Statements Aug 2019
Loan Agreement for Loan 3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project Agreements Jan 2018
Project Agreement for Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project Agreements Jan 2018
新疆昌吉州统筹城乡基础设施建设示范项目 : 项目数据表 Translated PDS Sep 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Report and Recommendation of the President Reports and Recommendations of the President Aug 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Project Administration Manual (As of Board Approval) Project/Program Administration Manual Aug 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Social and Gender Action Plan Gender Action Plans Aug 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Initial Poverty and Social Analysis Initial Poverty and Social Analysis Jul 2015
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Project Preparatory Technical Assistance Report Project Preparatory Technical Assistance Reports Jul 2015

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Hutubi Subproject Social Monitoring Report (June 2020-May 2021) Social Monitoring Reports Jul 2021
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai County Subproject Social Monitoring Report (September 2020-June 2021) Social Monitoring Reports Jul 2021
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang City Subproject Resettlement External Monitoring Report (July 2020-May 2021) Social Monitoring Reports Jul 2021
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Environmental Monitoring Report (January-November 2020) Environmental Monitoring Reports Nov 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai County Subproject Ethnic Minority Development Plan Indigenous Peoples Plans/Indigenous Peoples Development Plans Nov 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai County Subproject Resettlement External Monitoring Report Social Monitoring Reports Oct 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang City Subproject Resettlement External Monitoring Report Social Monitoring Reports Jul 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang Subproject Ethnic Minority Development Plan Indigenous Peoples Plans/Indigenous Peoples Development Plans Jul 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Hutubi City Subproject Social Monitoring Report Social Monitoring Reports Jun 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Hutubi City Subproject Ethic Minority Development Plan Indigenous Peoples Plans/Indigenous Peoples Development Plans Jun 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Changhua Road Social and Resettlement Due Diligence Report Safeguards Due Diligence Reports Jun 2020
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang City Subproject Updated Resettlement Plan Resettlement Plans Aug 2019
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai Solid Waste Landfill Component Updated Resettlement Plan Resettlement Plans Jul 2019
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai County Subproject Updated Resettlement Plan Resettlement Planning Documents Dec 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang City Subproject Updated Resettlement Plan Resettlement Planning Documents Dec 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Environmental Management Plan Environmental Management Plans Apr 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Ethnic Minority Development Plan Indigenous Peoples Plans/Indigenous Peoples Development Plans Apr 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Draft Initial Environmental Examination Initial Environmental Examination Feb 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Fukang City Subproject Resettlement Plan Resettlement Plans Jan 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Qitai County Subproject Resettlement Plan Resettlement Planning Documents Jan 2017
Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project: Hutubi County Subproject Resettlement Plan Resettlement Plans Dec 2016

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project (QT-G2) Invitation for Bids Closed 12 Sep 2019 29 Oct 2019
Loan 3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project [QT-G1] Invitation for Bids Closed 06 Sep 2019 08 Oct 2019
Initial Project Implementation Support Individual - Consulting Closed 05 Sep 2019 11 Sep 2019
Project management and institutional strengthening support Firm - Consulting Closed 05 Sep 2019 09 Oct 2019
Initial Project Implementation Support Individual - Consulting Closed 05 Sep 2019 11 Sep 2019
Loan 3568 PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project (QT-W1) Invitation for Bids Closed 22 Jul 2019 19 Aug 2019
3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project Invitation for Bids Closed 17 May 2019 17 Jun 2019
3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project [FK-G1] - CORRIGENDUM Invitation for Bids Closed 13 Mar 2018 11 Mar 2019
3568-PRC: Xinjiang Changji Integrated Urban-Rural Infrastructure Demonstration Project [FK-G1] - ORIGINAL Invitation for Bids Closed 06 Mar 2018 24 Apr 2018

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
CS1:PROJECT MANAGEMENT AND INSTITUTIONAL STRENGTHE NING SUPPORT Loan 3568 20 Jan 2021 ENERGY AND ENVIRONMENTAL DEVELOPMENT RESEARCH BEIJING,PRC. CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSULTANCY 992,387.37 992,387.37
QT-W1:RE-BID01 QITAI COUNTY WATER TRANSMISSION WOR KS:PIPELINES SUPPLY AND INSTALLATION Loan 3568 02 Dec 2020 ZHENGYI GROUP CO.LTD YIBIN,SICHUAN,PRC CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 6,039,124.57 3,968,234.28
HTB-W3:CHANGHUA RD. CIVIL ENGINEERING & INSTALLATI ON OF WATER SUPPLY,DRAINAGE,HEATING AND GAS PEPELI NES Loan 3568 05 Aug 2020 XINJIANG CHANGJI MUNICIPAL CONSTRUCTION XINJIANG CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 3,578,446.88 3,488,337.10
FK-W4 FUKANG CITY RD. AND ASSOCIATED UTILITIES(HUI YUAN RD.,RUIYING RD.AND BOYA RD.):WORKS AND PIPELI NE INSTALLATION(WATER SUPPLY,WASTEWATER AND HEAT Loan 3568 30 Dec 2019 ZHEJIANG WANLI CONSTRUCTION ENGINEERING CO., ZHEJIANG CHINA,PEOPLE'SREP.OF CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 6,039,629.69 5,680,802.74
FK-W1 FUKANG CITY RD. AND ASSOCIATED UTILITIES(TIA NSHAN ST.AND TIANCHI ST.):WORKS AND PIPELINE INSTA LLATION(WATER SUPPLY,WASTEWATER AND HEATING) Loan 3568 30 Dec 2019 XI'AN CONSTRUCTION ENGINEERING GROUP CO.,LTD. NO.168 KECHUANG RD. GAO XIN DISTRICT XI'AN CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 7,230,867.53 6,802,625.72
FK-W8 NORTH RING RD.ECOLOGICAL PROTECTION:WORKS,SU PPLY AND PLANTING IN THE NORTHERN PART Loan 3568 26 Dec 2019 SICHUAN HUAYUAN CONSTRUCTION ENGINEERING CO., SICHUAN CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 4,767,648.26 4,484,392.37
QT-W2 QITAI COUNTY SANITARY LANDFILL WORKS(BURIED ZONE,MANAGEMENT AREA,AND ACCESS ROAD) Loan 3568 28 Nov 2019 XINJIANG CHANGJI MUNICIPAL CONSTRUCTION XINJIANG CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government CONSTRUCTION 9,938,393.93 6,367,453.89
FK-G1 FUKANG CITY ROADS MAINTENANCE EQUIPMENT AND GANHEZI TOWN SNOW CLEARING EQUIPMENT Loan 3568 05 Aug 2019 HUNAN FORWARD MECHANICAL ENGIEERING & FURONG ROAD,CHANGSHA CITY,HUNAN PROVINCE CHINA,PEOPLE'SREP.OF Xinjiang Uygur Autonomous Region Government SUPPLY OF GOODS 3,334,879.21 3,334,879.00