fbpx 49107-002: State-Level Support for National Flagship Urban Programs | Asian Development Bank

India: State-Level Support for National Flagship Urban Programs

Sovereign (Public) Project | 49107-002 Status: Active

The project preparatory technical assistance (PPTA) is needed for preparing the investment program and conducting technical, economic, financial, governance, safeguards, gender and social due diligence for the ensuing multi-tranche financing facility (MFF).

Project Details

Project Officer
Di Mario, Luca South Asia Department Request for information
Country
  • India
Modality
  • Technical Assistance
Sector
  • Water and other urban infrastructure and services
 
Project Name State-Level Support for National Flagship Urban Programs
Project Number 49107-002
Country India
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 9022-IND: State-Level Support for National Flagship Urban Programs
Technical Assistance Special Fund US$ 1.12 million
TA 9022-IND: State-Level Support for National Flagship Urban Programs (Supplementary)
Technical Assistance Special Fund US$ 1.50 million
TA 9022-IND: State-Level Support for National Flagship Urban Programs (Supplementary)
Technical Assistance Special Fund US$ 1.87 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Partnerships
Private sector development
Sector / Subsector

Water and other urban infrastructure and services / Urban flood protection - Urban policy, institutional and capacity development - Urban sanitation - Urban sewerage - Urban solid waste management - Urban water supply

Gender Equity and Mainstreaming Effective gender mainstreaming
Description The project preparatory technical assistance (PPTA) is needed for preparing the investment program and conducting technical, economic, financial, governance, safeguards, gender and social due diligence for the ensuing multi-tranche financing facility (MFF).
Project Rationale and Linkage to Country/Regional Strategy Urban centers are driving economic growth in India. More than 30% of India's current population lives in urban areas and contributes 63% of India's gross domestic product (Census 2011). These figures are expected to increase to 40% and 75%, respectively, by 2030. While high urbanization can yield higher productivity and better living standards, Indian cities face persistent development challenges: high urban poverty (35%), environmental and public health hazards, poor hygiene and sanitation behaviors, high water losses (up to 60%) with limited access to 24x7 supply, extensive flooding, unmet energy demands, infrastructure deficits, and weak governance and institutions. Integrated and effective urban development is needed to provide sustainable and affordable basic services. There is an enormous potential to scale up good practices in urban planning and infrastructure development, improve behaviors in hygiene and sanitation, and strengthen institutions to improve living standards for all urban residents.
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Gujarat, Maharashtra, Tamil Nadu, West Bengal
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services ADB will recruit consultants on an individual basis. All consultants will be recruited in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). Lump sum payments/output-based contracts will be considered for consulting services under the TA.
Procurement n/a
Responsible ADB Officer Di Mario, Luca
Responsible ADB Department South Asia Department
Responsible ADB Division Urban Development and Water Division, SARD
Executing Agencies
Ministry of Housing and Urban Affairs
Nirman Bhawan, Maulana Azad Road
New Delhi 110 011
India
Tamil Nadu Urban Infrastructure Financial Services Ltd.
#19, T.P Scheme Road, Raja Annamalai Puram Chennai - 600028, India
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 11 Dec 2015
Last Review Mission -
Last PDS Update 27 Sep 2018

TA 9022-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Dec 2015 11 May 2016 11 May 2016 31 Dec 2016 30 Nov 2020 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
4,480,000.00 0.00 0.00 0.00 0.00 0.00 4,480,000.00 11 Dec 2015 1,982,422.05

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Urban Drainage Specialist Individual - Consulting Closed 29 Mar 2019 10 Apr 2019
Project Management and Procurement Specialist Individual - Consulting Closed 22 Feb 2019 28 Feb 2019
State-Level Support for National Flagship Urban Programs - Social Safeguards Consultant Individual - Consulting Closed 29 Nov 2018 10 Dec 2018
Social Safeguards Consultant Individual - Consulting Closed 19 Sep 2018 25 Sep 2018
Municipal Financial Management Expert Individual - Consulting Closed 07 Sep 2018 14 Sep 2018
Urban Development and Project Management Expert Individual - Consulting Closed 14 Aug 2018 21 Aug 2018
International Senior Remote Sensing Expert Individual - Consulting Closed 30 Jun 2018 09 Jul 2018
Knowledge Management Expert Individual - Consulting Closed 15 Jun 2018 21 Jun 2018
Senior Electro-Mechanical and Procurement Expert Individual - Consulting Closed 06 Jun 2018 12 Jun 2018
Environment Safeguards Specialist Individual - Consulting Closed 02 Jun 2018 08 Jun 2018
State-Level Support for National Flagship Urban Programs (Transport Specialist) Individual - Consulting Closed 18 May 2018 24 May 2018
Climate Change Specialist Individual - Consulting Closed 09 May 2018 20 May 2018
Financial Management Specialist Individual - Consulting Closed 24 Apr 2018 07 May 2018
Environmental Safeguards Specialist Individual - Consulting Closed 18 Apr 2018 27 Apr 2018
Social Development Consultant Individual - Consulting Closed 18 Apr 2018 07 May 2018
Social Safeguards Specialist Individual - Consulting Closed 17 Apr 2018 07 May 2018
Project Management and Institutional Development Expert Individual - Consulting Closed 17 Apr 2018 23 Apr 2018
Social Safeguards Specialist Individual - Consulting Closed 10 Mar 2018 16 Mar 2018
Procurement Assistant Individual - Consulting Closed 09 Mar 2018 22 Mar 2018
State-Level Support for National Flagship Urban Programs (Environmental Safeguards Specialist) Individual - Consulting Closed 02 Feb 2018 08 Feb 2018
Financial Management Expert Individual - Consulting Closed 20 Jan 2018 26 Jan 2018
State-Level Support for National Flagship Urban Programs (Urban Infrastructure and Planning Expert) Individual - Consulting Closed 05 Dec 2017 11 Dec 2017
State-Level Support for National Flagship Urban Programs (Social Safeguards Specialist) Individual - Consulting Closed 05 Dec 2017 11 Dec 2017
State-Level Support for National Flagship Urban Programs-Environmental Safeguards Expert Individual - Consulting Closed 02 Dec 2017 08 Dec 2017
State-Level Support for National Flagship Urban Programs Individual - Consulting Closed 27 Jul 2017 04 Aug 2017
State-Level Support for National Flagship Urban Programs Individual - Consulting Closed 05 Jul 2017 11 Jul 2017
State-Level Support for National Flagship Urban Programs Individual - Consulting Closed 05 Jul 2017 11 Jul 2017
State-Level Support for National Flagship Urban Programs Individual - Consulting Closed 27 Apr 2017 03 May 2017

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.