Fiji : Ports Development Master Plan in Fiji
Project Details
-
Project Officer
Ling, David Tai-Wen
Pacific Department
Request for information -
Country/Economy
Fiji -
Sector
- Transport
- Project Name
- Ports Development Master Plan in Fiji
- Project Number
- 49281-001
- Country / Economy
- Fiji
- Project Status
- Closed
- Project Type / Modality of Assistance
- Technical Assistance
- Source of Funding / Amount
TA 9063-FIJ: Ports Development Master Plan in Fiji Source Amount Technical Assistance Special Fund US$ 200,000.00 - Strategic Agendas
- Environmentally sustainable growth
- Inclusive economic growth
- Regional integration
- Drivers of Change
- Governance and capacity development
- Private sector development
- Sector / Subsector
Transport / Water transport (non-urban)
- Gender
- No gender elements
- Description
- Project Rationale and Linkage to Country/Regional Strategy
- Impact
Improved efficiency and productivity of ports in Fiji
Project Outcome
- Description of Outcome
Government endorsed 15-year ports development master plan for Fiji's six declared ports of entry.
- Progress Toward Outcome
- TA consultants have been mobilized and development of the master plan is in progress.
Implementation Progress
- Description of Project Outputs
Demand Assessment
- Status of Implementation Progress (Outputs, Activities, and Issues)
- The demand assessment is underway and expected to be completed by October 2016.
- Geographical Location
- Nation-wide
Summary of Environmental and Social Aspects
- Environmental Aspects
- Involuntary Resettlement
- Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
- During Project Design
- Key government organizations including Ministry of Economy, Ministry of Public Enterprises, Ministry of Infrastructure and Transport, and Fiji Ports Corporation Limited were consulted in formulating the project design.
- During Project Implementation
- Key government organizations including Ministry of Economy, Ministry of Public Enterprises, Ministry of Infrastructure and Transport, and Fiji Ports Corporation Limited are consulted with during project implementation. Key port users including stevedores, shipping lines, shipping agents, fisheries, and other port users are also consulted to provide inputs into the master plan.
Contact
- Responsible ADB Officer
- Ling, David Tai-Wen
- Responsible ADB Department
- Pacific Department
- Responsible ADB Division
- Transport, Energy and Natural Resources Division, PARD
- Executing Agencies
-
Min of Finance, Public Enterprise, Sugar Ind & Inf
Timetable
- Concept Clearance
- -
- Fact Finding
- 20 Jul 2015 to 22 Jul 2015
- MRM
- -
- Approval
- 21 Dec 2015
- Last Review Mission
- -
- Last PDS Update
- 29 Sep 2016
Funding
TA 9063-FIJ
Approval | Signing Date | Effectivity Date | Closing | ||
---|---|---|---|---|---|
Original | Revised | Actual | |||
21 Dec 2015 | - | 21 Dec 2015 | 31 Dec 2016 | 31 May 2017 | 30 Jun 2017 |
ADB | Cofinancing | Counterpart | Total | |||
---|---|---|---|---|---|---|
Gov | Beneficiaries | Project Sponsor | Others | |||
200,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 200,000.00 |
Date | Amount |
---|---|
17 Jun 2022 | 153,884.29 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Ports Development Master Plan in Fiji: Technical Assistance Completion Report | TA Completion Reports | Jul 2017 |
Ports Development Master Plan in Fiji: Small-scale Technical Assistance Memo | Small-scale Technical Assistance Memo | Dec 2015 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
Fiji’s Ports Are Upgraded to Become Safe Havens of Trade
A project that was unveiled in 2006 making Fiji’s ports safer and more efficient has contributed to the country’s economic growth and stability. ADB contributed to the project with a $16.8 million loan.
Tenders
Contracts Awarded
Procurement Plan
None currently available.