Pakistan : Greater Thal Canal Irrigation Investment Program
The Greater Thal Canal irrigation scheme was partially constructed by the government. The proposed project will support the construction of the remaining parts of the scheme and will provide support for on-farm development.
Project Details
-
Project Officer
Totsuka, Natsuko
Central and West Asia Department
Request for information -
Country/Economy
Pakistan -
Sector
- Agriculture, natural resources and rural development
Project Name | Greater Thal Canal Irrigation Investment Program | ||||
Project Number | 49372-003 | ||||
Country / Economy | Pakistan |
||||
Project Status | Proposed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||
Sector / Subsector | Agriculture, natural resources and rural development / Agricultural production - Irrigation - Rural water policy, institutional and capacity development |
||||
Gender Equity and Mainstreaming | Some gender elements | ||||
Description | The Greater Thal Canal irrigation scheme was partially constructed by the government. The proposed project will support the construction of the remaining parts of the scheme and will provide support for on-farm development. | ||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | Food insecure population reduced; Rural poverty in Punjab reduced | ||||
Outcome | Agricultural production in the project area increased | ||||
Outputs | Three branches of the Greater Thal Canal Irrigation System constructed Farmer's on-farm and water management capacity improved Institutional system for irrigation scheme management strengthened |
||||
Geographical Location |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | The project is likely to be categorized A for environment. The categorization, potential impacts and mitigation measures will be assessed, and necessary safeguards documents like IEE/EIA including the EMP will be prepared during the project preparation. |
Involuntary Resettlement | The project is likely to be categorized A for involuntary resettlement due to land acquisition. Necessary due diligence and documentation will be conducted during the project preparation. |
Indigenous Peoples | The project is likely to be categorized C for indigenous peoples. The categorization will be assessed during the project preparation. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Stakeholders will be duly consulted during the project preparation. |
During Project Implementation | Stakeholders will be duly consulted during the project implementation. |
Business Opportunities | |
---|---|
Consulting Services | To be determined. |
Procurement | To be determined. |
Responsible ADB Officer | Totsuka, Natsuko |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Environment, Natural Resources & Agriculture Division, CWRD |
Timetable | |
---|---|
Concept Clearance | 11 Dec 2017 |
Fact Finding | 05 Feb 2020 to 19 Feb 2020 |
MRM | 30 Mar 2020 |
Approval | - |
Last Review Mission | - |
Last PDS Update | 26 Sep 2018 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Greater Thal Canal Irrigation Investment Program: Project Data Sheet (Urdu translation) | Translated PDS | Dec 2017 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.