Bangladesh : Bangladesh Power System Enhancement and Efficiency Improvement Project
The proposed project will enhance the coverage and improve the reliability and efficiency of the transmission and distribution network, to facilitate better utilization of the expanding power generation capacity to meet the growth in electricity demand across the country
Project Details
-
Project Officer
Nahar, Nazmun
South Asia Department
Request for information -
Country/Economy
Bangladesh -
Sector
- Energy
Project Name | Bangladesh Power System Enhancement and Efficiency Improvement Project | ||||||||||||
Project Number | 49423-005 | ||||||||||||
Country / Economy | Bangladesh |
||||||||||||
Project Status | Active | ||||||||||||
Project Type / Modality of Assistance | Grant Loan |
||||||||||||
Source of Funding / Amount |
|
||||||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships |
||||||||||||
Sector / Subsector | Energy / Electricity transmission and distribution - Energy efficiency and conservation - Energy sector development and institutional reform - Renewable energy generation - solar - Renewable energy generation - wind |
||||||||||||
Gender | Effective gender mainstreaming | ||||||||||||
Description | The proposed project will enhance the coverage and improve the reliability and efficiency of the transmission and distribution network, to facilitate better utilization of the expanding power generation capacity to meet the growth in electricity demand across the country | ||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | In 1971, when Bangladesh gained independence, only 3% of its population had access to electricity. By 2015, this had risen to about 72% with per capita electricity consumption reaching 371 kilowatt-hours per annum. The gross domestic product of Bangladesh has been growing at a rate of over 6% consistently during 20052015. Meeting the need for reliable and affordable electricity is a challenge for Bangladesh as it seeks to sustain economic growth and consolidate its transition to middle-income country status by 2021. To support inclusive growth and development as well as the creation of more and better jobs, the government has set a target of electricity for all by 2021, and is working across the electricity generation, transmission, and distribution value chain to enhance improved delivery of electricity and meet the expected demand of 19 gigawatts (GW) by 2021. | ||||||||||||
Impact | 100% access to power by 2021 and power sector sustainability improved in Bangladesh by 2030 |
Project Outcome | |
---|---|
Description of Outcome | Access to efficient and reliable electricity supply in Bangladesh improved |
Progress Toward Outcome | Completed. |
Implementation Progress | |
Description of Project Outputs | National transmission network in southern Bangladesh strengthened Distribution network in DESCO service areas improved Distribution network in rural areas of Bangladesh including the capacity of end-users improved Capacity in power sector agencies enhanced |
Status of Implementation Progress (Outputs, Activities, and Issues) | Output 1- There were four contracts under output 1. Construction of Aminbazar 400 kV substation was completed in 2021. This substaion plays a vital role in receving the power from the southern part of Bangladesh and distributing it to other part. Aminbazar Mowa Mongla 400 kV 179.5 km transmission line has been constructed. The line is capable to serve 2000 MW power from the southern part of Bangladesh Output-2. Under output 2, SCADA system has been implemented for 69 substation of DESCO area. Output 3. Output 3 is for BREB where around 9,50,000 consumers got new connection. 38,000 km 33 and 11 kV distribution lines and associated facilities have been rehabilitated. 12,000 km 33 and 11 kV distribution lines and associated facilities constructed. Output 4. 2 studies completed for 4 solar and wind project development. GIS based mapping system implemented for NESCO. |
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | Potential environmental impacts are mostly temporary, predictable, and reversible; and can be mitigated through adherence to national and international standards, design criteria, and implementation of the environmental management plans (EMPs). The transmission towers across the Padma River will be constructed on platforms (associated facilities) provided by the Bangladesh Bridge Authority under an ongoing project and due diligence on the approved environmental impact assessment report found it to be in compliance with ADB's Safeguard Policy Statement (2009). |
Involuntary Resettlement | A covenant is included to facilitate verification of the mitigation measures for the platforms. Due diligence has confirmed that the land required for receiving bays at the Aminbazar site is in the possession of PGCB, and no resettlement impacts are expected. |
Indigenous Peoples | Based on social assessments, no indigenous peoples are expected to be affected by the project. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | A series of consultations with key stakeholder groups and communities have been conducted during project preparation, and communities' inputs have been incorporated into the project design. |
During Project Implementation | Consultation with stakeholders and communities will be continued throughout implementation of the project. |
Business Opportunities | |
---|---|
Consulting Services | DESCO has initiated tendering in 2016. Other EAs will initiate the tendering in 2017 |
Procurement | BREB has initiated tendering in 2016. Other EAs will initiate the tendering in 2017 |
Responsible ADB Officer | Nahar, Nazmun |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Bangladesh Resident Mission (BRM) |
Executing Agencies |
Bangladesh Rural Electrification Board Dhaka Electric Supply Company Ltd. (DESCO) Power Div-Min of Power, Energy & Mineral Resources Power Grid Company of Bangladesh, Ltd. (PGCB) |
Timetable | |
---|---|
Concept Clearance | 10 Jun 2016 |
Fact Finding | 21 Jul 2016 to 28 Jul 2016 |
MRM | 29 Sep 2016 |
Approval | 29 Mar 2017 |
Last Review Mission | - |
Last PDS Update | 30 Nov 2023 |
Grant 9190-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
29 Mar 2017 | 29 May 2017 | 22 Jun 2017 | 31 Dec 2020 | 31 Dec 2021 | 06 Feb 2022 |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 2.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 04 Mar 2024 | 0.00 | 1.76 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 2.00 | 04 Mar 2024 | 0.00 | 1.76 | 100% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Loan 3522-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
29 Mar 2017 | 29 May 2017 | 22 Jun 2017 | 31 Dec 2020 | 30 Jun 2023 | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 1,040.70 | Cumulative Contract Awards | |||
ADB | 600.00 | 04 Mar 2024 | 542.96 | 0.00 | 97% |
Counterpart | 440.70 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 04 Mar 2024 | 537.37 | 0.00 | 96% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Loan 3523-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
29 Mar 2017 | 29 May 2017 | 22 Jun 2017 | 31 Dec 2020 | 31 Mar 2024 | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 16.00 | Cumulative Contract Awards | |||
ADB | 16.00 | 04 Mar 2024 | 15.69 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 04 Mar 2024 | 13.61 | 0.00 | 87% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB to Help Improve Power System Efficiency, Coverage in Bangladesh
ADB has approved loans totaling $616 million to enhance the coverage and reliability of Bangladesh’s power systems, while improving the efficiency of the country’s distribution network.
Tenders
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Study on Incorporation of Battery Energy Storage System for Reliable and Efficient Power Supply in Bangladesh Power Sector | Loan 3523 | 12 May 2023 | Operation Technology Inc. | 17 Goodyear, Irvine, CA 92618, United States of America | Power Div-Min of Power, Energy & Mineral Resources | 2,573,139.08 | 2,572,300.37 |
Pre Feasibility and detail feasibility study to develop offshore wind firm | Loan 3523 | 05 Mar 2023 | CESI S.P.A. Italy | Via Rubattino 54, 20143 Milan | Power Div-Min of Power, Energy & Mineral Resources | 2,608,251.68 | 2,608,251.68 |
Establishment of Building Energy Efficiency Rating System For SREDA | Loan 3523 | 20 Jul 2022 | EnergySolve International (Pvt) Ltd., Sri Lanka | 165/55 Sri Saddharmarama Mawatha, Nawala Road, Narahenpita, Colombo-5, Sri Lanka | Power Div-Min of Power, Energy & Mineral Resources | 502,226.14 | 500,781.99 |
Study on Energy Auditing and Efficiency Improvement Procedures for Power Plants and Assessment of Cogeneration Potential in the Industrial Sector | Loan 3523 | 13 Apr 2022 | STEAG Energy Services lndia Pvt. Ltd | A 29, Sector-16, Noida 201301, India | Power Div-Min of Power, Energy & Mineral Resources | 288,944.09 | 288,802.01 |
IMPLEMENTATION OF GIS BASED MANAGEMENT SYSTEM IN NESCO AREA | Loan 3523 | 02 May 2021 | NRECA INTERNATIONAL, USA | 4301 WILSON BOULEVARD, VIRGINIA UNITED STATES | Power Div-Min of Power, Energy & Mineral Resources | 5,032,957.03 | 5,032,957.03 |
GRID RELIABILITY STUDY FOR LNTEGRATION OF RENEWABL ENERGY INTO THE NATIONAL GRID | Loan 3523 | 22 Mar 2021 | STEAG ENERGY SERVICES LNDIA PVT. LTD., LNDIA | A-29, SECTCRR-16, NOIDA-201301, LNDIA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 179,590.58 | 179,590.58 |
PROCUREMENT OF CIVIL WORK FOR CONSTRUCTION OF HEAD QUATER OFFICICE BUILDING, WAREHOUSE RESIDENTIAL B UILDING AND OTEHR ANCILIARY WORK AT CHANDPUR PBS | Loan 3522 | 20 Jan 2020 | TBEAL-CC (JV) | 2ND FLOOR, STADIUM COMPLEX, KAZIR DEWARY CHITTAGONG, BANGLADESH BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,309,665.82 | 2,309,121.41 |
CONSTRUCTION OF OFFICE BUILDING, WORKSHOP, RESIDEN TIAL BUILDING, ANSAR BARAK ETC IN THAKURGOAN PBS AND DINAJPUR PBS-2 | Loan 3522 | 30 Jan 2020 | JOINT VENTURE OF DEDA-SSL | KABI FARUQUE SHARONI, NIKUNJA-2, KHULKHE T, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 5,811,014.55 | 5,811,014.55 |
CONSTRUCTION OF OFFICE BUILDING, RESIDENTIAL BUILD ING AT NAOGAON PBS-2, BOGRA PBS-2 AND BOGRA PBS-1 | Loan 3522 | 28 Jan 2020 | JOINT VENTURE OF DEDA-SSL | HOUSE NO. 11, KABI FARUQUE SARANI, NIKUN JA-2, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 6,125,672.09 | 6,124,938.25 |
TRANSMISSION PLANNING AND PROJECT PREPARATORY STUD IES FOR PGCB | Loan 3523 | 30 Jan 2020 | POWER GRID CORPORATION OF INDIA LTD | SAUDAMINI, PLOT NO.2, SECTOR 29, GURGAON , HARYANA, INDIA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,060,203.24 | 1,060,203.24 |
DESIGN, SUPPLY, INSTALLATION, TESTING & COMMISSION ING OF GOPALGANJ-MONGLA 400KV DOUBLE CIRCUIT TRANS MISSION LINE ON TURNKEY BASIS | Loan 3522 | 03 Jan 2019 | M/S KALPATARU POWER TRANSMISSION LIMITED | PLOT NO 101 PART III GIDC ESTATE SECTOR 28 GANDHINAGAR 382 028 GUJARAT INDIA | Power Div-Min of Power, Energy & Mineral Resources | 78,925,625.34 | 78,896,186.27 |
DESIGN,SUPPLY,INSTALLATION,TESTING AND COMMISSION ING OF PADMA RIVER CROSSING PORTION OF AMINBAZAR- GOPALGANJ 400KV DOUBLE CIRCUIT TRANSMISSION LINE | Loan 3522 | 03 Jan 2019 | M/S POWERCHINA SEPCO1 ELECTRIC POWER CONSTRUC | BUILDING A2-6, NO.7000 JINGSHIDONG ROAD HANYU JINGU JINAN INNOVATION ZONE SHANDO CHINA,PEOPLE'SREP.O | Power Div-Min of Power, Energy & Mineral Resources | 66,932,636.12 | 66,916,865.68 |
URIDS(W)-G-17-01 - LINE TOOLS AND OPERATIONAL EQUIPMENT | Loan 3522 | 21 Jan 2019 | MULTITECH INTERNATIONAL | HOUSE 4 ROAD 29 PALLABI MIRPUR 12 DHAKA 1216 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,170,000.25 | 1,170,000.25 |
DESIGN, MANUFACTURE, TEST, DELIVER AND COMMISSION FACILITIES FOR SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA) | Loan 3522 | 22 Apr 2019 | SIEMENS LIMITED INDIA | BIRLA AURORA LEVEL 21 PLOT NO. 1080 DR. ANNIE BEANT ROAD WORLI MUMBAI INDIA | Power Div-Min of Power, Energy & Mineral Resources | 9,015,331.69 | 9,008,181.40 |
PROCUREMENT UNDER URIDS(W)-G-15-01/01 FOR RAJSHAHI | Loan 3522 | 14 May 2019 | TOSHIBA TRANSMISSION & DISTRIBUTION SYSTEMS | RUDRARAM VILLAGE,PATANCHERU MANDAL, SANGAREDDY DISTRICT,PIN 502329,HYDERABAD INDIA | Power Div-Min of Power, Energy & Mineral Resources | 7,685,454.00 | 7,685,454.00 |
ANALYSIS OF TRANSMISSION AND DISTRIBUTION LOSSES AND ESTABLISHING LOSS TARGETS | Loan 3523 | 21 Jun 2019 | TATA POWER DELHI DISTRIBUTION LTD. INDIA | NDPL HOUSE HUDSON LINES KINGSWAY CAMP DELHI INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,117,800.00 | 1,117,800.00 |
DEVOLOPING NEW BUSINESS MODEL AND FEASIBILITY STUD Y IN ALLOCATED SITES FOR WIND POWER GENERATION | Loan 3523 | 26 Nov 2019 | POWER AND ENERGY CONSULTANTS INDIA LTD | DEVELOPMENT CHAMBER U-138, FIRST FLOOR, VIKAS MARG, SIKARPUR, DELHI, INDIA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 471,106.11 | 471,106.11 |
FEASIBILITY STUDIES AND DEVELOPMENT OF NEW BUISNES S MODELS FOR SOLAR PARKS AT TWO SITES IN BANGLADES H | Loan 3523 | 26 Nov 2019 | POWER AND ENERGY CONSULTANTS INDIA LTD. | DEVELOPMENT CHAMBER U-138, FIRST FLOOR, VIKAS MARG, SHAKARPUR, DELHI, INDIA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 467,232.64 | 467,232.64 |
CONSTRUCTION OF HEAD QUARTER OFFICE, ZONAL OFFICE COMPLEX FOR RAJSHASHI AREA URIDS(W)-CW-01, LOT NO. URIDS(W)-CW-01-04 | Loan 3522 | 23 Nov 2018 | DESH ENGINEERING & DEVELOPMENT AGENCY PVT LTD | HOUSE NO. 11 KABI FARUQUES SHARONI NIKUNJA 2 JOAR SHAHARA KHILKET DHAKA1229 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,912,180.00 | 1,908,184.00 |
CONSTRUCTION OF HEAD QUARTER OFFICE, ZONAL OFFICE COMPLEX AND RESIDENTIAL BLDG URIDS(W)-CW-01, LOT NO. URIDS(W)-CW-01-01 | Loan 3522 | 27 Nov 2018 | ZAZ & RT (JV) | PATKIYA BARI, HEMAYETPUR, PABNA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 4,338,421.00 | 4,338,421.00 |
CONSTRUCTION OF HEAD QUARETER OFFICE ZONAL OFFICE COMPLEX FOR RAJSHASHI AREA URIDS(W)CW-01, LOT NO. URIDS(W)CW-01-05 | Loan 3522 | 23 Nov 2018 | DESH ENGINEERING & DEVELOPMENT AGENCY PVT LTD | HOUSE NO. 11 KABI FARUQUE SHARONI NIKUN- JA 2 JOAR SHAHARA KHILKHET DHAKA 1229 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 4,213,270.00 | 4,204,465.00 |
CONSTRUCTION OF HEAD QUARTER OFFICE ZONAL OFFICE COMPLEX FOR RAJSHASHI AREA URIDS(W)-CW-01 LOT NO. URIDS(W)CW-01-06 | Loan 3522 | 23 Nov 2018 | DESH ENGINEERING & DEVELOPMENT AGENCY PVT LTD | HOUSE NO. 11 KABI FARUQUE SHARONI NIKUN- JA 2 JOAR SHAHARA KHILKHET DHAKA 1229 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,447,733.00 | 2,442,618.00 |
DESIGN, SUPPLY, TESTING AND COMMISSIONING OF AMINBAZAR 400/230 KV SUBSTATION ON TURNKEY BASIS | Loan 3522 | 01 Oct 2018 | HYOSUNG CORPORATION, KOREA | 119, MAPO-DAERA, MAPO-GU SEOUL, KOREA 121-720 KOREA, REPUBLIC OF | Power Div-Min of Power, Energy & Mineral Resources | 19,605,465.00 | 19,605,465.00 |
CIVIL WORKS FOR THE OCNSTRUCTION OF ZONAL OFFICE & RESIDENTIAL BUILDINGS AT MOHESKHALI AND UKHIYA OF COX'S BAZAR PBS | Loan 3522 | 30 Oct 2018 | MNH-SE (JV) | 3/4 A PURANA PALTON SABBIR TOWER 7TH FLR ROOM NO. 802 DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,467,376.00 | 2,467,376.00 |
CIVIL WORKS FOR THE CONSTRUCTION OF ZONAL OFFICE & RESIDENTIAL BUILDING AT CHATOK ZONAL OFFICE COMPLEX OF SUNAMGONJ PBS | Loan 3522 | 30 Oct 2018 | AHNAF TRADINGS | 384 MANIPUR MIRPUR-2 DHAKA 1216 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,222,285.00 | 1,222,285.00 |
CIVIL WORKS FOR THE CONSTRUCTION OF ZONAL OFFICE & RESIDENTIAL BUILDING AT NANDIL ZONAL OFFICE COMPLEX OF KISHORGONJ PBS | Loan 3522 | 30 Oct 2018 | AE & EE (JV) | KALIKIRTRE, RATANPUR, BHOLA SADAR, BHOLA DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,091,786.00 | 1,091,786.00 |
CIVIL WORKS FOR THE CONSTRUCTION OF ZONAL OFFICE & RESIDENTIAL BUILDING AT DAMUDA ZONAL OFFICE COMPLEX IN SHARIATPUR PBS | Loan 3522 | 30 Oct 2018 | A.K. ENTERPRISE | 44/F/8A WEST PANTHAPATH SHER-E-BANGLA NAGOR DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,076,719.00 | 1,076,719.00 |
CIVIL WORKS FOR THE CONSTRUCTION OF ZONAL OFFICE & RESIDENTIAL BUILDING AT FULLGAZI ZONAL OFFICE COMPLEX IN FENI PBS | Loan 3522 | 30 Oct 2018 | KARIGORI ENGINEERS & BUILDERS | HOUSE NO. 11 ROAD NO. 03 BLOCK H MIRPUR 1, SHAALI, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,004,030.00 | 1,004,030.00 |
PROCUREMENT OF CONDUCTOR (SUBMARINE & UNDERGROUND) UNDER URIDS(W)-G-02-03 FOR RAJSHAHI AREA | Loan 3522 | 18 Sep 2018 | MM CORPORATION | H-429, ROAD 30, NEW DOHS, MOHAKHALI, DHAKA 1206 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,865,110.00 | 1,865,110.00 |
PROJECT IMPLEMENTATION MONITORING CONSULTANT (PIMC) FOR URIDS | Loan 3522 | 06 Sep 2018 | SMEC INTERNATIONAL PTY. LTD. AUSTRALIA | LEVEL 10, 71 QUEENS ROAD, MELBOURNE VICTORIA 3004 AUSTRALIA | Power Div-Min of Power, Energy & Mineral Resources | 2,440,942.00 | 2,439,816.00 |
PROCUREMENT OF CONDUCTOR (BARE) FOR URIDS(E) DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 01 Aug 2018 | JIANGSU BOAN CABLE CO. LTD. | WEST SIDE OF CHAQUAN ROAD, HUANKEYUAN XINJIE STREET, YIXING CITY CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 10,866,404.00 | 10,866,404.00 |
PROCUREMENT OF LINE TOOLS AND OPERATIONAL EQUIP- MENT UNDER URIDS(E)-G-18-01 | Loan 3522 | 12 Jul 2018 | M/S TRADE EAST WEST CORPORATION LTD. | AFTAB HERITAGE 4TH FLOOR HOLDING NO. 2 ROAD NO. 4 SECTOR 1 UTTARA DHAKA 1230 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,439,957.00 | 1,439,957.00 |
PROCUREMENT OF SECTIONALIZING DEVICE UNDER URIDS (W)-G-15-02 | Loan 3522 | 12 Jul 2018 | GLOBAL MARKETING SERVICES JV SQ TRADING & | FLAT 13B 13TH FLOOR HOUSE#21 ROAD#17 BANANI, DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,166,351.00 | 1,166,351.00 |
DESIGN, SUPPLY, INSTALLATION, TESTING & COMMISSION ING OF THE PADMA RIVER CROSSING PORTION OF AMINBA- ZAR-MONGLA 400KV DOUBLE CIRCUIT TRANS.LINE | Loan 3522 | 20 Jun 2018 | M/S KEC INTERNATIONAL LIMITED | RPG HOUSE, 1ST FLOOR 463 DR. ANNIE BESAN T ROAD WORLI MUMBAI 400030 INDIA | Power Div-Min of Power, Energy & Mineral Resources | 14,732,061.00 | 14,732,061.00 |
PROCUREMENT OF CONDUCTOR (BARE) UNDER URIDS(W)-G- 11 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 13 Jun 2018 | BRB CABLE INDUSTRIES LIMITED | BSCIC INDUSTRIAL ESTATE, KUSHTIA 7000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 9,993,943.00 | 9,993,943.00 |
PROCUREMENT OF CONDUCTOR (INSULATED) UNDER URIDS(W G-11 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 13 Jun 2018 | JIANGSU BOAN CABLE CO. LTD. | WEST SIDE OF CHAQUAN ROAD, HUANKEYUAN XINJE STREET, YIXING CITY, JIANGSU CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 7,031,752.00 | 7,031,752.00 |
PROCUREMENT OF CONDUCTOR (SUBMARINE & UNDERGROUND) UNDER URIDS(W)-G-11 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 13 Jun 2018 | MM CORPORATION | HOUSE# 429 ROAD# 30 NEW DOHS MOHAKHALI DHAKA 1206 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,540,528.00 | 1,540,528.00 |
PROCUREMENT OF METER UNDER URIDS(E)-G-17 FOR DHAKA MYMENSINGH, CHITTAGONG & SYLHET DIVISION | Loan 3522 | 08 May 2018 | GLOBAL MARKETING SERVICES | BASHATI, HORIZON, LEVEL 13-B(13TH FLR) HOUSE21 ROAD17 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 4,329,264.00 | 4,329,264.00 |
PROCUREMENT OF INSULATOR UNDER URIDS(E)-G-10 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 11 May 2018 | PINGXIANG CENTRAL SOURCING CERAMIC CO. LTD. | FUTIAN GAOKENG ANYUAN DISTRICT PINGXIANG CITY JIANGXI PROVINCE CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 2,158,770.00 | 2,158,770.00 |
PROCUREMENT OF DISTRIBUTION TRANSFORMER UNDER URIDS(E)-G-16 FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 05 Apr 2018 | TOSHIBA TRANSMISSION & DISTRIBUTION SYSTEMS | RUDRARAM VILLAGE, PATANCHERU MANDAL, SANGAREDDY DISTRICT 502329 HYDERABAD INDIA | Power Div-Min of Power, Energy & Mineral Resources | 9,097,420.00 | 9,097,420.00 |
LOT 2: URIDS(E)-G-16-02 PROCUREMENT OF SECTIONALIZING DEVICES FOR DHAKA, MYMESIGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 18 Apr 2018 | GLOBAL MARKETING SVCES JV SQ TRADING & ENGG | BASHATI HORIZON, 13B, HSE 21, RD 17, BANANI, DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,162,859.00 | 1,162,859.00 |
PROCUREMENT OF CONDUCTOR BARE UNDER URIDS(E) FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 28 Mar 2018 | B&T CABLES LIMITED JV WITH SQ WIRE & CABLE | HOUSE NO 78 ROAD NO 2 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 12,839,568.00 | 12,839,568.00 |
PROCUREMENT OF CONDUCTOR, INSULATED FOR URIDS(E) UNDER DHAKA, MYMENSINGH,CHITTAGONG & SYLHET DIVI SIONS | Loan 3522 | 28 Mar 2018 | BRB CABLE INDUSTRIES LIMITED | BSCIC INDUSTRIAL ESTATE, KUSHTIA 7000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 8,674,841.00 | 8,674,695.00 |
PROCUREMENT OF CONDUCTOR, BARE UNDER URIDS(W)-G-02 FOR RAJSHAHSI, RANGPUR, KHULNA AND BARISHAL DIVISI ONS | Loan 3522 | 20 Feb 2018 | BRB CABLE INDUSTRIES LIMITED | BSCIC INDUSTRIAL ESTATE, KUSHTIA 7000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 9,313,902.00 | 9,313,869.00 |
PROCUREMENT OF CONDUCTOR, INSULATED UNDER URIDS(W) -G-02 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 20 Feb 2018 | BRB CABLE INDUSTRIES LIMITED | BSCIC INDUSTRIAL ESTATE, KUSHTIA 7000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 7,955,416.00 | 7,955,384.00 |
PROCUREMENT UNDER URIDS(W)-G-16 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 23 Feb 2018 | M/S GLOBAL MARKETING SERVICES | BASHATI HORIZON LEVEL 13B 13TH FLR HOUSE 21 ROAD 17 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 3,350,327.00 | 3,350,327.00 |
PROCUREMENT OF GUY & GROUDING WIRE UNDER URIDS(W)- G-12 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 20 Feb 2018 | M/S TRADE EAST WEST CORPORATION LTD. | AFTAB HERITAGE 4TH FLR HOLDING NO.2 ROAD NO 4 SECTOR 1 UTTARA DHAKA 1230 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,121,684.00 | 2,121,662.00 |
PROCUREMENT OF CONDUCTOR & GUY ACCESSORIES UNDER URIDS(W)-G-12 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 23 Feb 2018 | KSE ELECTRICALS PVT. LTD. | 33A CHOWRINGHEE ROAD 7TH FLR BLK 2 KOLKATA 700071 INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,452,400.00 | 1,452,400.00 |
PROCUREMENT OF SPC POLE UNDER URIDS(E) FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS. | Loan 3522 | 02 Jan 2018 | DADA ENGINEERING LIMITED JV WITH POLES AND | JAMUNA FUTURE PARK 6TH FLOOR KA-244 PRO GOTI SARANI BARIDHARA DHAKA 1229 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 13,432,744.00 | 13,432,744.00 |
LINE HARDWARE UNDER URIDS(W)-G-10 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 22 Jan 2018 | M/S PINGXIANG HUACI INSULATORS GROUP CO. LTD. | LUXI INDUSTRIAL PARK, PINGXIANG, JIANGXI CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 2,189,460.00 | 2,189,460.00 |
PROCUREMENT OF SPC POLE UNDER URIDS(E) FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 02 Jan 2018 | ROYAL GREEN PRODUCTS LIMITED JV WITH PATHER | 9/F MOTIJHEEL C/A STOCK EXCHANGE BUILDIN G 5TH FLOOR DHAKA1000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 9,027,859.00 | 9,027,859.00 |
PROCUREMENT OF LINE HARDWARE UNDER URIDS(E)-G-10 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 25 Jan 2018 | M/S CONFIDENCE STEEL LIMITED JV WITH PASHA | UTC BLDG LEVEL 7 08 PANTHAPATH KAWRAN BAZAR DHAKA1215 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 3,123,955.00 | 3,123,955.00 |
PROCUREMENT OF GUY & GROUNDING WIRE UNDER URIDS(E) FOR DHAKA, MYMENSIGH, CHITTAGONG & SYLHET DIVISION | Loan 3522 | 02 Jan 2018 | M/S GLOBAL MARKETING SERVICES | BASHATI HORIZON LEVEL 12B 13TH FLR HOUSE 21 ROAD 17 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,333,720.00 | 2,333,720.00 |
PROCUREMENT OF LINE HARDWARE UNDER URIDS(E)-G-10 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 25 Jan 2018 | M/S PASHA ELECTRO INDUSTRIES LIMITED JV WITH | SOUTH AVENUE TOWER BLOCK B 2ND FLR HOUSE 50 ROAD 3 GULSHAN AVE GULSHAN DHAKA 1212 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 3,123,390.00 | 3,123,390.00 |
SPC POLES UNDER URIDS(W) FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 03 Jan 2018 | CONTECH CONSTRUCTION LIMITED JV WITH ROYAL | HOUSE NO 78 ROAD NO 2 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 12,377,890.00 | 12,377,890.00 |
SPC POLES UNDER URIDS(W) FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 03 Jan 2018 | POLES AND CONCRETE LIMITED JV WITH ELECTROPAC | BANASHILPA BHABAN 4TH FLR 73 MOTIJHEEL C/A DHAKA 1000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 12,376,535.00 | 12,376,535.00 |
SPC POLES UNDER URIDS(W) FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 03 Jan 2018 | GEMCON LIMITED JV WITH DADA ENGINEERING LTD. | HOUSE NO 44 ROAD NO 16 (NEW) 27(OLD) DHANMONDI DHAKA 1209 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 12,370,418.00 | 12,370,418.00 |
SPC POLES UNDER URIDS(W) FOR RAJSHAHSI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 03 Jan 2018 | CASTLE CONSTRUCTION CO. LTD. JV WITH (1)PRE- | HOUSE NO 44 ROAD NO 16(NEW) 27 (OLD) DHANMONDI DHAKA 1209 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 8,041,920.00 | 8,041,920.00 |
PROCUREMENT OF CONDUCTOR ACCESSORIES AND GUY ACCESSORIES UNDER URIDS(E)-G-14 FOR DHAKA, MYMEN- SINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 09 Jan 2018 | KSE ELECTRICALS PVT. LTD. | 33A CHOWRINGHE ROAD, 7TH FLOOR, BLOCK 2 KOLKATA 700071 INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,538,560.00 | 1,538,560.00 |
PROCUREMENT OF CONDUCTOR UNDER URIDS(E) FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 12 Jan 2018 | NINGBO ORIENT WIRES AND CABLES CO. LTD. | 21F NO. 1 BUILDING LANE 999 YANGFAN ROAD NINGBO NATIONAL HI & NEW TECH IND DEV CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 1,433,760.00 | 1,433,721.00 |
PROCUREMENT OF SPC POLE UNDER URIDS(E) FOR DHAKA, MYMENSIGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 02 Jan 2018 | TSCO POWER LIMITED JV WITH CHARKA SPC POLES | LEVEL 13/B HOUSE 21 ROAD 17 BANANI C/A DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 13,438,316.00 | 13,438,316.00 |
PROCUREMENT OF LINE HARDWARE UNDER URIDS(W)-G-10 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL | Loan 3522 | 22 Jan 2018 | M/S PASHA ELECTRO INDUSTRIES LIMITED JV WITH | SOUTH AVENUE TOWER BLOCK B 2ND FLOOR, HOUSE 50 ROAD 3 GULSHAN AVE DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,937,424.00 | 2,937,424.00 |
PROCUREMENT OF SPC POLE FOR URIDS(E) FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS. | Loan 3522 | 02 Jan 2018 | CONFIDENCE POWER LIMITED JV WITH PRE-STRESSED | UTC BUILDING LEVEL 7 08 PANTHUPATH KAWRA N BAZAR DHAKA 1215 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 13,437,064.00 | 13,437,064.00 |
LINE HARDWARE UNDER URIDS(W)-G-10 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS. | Loan 3522 | 22 Jan 2018 | M/S CONFIDENCE STEEL LIMITED JV WITH PASHA | UTC BLDG LEVEL 7 08 PANTHAPATH KAWRAN BAZAR DHAKA 1215 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,933,900.00 | 2,933,900.00 |
URIDS (W)-G-14-01 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 07 Dec 2017 | M/S B-TRAC ENGINEERING LIMITED JV WITH | 335/A TEJGAON I/A DHAKA 1208 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,420,601.00 | 2,420,601.00 |
URIDS(E)-G-02-02 FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 07 Dec 2017 | B&T CABLES LIMITED JV WITH SQ WIRE & CABLE CO | HOUSE NO. 78 ROAD NO.2 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 8,757,313.00 | 8,757,313.00 |
URIDS(E)-G-06-01 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 07 Dec 2017 | TS TRANSFORMERS LIMITED | LEVEL #13/B, HOUSE #21 ,ROAD #17 BANANI C/A DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 7,591,460.00 | 7,591,460.00 |
URIDS(E)-G-06-02 FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 22 Dec 2017 | M/S GLOBAL MARKETING SERVICES JV SQ TRADING | BASHATI HORIZON LEVEL 38 (13TH FLR) HOUSE#21 ROAD#17 BANANI DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,026,346.00 | 1,026,346.00 |
URIDS(W)-G-06-01 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 07 Dec 2017 | M/S CONFIDENCE ELECTRIC LIMITED | UTC BUILDING 7TH FLOOR 8 PANTHAPATH KAWRAN BAZAR DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 6,050,820.00 | 6,050,820.00 |
URIDS(W)-G-14-02 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 07 Dec 2017 | M/S MAMA BHAGNA TIMBER TRADERS JV WITH M/S | JOYNABARI, HEMAYETPUR, SAVAR, DHAKA 1340 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,181,630.00 | 1,181,630.00 |
URIDS(W)-G-03-01 | Loan 3522 | 03 Nov 2017 | KSE ELECTRICALS PVT. LTD | 33A CHOWRINGHEE ROAD, 7TH FLR, BLOCK 2 KOLKATA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,380,795.00 | 1,380,795.00 |
URIDS(W)-G-03-03 | Loan 3522 | 03 Nov 2017 | M/S GLOBAL MARKETING SERVICES | BASHAL HORIZON LEVEL 13B HOUSE#21 ROAD17 BANANI DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,699,239.00 | 1,699,239.00 |
URIDS(E)-G-07-01 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 07 Nov 2017 | M/S TECHNO ELECTRICALS LTD. | BASHATI HORIZON LEVEL 12A HOUSE 21 ROAD 17 BANANI DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 4,023,410.00 | 4,023,410.00 |
CONSULTANCY SERVICES FOR PROJECT MANAGEMENT, SUPERVISION AND IMPLEMENTATION SUPPORT FOR DESCO | Loan 3522 | 02 Nov 2017 | HIFAB OY (FINLAND) | LARS SONCKIN KAAR1 16 02600 ESPOO FINLAND | Power Div-Min of Power, Energy & Mineral Resources | 1,510,501.00 | 1,510,501.00 |
LOT 2: PROCUREMENT OF ANCHOR LOG | Loan 3522 | 31 Oct 2017 | DIRAN ENTERPRISE LTD. JV ESACK BROTHER IND | 582/1 KAZIPARA BEGUM ROKEYA SARANI MIRPUR DHAKA-1216 BANGLADESH BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,285,013.00 | 1,285,013.00 |
URIDS(E)-G-01-03 FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 06 Oct 2017 | M/S PINGSIANG HUACI INSULATORS GROUP CO. LTD. | LUXI INDUSTRIAL PARK PINGXIANG JIANGXI CHINA CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 1,949,540.00 | 1,949,540.00 |
LOT 1: PROCUREMENT OF STEEL CROSS ARM | Loan 3522 | 31 Oct 2017 | CONFIDENCE STEEL LTD JV B-TRAC ENGINEERING | UTC BUILDING 7TH FLOOR, 8 PANTHAPATH KAWRAN BAZAAR DHAKA 1215 BANGLADESH BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,331,280.00 | 2,331,280.00 |
URIDS(E)-G-01-02 FOR DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISION | Loan 3522 | 05 Oct 2017 | M/S PASHA ELECTRO INDUSTRIES LTD. | SOUTH AVENUE TOWER, BLOCK B 2ND FLOOR, HOUSE 50 ROAD 3 GULSHAN AVE, GULSHAN BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,985,461.00 | 2,985,461.00 |
URIDS(E)-G-01-01 PROCUREMENT OF LINE HARDWARE & INSULATOR | Loan 3522 | 05 Oct 2017 | M/S CONFIDENCE STEEL LIMITED | UTC BLDG LEVEL 7, 08, PANTHAPATH KAWRAN BAZAR, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 3,030,675.00 | 3,030,675.00 |
UIRDS(E)G-03-01: PROCUREMENT OF CONDUCTOR ACCESSOR IES & GUY ACCESSORIES FOR DHAKA, MYMENSIGNH, CHITT AGONG & SYLHET DIVISIONS | Loan 3522 | 20 Sep 2017 | KSE ELETRICALS PVT. LTD. | 33A CHOWRINGHEE ROAD, 7TH FLOOR, BLK2 KOLKATA 700071 INDIA | Power Div-Min of Power, Energy & Mineral Resources | 1,500,892.00 | 1,500,892.00 |
URIDS(E)-G-03-03: PROCUREMENT OF GUY & GROUNDING WIRE FOR DHAKA, MYMENSINGH, CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 20 Sep 2017 | M/S GLOBAL MARKETING SERVICES | BASHATI HORIZON, LEVEL 138(13TH FLR) HOUSE 21 ROAD17 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,857,957.00 | 1,857,957.00 |
URIDS(W)-G-07-01 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 12 Sep 2017 | HEXING ELECTRICAL CO. LTD. | 1418 MOGANSHAN ROAD, SHANGCHENG INDUSTRI AL ZONE 310011 HANGZHOU CHINA,PEOPLE'SREP.OF | Power Div-Min of Power, Energy & Mineral Resources | 2,019,850.00 | 2,019,850.00 |
URIDS(W)-G-04, LOT NO. URIDS(W)-G-04-02 | Loan 3522 | 09 Aug 2017 | CONTECH CONSTRUCTION LIMITED JV WITH | HOUSE NO. 78 ROAD NO. 2 BANANI DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 14,516,455.00 | 14,516,455.00 |
URIDS(W)-G-01-03 FOR RAJSHASHI, RANGPUR, KHULNA, AND BARISHAL DIVISIONS | Loan 3522 | 30 Aug 2017 | M/S DIRAN INSULATOR FACTORY LIMITED | INDIA | Power Div-Min of Power, Energy & Mineral Resources | 2,112,420.00 | 2,112,420.00 |
URIDS(W)-G-01-01 FOR RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 30 Aug 2017 | M/S PASHA ELECTRO INDUSTRIES LTD. | SOUTH AVENUE TOWER, BLOCK B 2ND FLR HOUSE #50 ROAD3, GULSHAN AVE, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,355,449.00 | 2,355,449.00 |
URIDS(W)-G-01-02 FOR RAJSHASHI, RANGPUR, KHULNA BARISHAL DIVISIONS | Loan 3522 | 30 Aug 2017 | M/S CONFIDENCE STEEL LIMITED | UTC BLDG LEVEL 7,08, PANTHAPATH, KAWRAN BAZAR, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 2,470,215.00 | 2,470,215.00 |
URIDS(W)-G-04, LOT NO. URIDS(W)-G-04-03 | Loan 3522 | 09 Aug 2017 | POLES & CONCRETE LIMITEDJV WITH | 4TH FLOOR 73 MOTIJHEEL C/A DHAKA 1000 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 14,511,474.00 | 14,511,474.00 |
URIDS(W)-G-04, LOT NO. URIDS(W)-G-04-01 | Loan 3522 | 09 Aug 2017 | CASTLE CONSTRUCTION CO. LTD. JV WITH | HOUSE NO. 44 ROAD NO. 16 (NEW) 27 (OLD) DHANMONDI, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 14,514,830.00 | 14,514,830.00 |
LOT 1:URIDS(E) G-05-2 OF PACKAGE NO. G-05 PROCUREMENT OF ANCHOR LOG UNDER URIDS DHAKA, MYMENSINGH,CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 11 Jul 2017 | M/S MAMA BHAGNA TIMBER TRADERS JV WITH | JOYNABARI, HEMAYETPUR, SAVAR, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,286,592.00 | 1,286,592.00 |
PACKAGE NO. URIDS(W) G-05 LOT NO: URIDS(W)G-05-1 PURCHASE OF STEEL CROSS ARM UNDER URIDS RAJSHASHI, RANGPUR, KHULNA & BARISHAL DIVISIONS | Loan 3522 | 11 Jul 2017 | KSE ELECTRICALS PVT. LTD. | 33A CHOWRINGHEE ROAD 7TH FLOOR BLOCK 2 KOLKATA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 2,142,670.00 | 2,142,670.00 |
LOT 1:URIDS(E) G-05-01 OF PACKAGE NO. URIDS(E)G-05 PROCUREMENT OF STEEL CROSS ARM UNDER URIDS DHAKA, MYMENSINGH, CHITTAGONG AND SYLHET DIVISIONS | Loan 3522 | 11 Jul 2017 | KSE ELECTRICALS PVT. LTD | 33A CHOWRINGBEE ROAD 7TH FLOOR BLOCK 2 KOLKATA INDIA | Power Div-Min of Power, Energy & Mineral Resources | 2,336,757.00 | 2,336,757.00 |
LOT 1:URIDS(E) G-04-3 OF PACKAGE NO. URIDS(E) G-04 PROCUREMENT OF SPC POLE UNDER URIDS DHAKA,MYMENSINGH,CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 11 Jul 2017 | DADA ENGINEERING LIMITED JV WITH CHARKA SPC | JAMUNA FUTURE PARK 6TH FLOOR KS-244 PROTOGI SARANI, BARIDHARA, DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 15,991,240.00 | 15,991,240.00 |
LOT 1: URIDS(E) G-04-01 OF PACKAGE NO. UIRDS(E) G-04 (PROCUREMENT OF SPC POLE UNDER URIDS DHAKA,MYMENSINGH,CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 11 Jul 2017 | M/S CONFIDENCE POWER LIMITED JV WITH | UTC BLDG 08 PANTHAPATH KAWRAN BAZAR DHAKA 1215 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 15,993,736.00 | 15,993,736.00 |
LOT 1:URIDS(E) G-04-2 OF PACKAGE NO. URIDS(E) G-04 PROCUREMENT OF SPC POLE UNDER URIDS DHAKA,MYMENSINGH,CHITTAGONG & SYLHET DIVISIONS | Loan 3522 | 11 Jul 2017 | TSCO POWER LIMITED JV WITH POLES & CONCRETE | LEVEL 13B HOUSE#21 ROAD#17 BANANI C/A DHAKA 1213 BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 15,997,552.00 | 15,997,552.00 |
PACKAGE NO. URIDS(W)G-05 LOT NO. URIDS(W)G-05-02 PURCHASE OF ANCHOR LOG UNDER URIDS RAJSHASHI, RANGPUR, KHULNA AND BARISHAL DIVISIONS | Loan 3522 | 11 Jul 2017 | M/S DIRAN ENTERPRISE LTD. JV QUALITY TIMBER | 582/1, KAZIPARA, ROKEYA SARANI, MIRPUR DHAKA BANGLADESH | Power Div-Min of Power, Energy & Mineral Resources | 1,184,537.00 | 1,184,537.00 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Bangladesh Power System Enhancement and Efficiency Improvement Project: Procurement Plan | Procurement Plans | Jan 2023 |
Bangladesh Power System Enhancement and Efficiency Improvement Project: Procurement Plan | Procurement Plans | Jul 2016 |