Myanmar : Power Network Development Project
The project will construct (i) 16.6 km transmission line between Ahlone and Thida substations with a 230/66/11kV 150 MVA Ahlone substation and 230/66/11kV (3x150 MVA) GIS Thida substation; (ii) 286km Mawlamyine-Ye-Dawei transmission line with 230/66/11kV (2 x 50 MVA) Ye substation and 230/66/11kV (2 x 50 MVA) Dawei substation; and (iii) upgrade and construct 48 new 66/33/11kV substations with 843 km distribution lines in the following states and regions: Aeyawardy, Bago, Mon, Kayin and Rakhine. The project will also install a computerized transmission asset management systems (CAMS) and a computerized customer billing system (CCBS) to improve operational efficiency and reduce losses in the transmission and distribution systems.
Project Details
-
Project Officer
Inoue, Yuki
Sectors Group
Request for information -
Country/Economy
Myanmar -
Modality
-
Sector
- Energy
Related Projects
- Project Name
- Power Network Development Project
- Project Number
- 50020-002
- Country / Economy
- Myanmar
- Project Status
- Active
- Project Type / Modality of Assistance
- Loan
- Source of Funding / Amount
Loan 3748-MYA: Power Network Development Project Source Amount Concessional ordinary capital resources lending US$ 298.90 million - Strategic Agendas
- Environmentally sustainable growth
- Inclusive economic growth
- Drivers of Change
- Private sector development
- Sector / Subsector
Energy / Electricity transmission and distribution
- Gender
- No gender elements
- Description
- The project will construct (i) 16.6 km transmission line between Ahlone and Thida substations with a 230/66/11kV 150 MVA Ahlone substation and 230/66/11kV (3x150 MVA) GIS Thida substation; (ii) 286km Mawlamyine-Ye-Dawei transmission line with 230/66/11kV (2 x 50 MVA) Ye substation and 230/66/11kV (2 x 50 MVA) Dawei substation; and (iii) upgrade and construct 48 new 66/33/11kV substations with 843 km distribution lines in the following states and regions: Aeyawardy, Bago, Mon, Kayin and Rakhine. The project will also install a computerized transmission asset management systems (CAMS) and a computerized customer billing system (CCBS) to improve operational efficiency and reduce losses in the transmission and distribution systems.
- Project Rationale and Linkage to Country/Regional Strategy
- The core developmental problem of Myanmar's power sector is insufficient and obsolete transmission and distribution infrastructure and lack of generating capacity to adequately supply electricity to support economic development and poverty reduction. With forecasted high economic growth, Myanmar's electricity demand is expected to rise fivefold from 3070 megawatt (MW) in 2017 to 14500 MW in 2030. The project will contribute to increasing electricity supply to support inclusive and sustainable development, and to achieving the country's plan of universal electricity access by 2030.
- Impact
Universal electricity access achieved
Project Outcome
- Description of Outcome
Capacity and operational efficiency of power transmission and distribution in central and southern Myanmar increased
- Progress Toward Outcome
Implementation Progress
- Description of Project Outputs
Myanmar''s 230 kV power transmission network expanded
New distribution facilities added to the distribution systems in Ayeyarwady and Bago regions and in Kayin, Mon, and Rakhine states
New computerized assets management systems (CAMS) and computerized customer billing system (CCBS) installed
- Status of Implementation Progress (Outputs, Activities, and Issues)
- Geographical Location
- Nation-wide
Safeguard Categories
- Environment
- B
- Involuntary Resettlement
- B
- Indigenous Peoples
- C
Summary of Environmental and Social Aspects
- Environmental Aspects
- Under the Transmission Component, an environmental impact assessment report with environmental management plan was prepared. These reports were based on the results of site visits, discussions with local authorities and beneficiaries, and the use of secondary sources of information such as similar projects. The assessment provided that expected impacts will occur during the different phases of the project development. The project was initially categorized as A due to the long Mawlamyine-Ye-Dawei transmission line potentially encroaching a biodiversity area. However, the final alignment chosen as a result of due diligence completely avoided all environment sensitive areas, hence, the environment assessment confirmed that the project is not considered as highly complex and sensitive and is now re-categorized as B.
- Involuntary Resettlement
- Land acquisition for the project will result in physical and economic displacement. A total of 39 hectares for land (38 hectares for distribution component and 1 hectare for transmission component) will be acquired permanently to be used for tower footings and substations. The project will have an impact on a total of 814 households. Of these, 18 households will be severely affected: nine households will lose their primary residential structures under the transmission component, and the other nine households will lose more than 10% of the total land holdings or income under the distribution component.
- Indigenous Peoples
- Three of the five states, namely Mon, Kayin and Rakhine have ethnic groups residing in the project area. The project will not acquire lands that are traditionally used by the ethnic groups nor cause any adverse impact on their identity, social, culture, or spiritual importance or interfere with their socio-cultural beliefs and livelihood systems. Ethnic group communities will benefit from project activities through employment opportunities and household electrifications. However, the project also presents minor risks and challenges concerning ethnic groups, particularly in terms of ensuring that ethnic groups are not marginalized during the project implementation with regards to employment opportunities and access to electricity. The project will ensure adequate consultations and a comprehensive project management approach in project areas where there are already ethnic group organizations providing parallel social services and community infrastructure. REGDPs have been developed with the approaches and entries that ensure project design and implementation shall foster full respect of ethnic groups and full respect for all affected households and stakeholders and that the ethnic groups (i) do not suffer adverse impacts as a result of the project, (ii) have equitable access to benefits of the project, and (iii) can participate actively in the project.
Stakeholder Communication, Participation, and Consultation
- During Project Design
- Analyses for the following will be conducted: participation and empowerment; social impacts assessment; employment opportunities; gender issues and Gender Action Plan; ethnic minority issues, if applicable; consultations with project affected peoples, project beneficiaries, stakeholders, civil society organizations to identify issues, propose measures for addressing them through consultations; conduct specific conflict- sensitive consultations in all relevant project areas.
- During Project Implementation
- Continuous consultation and participation process will involve a stakeholder analysis followed by subsequent consultations with various groups. It is planned to conduct consultations at the household and community level, regional and national government officials, development partners, nongovernmental organizations, and commune- and village- level officials and beneficiaries. A series of focus group discussions will be undertaken as part of the socio-economic analysis.
Business Opportunities
- Consulting Services
- The project implementation consultants for transmission and distribution components will be recruited in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). An estimated 281 person-months of consulting services will be required for the transmission component and 300 person-months for the distribution component. The consultants will support the project implementation unit in project implementation, monitoring and reporting; and strengthen the institutional and operational capacity of the EA/IAs.
- Procurement
All procurement of goods and works, and advance contracting will be undertaken in accordance with ADB's Procurement Guidelines (2015, as amended from time to time).
The project involves the procurement of three (3) plant-design, supply and installation and one (1) IT product contract under the transmission component; and seven goods and one (1) IT product contract under the distribution component. International competitive bidding with single-stage one-envelope method will be used for procurement of these contracts. ADB's prior review procedures will be followed. Line installation works, substation installation works, and supply of concrete poles will be undertaken through national competitive bidding using ADB's standard bidding documents for small works. Before the start of any procurement, ADB and the government will review the public procurement laws of the central and state governments to ensure consistency with ADB's Procurement Guidelines (2015, as amended from time to time).
Contact
- Responsible ADB Officer
- Inoue, Yuki
- Responsible ADB Department
- Sectors Group
- Responsible ADB Division
- Energy Sector Office (SG-ENE)
- Executing Agencies
-
Ministry of Electricity and Energy
Timetable
- Concept Clearance
- 26 Sep 2016
- Fact Finding
- 22 Jan 2018 to 02 Feb 2018
- MRM
- 04 Apr 2018
- Approval
- 28 Nov 2018
- Last Review Mission
- -
- Last PDS Update
- 15 Jun 2019
Funding
Loan 3748-MYA
Approval | Signing Date | Effectivity Date | Closing | ||
---|---|---|---|---|---|
Original | Revised | Actual | |||
28 Nov 2018 | 28 Dec 2018 | 25 Feb 2019 | 31 Dec 2025 | - | - |
Total (Amount in US$ million) | |
---|---|
Project Cost | 308.90 |
ADB | 298.90 |
Counterpart | 10.00 |
Cofinancing | 0.00 |
Date | ADB | Others | Net Percentage | |
---|---|---|---|---|
Cumulative Contract Awards | 06 Jun 2024 | 72.03 | 0.00 | 24% |
Cumulative Disbursements | 06 Jun 2024 | 7.31 | 0.00 | 2% |
Category | Sector | Safeguards | Social | Financial | Economic | Others |
---|---|---|---|---|---|---|
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Power Network Development Project: Procurement Plan | Procurement Plans | Nov 2020 |
Power Network Development Project: Project Administration Manual | Project/Program Administration Manual | Jul 2019 |
Loan Agreement (Ordinary Operations [Concessional]) for Loan 3748-MYA: Power Network Development Project | Loan Agreement (Ordinary Resources) | Dec 2018 |
Power Network Development Project: Report and Recommendation of the President | Reports and Recommendations of the President | Oct 2018 |
Power Network Development Project: Project Administration Manual | Project/Program Administration Manual | Sep 2018 |
Power Network Development Project: Project Data Sheet (Myanmar Language Translation) | Translated PDS | Sep 2016 |
Power Network Development Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Sep 2016 |
Power Network Development Project: Project Preparatory Technical Assistance Report | Project Preparatory Technical Assistance Reports | Sep 2016 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Loan 3748-MYA: Power Network Development Project [Package No. (2) – 47(T) DPTSC(PTP)/(2019-2020)] - CORRIGENDUM | Invitation for Bids | Closed | ||
Loan 3748-MYA: Power Network Development Project [Package No. (2) – 47(T) DPTSC(PTP)/(2019-2020)] - ORIGINAL | Invitation for Bids | Closed | ||
Loan 3748-MYA: Power Network Development Project [Package No (3)] | Invitation for Bids | Closed | ||
Project Implementation Consultant (Transmission) | Firm - Consulting | Closed | ||
Project Implementation Consultant (Distribution) | Firm - Consulting | Closed | ||
50020-MYA: Power Network Development Project | Advance Notice | Active |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
PACKAGE 2. DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING, 230 KV YE & DAWEI SUBSTATION, EXTENSION OF 230 KV MAWLAMYINE SUBSTATION | Loan 3748 | 15 Sep 2020 | XIAN ELECTRIC ENGINEERING CO. LTD | 7 TANGXING ROAD, XIAN, PRC CHINA,PEOPLE'SREP.OF | Ministry of Electricity and Energy | 20,299,388.29 | 20,299,388.29 |
PACKAGE 3. DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING. 230 KV MAWLAMYINE-YE-DAWEI TRANSMISSION LINE | Loan 3748 | 14 Aug 2020 | KALPATARU POWER TRANSMISSION LIMITED | 101 KALPATARU SYNERGY OPP GRAND HYATT SANTACRUZ (E) MUMBAI INDIA | Ministry of Electricity and Energy | 47,285,740.78 | 47,285,740.78 |
PROJECT IMPLEMENTATION CONSULTANT (TRANSMISSION COMPONENT) PACKAGE 5. | Loan 3748 | 28 Apr 2020 | JV KOREA ELECTRIC ENGINEERING & CONSULTING | 1012-HO HYUNDAI VENTURE BLDG. GANGNAM-GU, SEOUL, KOREA KOREA, REPUBLIC OF | Ministry of Electricity and Energy | 4,442,904.25 | 4,442,904.25 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Power Network Development Project: Procurement Plan | Procurement Plans | Nov 2020 |