India : Assam Power Transmission Improvement Project
Government of Assam and Assam Electricity Grid Corporation Limited (AEGCL) informed ADB that number of subprojects from 13th Development Plan have been shortlisted and included in the proposed Assam Power Transmission Improvement Project (APTIP) with an estimated total project cost at around $670 million. The project plans to add significant transmission capacity in Assam as well as improve overall network efficiency and reliability. AEGCL through Government of Assam and Government of India is planning to request ADB for a loan up to $500 million to fund the project.
Detailed project report (DPR) for APTIP was submitted to ADB. The following subprojects are identified for investments:
(i)Construction of new grid substations (220/132 kV; 220/132/33 kV; 220/33 kV; 132/33 kV; and 132/11 kV);
(ii)Augmentation of existing 220/132 kV substations by increasing transformers capacity;
Project Details
-
Project Officer
Yusupov, Aziz A.
South Asia Department
Request for information -
Country/Economy
India -
Modality
-
Sector
- Energy
Project Name | Assam Power Transmission Improvement Project | ||||
Project Number | 50048-001 | ||||
Country / Economy | India |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development |
||||
Sector / Subsector | Energy / Electricity transmission and distribution |
||||
Gender | No gender elements | ||||
Description | Government of Assam and Assam Electricity Grid Corporation Limited (AEGCL) informed ADB that number of subprojects from 13th Development Plan have been shortlisted and included in the proposed Assam Power Transmission Improvement Project (APTIP) with an estimated total project cost at around $670 million. The project plans to add significant transmission capacity in Assam as well as improve overall network efficiency and reliability. AEGCL through Government of Assam and Government of India is planning to request ADB for a loan up to $500 million to fund the project. Detailed project report (DPR) for APTIP was submitted to ADB. The following subprojects are identified for investments: (i)Construction of new grid substations (220/132 kV; 220/132/33 kV; 220/33 kV; 132/33 kV; and 132/11 kV); (ii)Augmentation of existing 220/132 kV substations by increasing transformers capacity; (iii)Conversion of existing substations with air insulated switchgear to gas insulated switchgear (220/132/33kV and 132/33 kV) (iv)Construction of 220 kV and 132 kV transmission lines; and (v) Augmentation and reconductoring of the existing 220 kV and 132 kV transmission lines ADB is going to provide a project preparatory technical assistance (TA) to support the due diligence and preparatory work for the ensuing Assam Power Transmission Improvement Project. The TA will require total of 15 person-months of consulting services to help with project preparation. Individual consultants will be recruited to support the executing agency and ADB in conducting due diligence on financial management, financial and economic analysis, and safeguards (environment, involuntary resettlement, and indigenous peoples) as well as assisting the executing agency with contracting strategy and bid documents preparation. ADB intends to hire consultants as soon as possible, and conduct another mission to finalize the project concept, followed by further due diligence. Four international and two national consultants will be recruited. ADB will engage the consultants on an individual basis in accordance with its Guidelines on the Use of Consultants by ADB and its Borrowers, and other arrangements satisfactory to ADB for engaging individual consultants. |
||||
Project Rationale and Linkage to Country/Regional Strategy | Assam's power sector faces serious challenges: about 37% of households have access to electricity with about 56 hours of power cuts per day. In fiscal year (FY) 2015, peak demand for power was 1,457 megawatt (MW) against available supply of 1,250 MW, indicating a shortfall of 13.3%. Only about 35% of the state's 700 tea gardensone of the mainstays of the Assam economyare supplied with grid electricity. On the supply side, Assam is heavily dependent on power imports from other states, with only about 25% of demand currently met by in-state generation. During peak periods, Assam is forced to purchase as much as 15% of its power requirement from independent power producers at very high cost. Demand for power is projected to increase to 2,417 MW by FY2019. Substantial investments in power generation, transmission and distribution value chain are required to meet the growing demand and ensure energy security. In addition to inadequate generation capacity, the power availability in Assam has also been severely constrained by network limitations. While generation capacity is expected to soon catch up with anticipated demand, limited capacity of the Assam state transmission and distribution system can continue to constrain delivery of power to consumers. The current physical constraints in the transmission system mean that Assam residents are unable to fully access clean power, missing the opportunity to reduce greenhouse gas emissions. The system study indicates an imminent need for significant investment in transmission to ensure that capacity addition in generation results in power that is available for input into the distribution system. |
||||
Impact | Readiness in implementing clean energy transmission projects improved |
Project Outcome | |
---|---|
Description of Outcome | A well-designed investment project developed |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Financial, economic, technical, governance, safeguards, and procurement due diligence of the ensuing project completed |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Assam |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | The project's executing agency, ADB and consultants will conduct meaningful stakeholder consultations during the project design and preparatory stage. If needed, Stakeholder Communication Plan will be prepared |
During Project Implementation | The executing agency will continue involve local community and key stakeholders in project implementation through regular participatory consultations. |
Business Opportunities | |
---|---|
Consulting Services | The TA will require a total of 15 person-months of consulting services to help with project preparation. Individual consultants will be recruited to support the executing agency and ADB in conducting due diligence on financial management, financial and economic analysis, and safeguards (environment, involuntary resettlement, and indigenous peoples), as well as assisting AEGCL, the executing agency of the ensuing project, with contracting strategy and bid documents preparation. ADB intends to hire consultants at the earliest, and conduct another mission to finalize the project concept, followed by further due diligence. Four international and two national consultants will be recruited. ADB will engage the consultants on an individual basis in accordance with its Guidelines on the Use of Consultants (2013, as amended from time to time). The TA proceeds will be disbursed following ADB's Technical Assistance Disbursement Handbook (2010 as amended from time to time). The consultants will prepare inception, draft final, and final reports. Outline terms of reference are given in Attachment 2. Lump-sum contracts may be considered for consulting services under the TA. The consultants will be housed in AEGCL's office. |
Procurement | None |
Responsible ADB Officer | Yusupov, Aziz A. |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Energy Division, SARD |
Executing Agencies |
Asian Development Bank |
Timetable | |
---|---|
Concept Clearance | 15 Nov 2016 |
Fact Finding | - |
MRM | - |
Approval | 24 Nov 2016 |
Last Review Mission | - |
Last PDS Update | 01 Apr 2019 |
TA 9240-IND
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
24 Nov 2016 | - | 24 Nov 2016 | 31 Dec 2017 | 31 Dec 2018 | 05 Jun 2019 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
225,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 225,000.00 | 23 Nov 2023 | 92,983.48 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Assam Power Transmission Improvement Project: Technical Assistance Completion Report | TA Completion Reports | Nov 2023 |
Assam Power Transmission Improvement Project: Project Data Sheet (हिन्दी) | Translated PDS | Mar 2017 |
Assam Power Transmission Improvement Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Nov 2016 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.