Project Name | Third Rural Water Supply and Sanitation Services Sector Development Program | ||||||||||||||||||||
Project Number | 50101-002 | ||||||||||||||||||||
Country | Cambodia |
||||||||||||||||||||
Project Status | Active | ||||||||||||||||||||
Project Type / Modality of Assistance | Grant Loan |
||||||||||||||||||||
Source of Funding / Amount |
|
||||||||||||||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||||||||||||||
Drivers of Change | Gender Equity and Mainstreaming Partnerships Private sector development |
||||||||||||||||||||
Sector / Subsector | Water and other urban infrastructure and services / Urban policy, institutional and capacity development - Urban sanitation - Urban water supply |
||||||||||||||||||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||||||||||||||||||
Description | |||||||||||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||||||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | Targets are likely to be achieved. Despite delays in the project start up, water supply and sanitation facilities for 153 villages (Batch 1) are completed. Batch 2 subprojects (about 180 villages) are expected to start in June 2021. |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | The implementation of water quality testing procedures by PDRDs and district administrations are expected to start in 2021. Batch 1 subproject which include construction of water supply facilities to provide safe rural water supply is ongoing. Batch 1 subprojects started in June 2020, majority of Batch 1 facilities are completed. The sanitation facilities are expected to be completed by February 2021. The construction of Batch 2 subprojects are expected to start in June 2021. Water supply facilities in primary schools are being rehabilitated or constructed. Batch 1 facilities are to be completed in February 2021. The construction of Batch 2 facilities expected to start in June 2021. Water supply facilities in health centers are being rehabilitated or constructed. Batch 1 facilities are to be completed in February 2021. The construction of Batch 2 facilities expected to start in June 2021. 833 WSUGs in Batch 1 subprojects have been established. Standard procedure for septage management in rural areas is expected to be by mid 2021. Improved household latrines are being built. Batch 1 is expected for completion by February 2021. The construction of Batch 2 facilities are expected to start by June 2021. Primary schools are being provided with separate toilets in adequate numbers for males and females. Batch 1 is expected for completion by February 2021. Batch 2 will start by June 2021. Health centers are being provided with separate toilets in adequate numbers for males and females. Batch 1 is expected for completion by February 2021. Batch 2 will start by June 2021. Awareness program (Sanitation and Health Behavior Change) is being implemented. The transfer of personnel from MRD DRDOs and delegation of DRDO functions to the district administrations is expected to start in 2021. MRD regulation on the principles of responsibility, accountability, and transparency for private sector involvement in RWSS services is expected to be issued in 2021. National and subnational staff (at least 40% women) participated in technical, financial, management, and leadership training is expected to start in 2021. Target provinces produce an annual water quality monitoring report based on the rural drinking water quality standard is expected to start in 2021. RWSS safety plans incorporating CCA and DRM principles completed in at least 11 districts is to be implemented for Batches 2,3 and 4 (starting 2021). |
Geographical Location | Banteay Meanchey, Battambang, Kampong Chhnang, Kampong Speu, Kampong Thom, Kampot, Pursat, Siem Reap |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | C |
Indigenous Peoples | B |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | No significant adverse impacts have been identified. |
Involuntary Resettlement | No land acquisition is required so far. |
Indigenous Peoples | So far, the project has no impact on IPs. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | A stakeholder communication strategy was prepared to provide guidance during project implementation. |
During Project Implementation | Stakeholder consultations are conducted in line with the stakeholder communication strategy, which are recorded in the feasibility study for each commune (batches of subprojects). |
Responsible ADB Officer | Hasanah, Siti |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Urban Development and Water Division, SERD |
Executing Agencies |
Ministry of Rural Development [email protected] 169 Corner Road Soviet Blvd. Phnom Penh Cambodia |
Timetable | |
---|---|
Concept Clearance | 07 Oct 2016 |
Fact Finding | 06 Feb 2019 to 19 Feb 2019 |
MRM | 07 Aug 2019 |
Approval | 30 Sep 2019 |
Last Review Mission | - |
Last PDS Update | 22 Jan 2021 |
Grant 0670-CAM
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2019 | 30 Oct 2019 | 06 Dec 2019 | 30 Jun 2024 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 8.78 | Cumulative Contract Awards | |||
ADB | 8.78 | 30 Sep 2019 | 2.07 | 0.00 | 47% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 30 Sep 2019 | 1.07 | 0.00 | 24% |
Grant 0671-CAM
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2019 | 30 Oct 2019 | 06 Dec 2019 | 30 Jun 2024 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 2.00 | Cumulative Contract Awards | |||
ADB | 0.00 | 30 Sep 2019 | 0.00 | 0.00 | 0% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 2.00 | 30 Sep 2019 | 0.00 | 0.00 | 0% |
Loan 3832-CAM
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2019 | 30 Oct 2019 | 06 Dec 2019 | 31 Mar 2022 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 15.00 | Cumulative Contract Awards | |||
ADB | 15.00 | 30 Sep 2019 | 5.00 | 0.00 | 33% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 30 Sep 2019 | 5.00 | 0.00 | 33% |
Loan 3833-CAM
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
30 Sep 2019 | 30 Oct 2019 | 06 Dec 2019 | 30 Jun 2024 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 32.48 | Cumulative Contract Awards | |||
ADB | 29.61 | 30 Sep 2019 | 10.76 | 0.00 | 36% |
Counterpart | 2.87 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 30 Sep 2019 | 7.21 | 0.00 | 24% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Third Rural Water Supply and Sanitation Services Sector Development Program: Community Participation Framework | Resettlement Frameworks | Aug 2019 |
Third Rural Water Supply and Sanitation Services Sector Development Program: Indigenous Peoples Planning Framework | Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks | Jul 2019 |
Third Rural Water Supply and Sanitation Services Sector Development Program: Social Safeguard Due Diligence Report | Safeguards Due Diligence Reports | Jul 2019 |
Third Rural Water Supply and Sanitation Services Sector Development Program: Environmental Assessment and Review Framework | Environmental Assessment and Review Framework | Jun 2019 |
Third Rural Water Supply and Sanitation Services Sector Development Program:Initial Environmental Examination | Initial Environmental Examination | Jun 2019 |
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
ADB to Help Cambodia Expand Access to Water Supply, Sanitation Services
ADB has approved $49 million in financing to help the Government of Cambodia achieve its 2025 goal of providing universal access to improved water supply and sanitation services in the country’s rural areas.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Project Implementation Consultant | Firm - Consulting | Closed | 21 Feb 2019 | 22 Mar 2019 |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
CONSTRUCTION AND TRANSPORT OF RAIN WATER JARS IN 8 PROVINCES - 4 LOTS | Loan 3833 | 17 Jul 2020 | UNG KIM HENG CONSTRUCTION CO. LTD. | PHNOM PENH CAMBODIA | Ministry of Rural Development | CONSTRUCTION | 2,735,265.50 | 2,735,265.50 |
CONSTRUCTION OF NEW DRILLING WELLS, REHABILITATION OF DRILL WELLS AND HAND DUG WELLS IN 8 PROVINCES | Loan 3833 | 17 Jul 2020 | HOUT CHHOEUN CONSTRUCTION CO. LTD. | PHNOM PENH CAMBODIA | Ministry of Rural Development | CONSTRUCTION | 3,318,184.00 | 3,318,184.00 |
PROJECT IMPLEMENTATION SUPPORT CONSULTANTS | Loan 3833 | 26 Mar 2020 | VARIOUS | VARIOUS INDONESIA | Ministry of Rural Development | CONSULTANCY | 3,204,398.00 | 3,204,398.00 |
Procurement Plan
None currently available.