Bangladesh : Khulna 800 MW LNG Based Power Plant Project
In March 2016, the Government of Bangladesh requested the Asian Development Bank (ADB) for a loan to fund the Khulna 800 MW LNG Based Power Plant Project. Subsequently, in July 2016, the government requested ADB to provide a small-scale project preparatory technical assistance (TA) in an amount not exceeding $225,000 to help preparing the project. The TA will support the due diligence and preparatory work for the ensuing project. TA is not included in country operations business plan, 2016-2018 for Bangladesh. A fact-finding mission was not fielded as sufficient information had been gathered during previous consultation missions to proceed with TA processing.
Project Details
-
Project Officer
Yusupov, Aziz A.
South Asia Department
Request for information -
Country/Economy
Bangladesh -
Modality
-
Sector
- Energy
Related Projects
Project Name | Khulna 800 MW LNG Based Power Plant Project | ||||||||
Project Number | 50161-004 | ||||||||
Country / Economy | Bangladesh |
||||||||
Project Status | Closed | ||||||||
Project Type / Modality of Assistance | Technical Assistance |
||||||||
Source of Funding / Amount |
|
||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth Regional integration |
||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||||||
Sector / Subsector | Energy / Conventional energy generation - Electricity transmission and distribution - Oil and gas transmission and distribution |
||||||||
Gender | Some gender elements | ||||||||
Description | In March 2016, the Government of Bangladesh requested the Asian Development Bank (ADB) for a loan to fund the Khulna 800 MW LNG Based Power Plant Project. Subsequently, in July 2016, the government requested ADB to provide a small-scale project preparatory technical assistance (TA) in an amount not exceeding $225,000 to help preparing the project. The TA will support the due diligence and preparatory work for the ensuing project. TA is not included in country operations business plan, 2016-2018 for Bangladesh. A fact-finding mission was not fielded as sufficient information had been gathered during previous consultation missions to proceed with TA processing. | ||||||||
Project Rationale and Linkage to Country/Regional Strategy | The impact of the TA will be improved readiness in implementing clean energy projects. The outcome of the TA will be a well-designed investment project developed. | ||||||||
Impact | Readiness in implementing clean energy projects improved |
Project Outcome | |
---|---|
Description of Outcome | A well-designed investment project developed |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Procurement, environment, social safeguard, financial and economic due diligence reviews of components of the ensuing project completed |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Khulna |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | A series of consultations with key stakeholder groups and communities have been conducted during project preparation, and communities' inputs have been incorporated into the project design. |
During Project Implementation | Consultation with stakeholders and communities will be continued throughout implementation of the project. |
Business Opportunities | |
---|---|
Consulting Services | Consultants envisaged under the TA to help the executing agencies and ADB in conducting due diligence on financial management, financial and economic analysis, and safeguards (environment, involuntary resettlement, and indigenous peoples) as well as assessment of the procurement capacity of the executing agencies have been engaged and fielded. Implementation is ongoing and on track. |
Procurement | No procurement is envisaged under this S-PPTA. |
Responsible ADB Officer | Yusupov, Aziz A. |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Energy Division, SARD |
Executing Agencies |
Asian Development Bank |
Timetable | |
---|---|
Concept Clearance | 31 Oct 2016 |
Fact Finding | - |
MRM | - |
Approval | 01 Sep 2016 |
Last Review Mission | - |
Last PDS Update | 19 Mar 2018 |
TA 9164-BAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
01 Sep 2016 | - | 01 Sep 2016 | 31 Aug 2017 | 30 Aug 2018 | 13 Nov 2018 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
425,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 425,000.00 | 17 Jun 2022 | 370,182.68 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Khulna 800 MW LNG Based Power Plant Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Nov 2016 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Communications Specialist (National) | Individual - Consulting | Closed | ||
Communications Specialist (International) | Individual - Consulting | Closed | ||
International Gas Industry Specialist | Individual - Consulting | Closed | ||
National Gas Industry Specialist | Individual - Consulting | Closed | ||
International Power Systems Engineer | Individual - Consulting | Closed |