Kazakhstan : Fostering the Development of Renewable Energy
The proposed TA aims to assist the government to achieve its targets. The TA will: (i) train KEGOC's transmission system planning and operation staff on modern system planning tools; (ii) improve KEGOC's system planning tools improved; and (iii) prepare a list of transmission grid reinforcement projects necessary to integrate electricity generated from renewable energy sources.
Project Details
-
Project Officer
Mtchedlishvili, Levan G.
Central and West Asia Department
Request for information -
Country/Economy
Kazakhstan -
Modality
-
Sector
- Energy
Project Name | Fostering the Development of Renewable Energy | ||||
Project Number | 50318-001 | ||||
Country / Economy | Kazakhstan |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||
Sector / Subsector | Energy / Electricity transmission and distribution - Renewable energy generation - solar - Renewable energy generation - wind |
||||
Gender | No gender elements | ||||
Description | The proposed TA aims to assist the government to achieve its targets. The TA will: (i) train KEGOC's transmission system planning and operation staff on modern system planning tools; (ii) improve KEGOC's system planning tools improved; and (iii) prepare a list of transmission grid reinforcement projects necessary to integrate electricity generated from renewable energy sources. |
||||
Project Rationale and Linkage to Country/Regional Strategy | The Kazakhstan Electricity Grid Operating Company (KEGOC), a state owned electricity transmission and dispatch joint stock company, has been successfully managing high voltage grid of Kazakhstan (approximately 25 thousand kilometers) since the Soviet times. Its staff has gathered vast experience in operation, planning and maintenance of the network supplied from conventional energy generation sources (coal, gas and hydro) and has been adequately equipped to undertake static and dynamic stability analysis of integration of such type of generation sources. KEGOC does not possess sufficient technical capacity and tools to analyze the impact of integration of variable energy generation sources to the grid. As a result, the applications from public and private sector developers on construction of new wind and solar power plants are deferred until their impact on the power system is analyzed and adequate grid reinforcement measures are undertaken. The conceptualization of the TA is a result of consultations with the Ministry of Energy, state power generation company Samruk Energy and state transmission and dispatch company KEGOC. Each entity indicated on the lack of capacity related to integration of the renewable energy and clearly observed how TA outputs could benefit their business processes and Kazakhstan in general. |
||||
Impact | Electricity supply from renewable energy sources in Kazakhstan increased to 3% by 2020. |
Project Outcome | |
---|---|
Description of Outcome | Transmission system operator's capacity for planning and modeling of the integration of variable power generation sources into the Kazakh power system established. |
Progress Toward Outcome | To be assessed. TA implementation/activities are ongoing.The consultants have completed and submitted reports on (i) transforming the System Model into the format of PowerFactory and on Installation of Additional Services considering the special features of the Kazakhstan energy system; (ii) study for transmission planning in lieu of renewables' integration into the energy system of Kazakhstan; (iii) 1st draft final report on the main conclusions including the list of the transmission reinforcement projects. |
Implementation Progress | |
Description of Project Outputs | KEGOC's transmission system planning and operation staff trained on modern system planning tools KEGOC's system planning tools improved A list of transmission grid reinforcement projects necessary to integrate electricity generated from renewable energy sources prepared. |
Status of Implementation Progress (Outputs, Activities, and Issues) | Two formal and extensive on-the-job trainings on the PowerFactory software for power system studies and transmission planning were conducted for 22 KEGOC staff using practical system model. The trainings focused on (i) PowerFactory basic training; (ii) modeling of renewables integration; (iii) transfer capability calculation and the model used for perspective planning; (iv) short circuit calculation and protection coordination; (v) power quality planning with PowerFactory; (vi) RMS transients simulation and dynamic stability; and (vii) frequency stability calculation. To be assessed. To be determined. TA completion has been extended to 31 December 2018 to allow completion of all remaining project activities and deliverables. |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation | The data collection has been completed while the interpretation and calculation of the data collected have recently commenced. |
Business Opportunities | |
---|---|
Consulting Services | ADB will recruit a firm of international consultants to undertake this task. A consulting firm will be recruited using the quality- and cost-based selection (QCBS) method, following ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). Quality cost weighting of 90:10 will be used to ensure quality of the complex system analysis. The task will require 23 person-months of international consultant time during the 12 months implementation period. Out of the TA amount $450,000 will be allocated as provisional sums for the procurement of the transmission system planning software and associated licenses for DIgSILENT. |
Procurement | TBC |
Responsible ADB Officer | Mtchedlishvili, Levan G. |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Energy Division, CWRD |
Executing Agencies |
Kazakhstan Electricity Grid Operating Company (KEGOC) |
Timetable | |
---|---|
Concept Clearance | 27 Oct 2016 |
Fact Finding | - |
MRM | - |
Approval | 06 Mar 2017 |
Last Review Mission | - |
Last PDS Update | 28 Sep 2018 |
TA 9301-KAZ
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
06 Mar 2017 | 15 Mar 2017 | 15 Mar 2017 | 28 Feb 2018 | 30 Jun 2019 | 03 Dec 2019 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
0.00 | 1,000,000.00 | 0.00 | 400,000.00 | 0.00 | 0.00 | 1,400,000.00 | 17 Jun 2022 | 970,512.00 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Fostering the Development of Renewable Energy: Technical Assistance Completion Report | TA Completion Reports | Jul 2020 |
Fostering the Development of Renewable Energy: Technical Assistance Report | Technical Assistance Reports | Mar 2017 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Capacity Development | Technical Assistance 9301 | 24 Mar 2017 | Digsilent GmbH (Germany) in Association with Juru Energy Limited (United Kingdom) | Heinrich-Hertz Str. 9 Gomaringen, Baden- Rg 72810 Germany | Kazakhstan Electricity Grid Operating Company | 976,300.00 | — |