The TA will require total of 15 person-months of consulting services to help with project preparation. Individual consultants will be recruited to: (a) conduct a study on technical and regulatory aspects, and economic and financial implications of the solar rooftop power generation initiative, including lessons learnt from other countries on implementing solar rooftop projects; and (b) support the executing agency and ADB in conducting due diligence on technical, regulatory, financial management, financial and economic analyses, and relevant safeguards (mainly environment since solar rooftop installations will not have any involuntary resettlement and indigenous peoples impacts), as well as assisting executing and implementing agencies of the ensuing project with contracting strategy.
Project Name | Solar Rooftop Power Generation Project | ||||
Project Number | 50373-001 | ||||
Country | Sri Lanka |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development |
||||
Sector / Subsector | Energy / Renewable energy generation - solar |
||||
Gender Equity and Mainstreaming | No gender elements | ||||
Description | The TA will require total of 15 person-months of consulting services to help with project preparation. Individual consultants will be recruited to: (a) conduct a study on technical and regulatory aspects, and economic and financial implications of the solar rooftop power generation initiative, including lessons learnt from other countries on implementing solar rooftop projects; and (b) support the executing agency and ADB in conducting due diligence on technical, regulatory, financial management, financial and economic analyses, and relevant safeguards (mainly environment since solar rooftop installations will not have any involuntary resettlement and indigenous peoples impacts), as well as assisting executing and implementing agencies of the ensuing project with contracting strategy. | ||||
Project Rationale and Linkage to Country/Regional Strategy | Sri Lanka has improved its energy sector performance and achieved a national electrification ratio of 98% in 2014 compared with 29% in 1990. However, high dependence on expensive fossil fuel energy continues. Sector challenges include meeting growing demand for electricity at a low cost and acceptable reliability, and attaining long-term sustainability. The increase in the share of thermal oil-fired energy in power generation, from 6% in 1995 to 35% in 2014, creates a high cost base and is not a viable and sustainable solution for energy security and environment protection in the long term. Diversification of the generation mix primarily to renewable energy sources, improved network efficiency, reduced technical losses, and supply- and demand-side management are required. The Government of Sri Lanka aims to ensure sustainable development of energy resources by improving the power supply systems to provide access to electricity services to the entire population. Sri Lanka has a national investment program, including sector investments that are based on the National Energy Policy and Strategies. The National Energy Policy and Strategies includes a sector road map, a long-term investment plan, and policy and reform measures. The government objectives includes, among others, toe increase the share of energy supply from nonconventional renewable energy sources to 20% by 2020. The 20% increase in power generation from nonconventional renewable energy sources will add to 29% (2014) of conventional hydropower generation and will ensure that in the future a substantial portion of electricity is produced by clean energy sources. In September 2016, the government announced _The Battle for Solar Energy_ program. The program envisages boosting clean power generation through the use of net metering (or net accounting, or micro solar power producer) schemes to connect solar rooftop photovoltaic (PV) installations to the network. Under _the Battle for Solar Energy_ program the government plans to increase solar PV capacity to 200 MW of by 2020 and 1000 MW by 2025. |
||||
Impact | Readiness in implementing clean solar rooftop power generation projects |
Project Outcome | |
---|---|
Description of Outcome | A well-designed investment project developed |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Financial and economic, technical, governance, safeguards and procurement due diligence of the ensuing project completed |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Colombo |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Extensive consultations with the government and stakeholders, including local communities, local authorities and civil society groups, will be undertaken to ensure participatory approach. The stakeholders will be consulted throughout the design stage during the project preparatory technical assistance and the ensuing project implementation on the relevant issues, including environmental, social and other issues that may affect communities and poor people. |
During Project Implementation | The consultation process with the stakeholders will continue during project implementation as per Sri Lankan regulations. |
Business Opportunities | |
---|---|
Consulting Services | Consultants envisaged under the TA had been engaged and fielded. Implementation is ongoing. |
Procurement | Not applicable |
Responsible ADB Officer | Kolantharaj, Jaimes |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Energy Division, SARD |
Timetable | |
---|---|
Concept Clearance | 19 Jan 2017 |
Fact Finding | - |
MRM | - |
Approval | 14 Dec 2016 |
Last Review Mission | - |
Last PDS Update | 25 Sep 2017 |
TA 9278-SRI
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
14 Dec 2016 | - | 14 Dec 2016 | 31 Dec 2017 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
225,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 225,000.00 | 14 Dec 2016 | 206,887.63 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Solar Rooftop Power Generation Project: Project Data Sheet (Tamil Translation) | Translated PDS | Mar 2017 |
Solar Rooftop Power Generation Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Dec 2016 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.