Papua New Guinea: Health Services Sector Development Program, Subprogram 1

Sovereign (Public) Project | 51035-001 Status: Active

The Health Services Sector Development Program (HSSDP) will help Papua New Guinea (PNG) strengthen health services through policy reforms and direct investments in health systems. A diagnostic assessment of the coverage, financing, and quality of health services is required to ensure that the interventions are designed for maximum impact.

 
Project Name Health Services Sector Development Program, Subprogram 1
Project Number 51035-001
Country Papua New Guinea
Project Status Active
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Loan 3664-PNG: Health Services Sector Development Program
Ordinary capital resources US$ 100.00 million
Loan 3665-PNG: Health Services Sector Development Program
Ordinary capital resources US$ 45.10 million
Loan 3666-PNG: Health Services Sector Development Program
concessional ordinary capital resources lending / Asian Development Fund US$ 49.90 million
Grant 0648-PNG: Health Services Sector Development Program, Subprogram 1 (Additional Financing)
Government of Australia US$ 38.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Partnerships
Sector / Subsector

Health / Health sector development and reform

Public sector management / Public expenditure and fiscal management

Gender Equity and Mainstreaming Effective gender mainstreaming
Description The Health Services Sector Development Program (HSSDP) will help Papua New Guinea (PNG) strengthen health services through policy reforms and direct investments in health systems. A diagnostic assessment of the coverage, financing, and quality of health services is required to ensure that the interventions are designed for maximum impact.
Project Rationale and Linkage to Country/Regional Strategy The HSSDP will contribute to the achievement of the National Health Plan (NHP) (2011 to 2020) and the Development Strategic Plan (2010 to 2030). In particular, the HSSDP aims to improve national public expenditure management and strengthen health systems. The HSSDP builds upon ADB's long-term in-country engagement in both the health sector and public finance management (PFM).
Impact Affordable, accessible, equitable, and high-quality health services for all citizens developed (National Health Plan 2011 to 2020).
Project Outcome
Description of Outcome A more sustainable and efficient healthcare system achieved
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

National frameworks and PFM enhanced

Subnational health system management strengthened

Health service delivery components strengthened

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects

An environmental assessment and review framework for the sector

Project will be developed and at least one environmental assessment of a subproject identified during preparation. The framework will comply with the Safeguard Policy Statement (SPS) 2009, as well as national laws and requirements relating to environmental assessment, to facilitate compliance with environmental requirements during project implementation.

Involuntary Resettlement The project will have minimal or no adverse social impacts.
Indigenous Peoples The project will have minimal or no adverse social impacts.
Stakeholder Communication, Participation, and Consultation
During Project Design

Stakeholder and beneficiary consultations will be initiated during TRTA, which will lead to stakeholder engagement

and participation plan(s).

During Project Implementation A program and reform steering committee will bring together key stakeholders from government institutions and development partners. Project component designs and individual policy reforms are based on or will incorporate feedback from consultations with identified stakeholder groups, led by the responsible implementing agencies. Participatory capacity, human resource development, and training needs assessments will be conducted at the institutional level.
Business Opportunities
Consulting Services All consultants will be recruited according to ADB's Guidelines on the Use of Consultants.
Procurement Any procurement of equipment or consulting services will conform with ADB's Procurement Guidelines.
Responsible ADB Officer Mikkelsen-Lopez, Inez
Responsible ADB Department Pacific Department
Responsible ADB Division PASP
Executing Agencies
Department of Treasury
6/F The Treasury Building, Lamana Road
P.O Box 542, Waigani Drive, NCD
Papua New Guinea
Timetable
Concept Clearance 31 May 2017
Fact Finding 05 Dec 2017 to 13 Dec 2017
MRM 02 Mar 2018
Approval 31 May 2018
Last Review Mission -
Last PDS Update 28 Sep 2018

Grant 0648-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
14 Jun 2019 21 Jun 2019 12 Aug 2019 30 Sep 2025 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 38.00 Cumulative Contract Awards
ADB 0.00 14 Jun 2019 0.00 7.08 19%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 38.00 14 Jun 2019 0.00 0.89 2%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Loan 3664-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
31 May 2018 13 Jun 2018 18 Jul 2018 30 Oct 2018 - 03 Apr 2019
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 100.00 Cumulative Contract Awards
ADB 100.00 31 May 2018 100.00 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 31 May 2018 100.00 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Loan 3665-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
31 May 2018 13 Jun 2018 18 Jul 2018 30 Nov 2025 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 54.60 Cumulative Contract Awards
ADB 45.10 31 May 2018 15.15 0.00 34%
Counterpart 9.50 Cumulative Disbursements
Cofinancing 0.00 31 May 2018 2.64 0.00 6%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Loan 3666-PNG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
31 May 2018 13 Jun 2018 18 Jul 2018 30 Nov 2025 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 49.90 Cumulative Contract Awards
ADB 49.90 31 May 2018 4.43 0.00 9%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 31 May 2018 1.11 0.00 2%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

Title Document Type Document Date
ADBヘルス・ボンド2019 Brochures and Flyers Aug 2019
ADB Health Bond Brief 2019 Brochures and Flyers Aug 2019

The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Public Finance Management Specialist Individual - Consulting Closed 07 Oct 2019 20 Oct 2019
Clinical and Public Health Service Planning Specialist Individual - Consulting Closed 15 Aug 2019 28 Aug 2019
Implementation of PHASE 2 of the PNG electronic National Health Information System Firm - Consulting Closed 01 Jul 2019 30 Jul 2019
Public Finance Management Specialist Individual - Consulting Closed 30 Jun 2019 13 Jul 2019
HEALTH SYSTEMS INFORMATION SPECIALIST Individual - Consulting Closed 03 Jun 2019 16 Jun 2019
Performance Monitoring and Evaluation Firm - Consulting Closed 13 May 2019 11 Jun 2019
Strengthening Medical Supplies Procurement and Supply Chain Management Firm - Consulting Closed 20 Mar 2019 11 Apr 2019
Health Economist Individual - Consulting Closed 13 Mar 2019 26 Mar 2019
Environment Specialist Individual - Consulting Closed 05 Mar 2019 18 Mar 2019
Medical Supplies Procurement & Supply Chain Specialist Individual - Consulting Closed 05 Mar 2019 18 Mar 2019
Service Planning & Partnership Specialist Individual - Consulting Closed 19 Oct 2018 01 Nov 2018
Social Safeguards, Health Promotion & Gender Specialist Individual - Consulting Closed 19 Oct 2018 01 Nov 2018
Architect Individual - Consulting Closed 19 Oct 2018 01 Nov 2018
CLINICAL GOVERNANCE AND STANDARDS SPECIALIST Individual - Consulting Closed 19 Oct 2018 01 Nov 2018

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
IMPLEMENTATION OF PHASE 2 OF THE PNG ELEC TRONIC NATIONAL HEALTH INFORMATION SYSTEM Loan 3665 25 Mar 2020 PNG REMOTE SENSING CENTER LTD. PORT MPORESBY PAPUA NEW GUINEA Department of Treasury CONSULTANCY 4,848,097.10 4,848,097.10
CONSTRUCTION AND COMPLETION OF HEALTH CETRE - STAGE IV AT KOPIAGO IN LAKE KOPIAGO-KOROBA Grant 0648 21 Jan 2020 LAPWING CONSTRUCTIONS LTD. SECT 453 LOT 36 HOHOLA PO BOX 8864 BOROKO NCD PAPUA NEW GUINEA Department of Treasury 1,314,142.47
CONSTRUCTION AND COMPLETION OF HEALTH CENTER - STAGE II - KOPIAGO IN LAKE KOPIAGO-KOROBA DISTRICT Grant 0648 21 Jan 2020 LAPWING CONSTRUCTIONS LTD. SECT 453 LOT 36 HOHOLA PO BOX 8864 BOROKO NCD PAPUA NEW GUINEA Department of Treasury 1,421,443.07
CONSTRUCTIONOF KOPIAGO HEALTH CETRE -STAGE III IN LAKE KOPIAGO-KOROBA DISTRICT Grant 0648 21 Jan 2020 LAPWING CONSTRUCTIONS LTD. SECT 453 LOT 36 HOHOLA PO BOX 8864 BOROKO NCD PAPUA NEW GUINEA Department of Treasury 1,437,199.05
PRANITA SHARMA - PUBLIC FINANCIAL MANAGEMENT Grant 0648 13 Dec 2019 PRANITA SHARMA 77 HASELMERE CIRCUS ROCKINGHAM PERTH WESTERN AUSTRALIA 6168 AUSTRALIA Department of Treasury 615,214.50
STRENGTHENING MEDICAL SUPPLIES PROCUREMENT AND SUPPLY CHAIN MANAGEMENT Loan 3665 14 Nov 2019 AGILITY LTD., PAPUA NEW GUINEA PORTION 2508C OF GRANVILLE, NAPA NAPA RD PORT MORESBY NCD 121 PAPUA NEW GUINEA Department of Treasury CONSULTANCY 1,866,877.10 1,866,877.10
PEMRAJ GONSALKORALE, MEDICAL SUPPLIES PROCUREMENT AND SUPPLY CHAIN SPECIALIST Loan 3665 02 Sep 2019 PEMRAJ GONSALKORALE 3304/1 ALEXANDRA DRIVE CAMPERDOWN, NSW 2050 AUSTRALIA Department of Treasury CONSULTANCY 153,242.99 153,242.99
MR. KENNEDY KALMET - ARCHITECTURE DRAFTING Loan 3665 02 Sep 2019 KENNEDY KALMET FIG ST. HOHOLA STAGE 2 PORT MORESBY NORTH-WEST NCD PAPUA NEW GUINEA Department of Treasury CONSULTANCY 146,941.18 146,941.18
MISPAH MURO - CONSTRUCTION SUPERVISOR (NATIONAL) Loan 3665 16 Aug 2019 MISPAH MURO PORT MORESBY, NCD PAPUA NEW GUINEA Department of Treasury CONSULTANCY 147,058.56 146,808.88
MARC LEWARCA CONSTRUCTION SUPERVISOR (NATIONAL) Loan 3665 16 Aug 2019 MARC LEWARAKA PORT MORESBY, NCD PAPUA NEW GUINEA Department of Treasury CONSULTANCY 147,058.56 146,808.88
RONALD EDWARD HICKEY, HEALTH SYSTEMS INFORMATION SPECIALIST Loan 3665 15 Aug 2019 RONALD EDWARD HICKEY 39 PROMENADE AVENUE ROBINA GOLD COAST, QUEENSLAND AUSTRALIA Department of Treasury CONSULTANCY 393,476.00 393,268.78
PETER BARAN - HEALTH SECTOR ORGANIZATION AND PEOPLE DEVELOPMENT Grant 0648 01 Aug 2019 PETER BARAN 18 ARMFIELD PLACE CHISHOLM ACT 2905 AUSTRALIA Department of Treasury CONSULTANCY 1,016,883.96
JIM KIRE DOPO - ENVIRONMENT SPECIALIST-NATIONAL Loan 3665 29 May 2019 JIM KIRE DOPO BOROKO, NCD PORT MORESBY PAPUA NEW GUINEA Department of Treasury CONSULTANCY 147,602.24 147,552.32
KELWYN CRAIG BROWNE - HEALTH PROMOTION, SOCIAL SAFEGUARD AND GENDER SPECIALIST 21 JANUARY 2019 TO 31 JULY 2023 Loan 3665 17 Jan 2019 KELWYN CRAIG BROWNE 1181 BOOYONG ROAD, CLUNES NSW 2480 AUSTRALIA Department of Treasury CONSULTANCY 692,257.00 692,257.02
TREVOR RONALD GOWLAND - SERVICE PLANNING AND PARTNERSHIP SPECIALIST (21 JANUARY 2019 TO 30 SEPTEMBER 2023) Loan 3665 17 Jan 2019 TREVOR RONALD GOWLAND 31 WANDOO COURT MULWALA NEW SOUTH WALES AUSTRALIA Department of Treasury CONSULTANCY 493,997.00 493,996.97
PRAGATI BASNET - ARCHITECT (DESIGN, CONSTRUCTION AND CONTRACT MANAGEMENT (3 DECEMBER 2018 TO 30 SEPTEMBER 2023 Loan 3665 16 Jan 2019 PRAGATI BASNET LAGANKHEL-5, LALITPUR KATHMANDU VALLEY NEPAL Department of Treasury CONSULTANCY 1,111,439.00 1,111,438.77
VICKIASSENHEIM - CLINICAL GOVERNANCE AND STANDARDS SPECIALIST 3 DECEMBER 2018 TO 30 SEPTEMBER 2023 Loan 3665 16 Jan 2019 VICKI ASSENHEIM 1/69 CHERMSIDE ST., TENERIFFE QLD AUSTRALIA AUSTRALIA Department of Treasury CONSULTANCY 1,089,422.00 1,089,449.64
PROJECT MANAGER Loan 3665 05 Nov 2018 ROBERT CHARLES AKERS 2 MACADAMIA COURT BUSHLAND BEACH QUEENSLAND AUSTRALIA Department of Treasury Consulting Services 1,441,554.00 1,440,298.00
PROCUREMENT AND FINANCE SPECIALIST Loan 3665 05 Nov 2018 NANDA MAHARJAN LAGANKHEL -5, LALITPUR KATHMANDU VALLEY NEPAL Department of Treasury Consulting Services 1,413,318.00 1,411,735.00

Procurement Plan