Indonesia: Sustainable Energy Access in Eastern Indonesia — Electricity Grid Development Program (Phase 2)

Sovereign Project | 51114-001

Project Name Sustainable Energy Access in Eastern Indonesia — Electricity Grid Development Program (Phase 2)
Project Number 51114-001
Country / Economy Indonesia
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Grant 0753-INO: Sustainable Energy Access in Eastern Indonesia Electricity Grid Development Program Phase 2
Asian Clean Energy Fund under the Clean Energy Financing Partnership Facility US$ 3.00 million
Grant 9215-INO: Sustainable Energy Access in Eastern Indonesia Electricity Grid Development Program Phase 2
Japan Fund for Prosperous and Resilient Asia and the Pacific US$ 3.00 million
Loan 4009-INO: Sustainable Energy Access in Eastern Indonesia Electricity Grid Development Program Phase 2
Ordinary capital resources US$ 600.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Partnerships
Private sector development
Sector / Subsector

Energy / Electricity transmission and distribution

Gender Equity and Mainstreaming Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

The quality of life in Indonesian society is enhanced through the use of electricity (Electricity Power Supply Business Plan, 20192028)

Project Outcome
Description of Outcome

Sustainable, equitable, and reliable access to electricity for the population in Kalimantan, Maluku, and Papua enhanced.

Progress Toward Outcome

1. Number of PLN customers: 6.39 million against ADB 2021 and 2022 targets of 6.12 million and 6.38 millions respectively

2. Additional poor households provided with PLN electricity increased: 67,390 poor households against ADB 2021 and 2022 targets of 51,808 and 73,368 households respectively; 12,912 female-headed households against ADB 2024 target of 11,243 households

3. Reliability of electricity supply improved: 1.94/100 ckm below ADB 2022 thresholds of 15.59/100 ckm

4. Improved time use reported by women and men as a result of electricity access: . PLN is preparing procurement of the national survey firm to conduct baseline survey and data gathering in April 2023 . End line study will be initiated with data collection in 2024 and final report in 2025.

Implementation Progress
Description of Project Outputs

Power distribution network strengthened and expanded

Renewable energy use increased

Institutional capacity strengthened and social monitoring enhanced.

Status of Implementation Progress (Outputs, Activities, and Issues)

Output 1: 56,652 ckm (cumulative) against ADB 2021 target of 56,685 ckm and 2022 target of 58,792 ckm

Output 2 (i) 1,302.1 MWh, below 2018 baseline of 3,309 MWh. PLN plans to meet DLI 5 targets significantly in 2025 through PLTS revitalization, PLTS de dieselization and PLTS upgrades. Budget request and procurement process are ongoing for the above programs and (ii) PLN will conduct procurements for international consultants and EPC service for PLTS upgrades. Outcome from 10 PLTS upgrades that will be conducted in 2024 on remote monitoring and hybridization using EMS will be incorporated by international consultants in the training module in early 2025.

Output 3:

a. Asset and waste management

2020(i) target: inventory of used equipment for disposal as of 2019 was prepared by all 5 UIWs;

2021(i) and 2022 (i) targets: 3 out of 5 UIWs inventory of used equipment for disposal as of 2019 (51.38%) was approved by PLN Board of Commissioners in January and April 2022 and PLN is preparing for their disposals;

2020(ii),2021(ii), and 2022 (iii) targets: cumulative 9 out of 10 (2021 target) warehouses have secured environmental documents from the relevant regulatory agency;

b. Consumer education workshop

2020 (ii) 4 out of 5 UIWs have conducted consumer workshop.

2021 target: partially achieved with all 29 UP3s have conducted consumer workshop.

2022 target: 6 out of 29 UP3s have conducted consumer workshop.

c. Integrated eProcurement and system application product/ SAP: 63.89% contracts are recorded in the integrated system against ADB 2021 target of 50% and 2022 target of 60%;

d. The 2021 PLN Sustainability Report has been published on 30 June 2022 and the material for the social impact of electrification has been included in the report.

Geographical Location Nation-wide
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Palupi, Ira
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Indonesia Resident Mission
Executing Agencies
P.T. Perusahaan Listrik Negara
Timetable
Concept Clearance 24 Dec 2018
Fact Finding 11 Feb 2019 to 20 Feb 2019
MRM 16 May 2019
Approval 24 Nov 2020
Last Review Mission -
Last PDS Update 31 Oct 2022

Grant 0753-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
24 Nov 2020 08 Dec 2020 14 Jan 2021 30 Jun 2026 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 3.00 Cumulative Contract Awards
ADB 0.00 20 Jan 2023 0.00 0.00 0%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 3.00 20 Jan 2023 0.00 0.00 0%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Grant 9215-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Nov 2016 25 Nov 2016 25 Nov 2016 31 Dec 2021 31 Mar 2023 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 3.00 Cumulative Contract Awards
ADB 0.00 20 Jan 2023 0.00 0.75 25%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 3.00 20 Jan 2023 0.00 0.75 25%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Loan 4009-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
24 Nov 2020 08 Dec 2020 14 Jan 2021 30 Jun 2026 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 2,269.00 Cumulative Contract Awards
ADB 600.00 20 Jan 2023 275.14 0.00 46%
Counterpart 1,669.00 Cumulative Disbursements
Cofinancing 0.00 20 Jan 2023 275.80 0.00 46%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2): Audited Project Financial Statements (January-December 2021) Audited Project Financial Statements Jul 2022
Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2): Program Implementation Document Project/Program Administration Manual May 2022
Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2): Audited Project Financial Statements (January-December 2020) Audited Project Financial Statements Sep 2021
Amendment to the Loan Agreement for Loan 4009-INO: Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2) Loan Agreement (Ordinary Resources) Jul 2021
Guarantee Agreement (Ordinary Operations) for Loan 4009-INO, Grants 0753-INO and 9215-INO: Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2) Guarantee Agreements Dec 2020
Grant Agreement (Externally Financed) for Grant 0753-INO: Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2) Grant Agreement Dec 2020
Loan Agreement (Ordinary Operations) for Loan 4009-INO: Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2) Loan Agreement (Ordinary Resources) Dec 2020
Grant Agreement (Externally Financed) for Grant 9215-INO: Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program (Phase 2) Grant Agreement Dec 2020
Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program Phase 2: Report and Recommendation of the President Reports and Recommendations of the President Nov 2020
Sustainable Energy Access in Eastern Indonesia - Electricity Grid Development Program Phase 2: Initial Poverty and Social Analysis Initial Poverty and Social Analysis Dec 2018
Sustainable Energy Access in Eastern Indonesia—Electricity Grid Development Program Phase II: Concept Paper Concept Papers Dec 2018

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.


Contracts Awarded

No contracts awarded for this project were found


Procurement Plan

None currently available.