Samoa : Preparing the Central Cross Island Road Upgrading Project
The Government of Samoa requested the Asian Development Bank's (ADB) assistance for Central Cross Island Road Upgrading (the ensuing Project) a priority investment in transport sector. Samoa's land transport depends on key arterial roads that serve the two main islands, Upolu where capital Apia is located, and Savai'i. Upolu is served by three cross-island roads strategically located at the eastern, western, and central sections. The Central Cross Island Road is the key arterial road connecting West Coast Road in Apia with the South Coast Road in Siumu. The project road is 19.70 kilometers (km) that provides access to 8 villages to the capital, Apia. The existing two-lane narrow carriageway (4 meters 5 meters) road with surface seal carrying up to 6,000 average daily traffic (ADT) along first 5 km, and up to 1,500 ADT thereafter, is unsafe for road users and in need of upgrading.
Project Details
-
Project Officer
Ishenaliev, Rustam I.
Pacific Department
Request for information -
Country/Economy
Samoa -
Sector
- Transport
Related Projects
| Project Name | Preparing the Central Cross Island Road Upgrading Project | ||||
| Project Number | 51268-002 | ||||
| Country / Economy | Samoa |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships Private sector development |
||||
| Sector / Subsector | Transport / Road transport (non-urban) |
||||
| Gender | Some gender elements | ||||
| Description | The Government of Samoa requested the Asian Development Bank's (ADB) assistance for Central Cross Island Road Upgrading (the ensuing Project) a priority investment in transport sector. Samoa's land transport depends on key arterial roads that serve the two main islands, Upolu where capital Apia is located, and Savai'i. Upolu is served by three cross-island roads strategically located at the eastern, western, and central sections. The Central Cross Island Road is the key arterial road connecting West Coast Road in Apia with the South Coast Road in Siumu. The project road is 19.70 kilometers (km) that provides access to 8 villages to the capital, Apia. The existing two-lane narrow carriageway (4 meters 5 meters) road with surface seal carrying up to 6,000 average daily traffic (ADT) along first 5 km, and up to 1,500 ADT thereafter, is unsafe for road users and in need of upgrading. The project will also improve institutional capacity of executing and implementing agencies to plan, execute and maintain investment projects and will provide support to the Ministry of Natural Resource and Environment (MNRE) to improve their capacity in updating the current cadastral system. The socioeconomic impacts from upgrading are expected to improve access to public services, particularly increase in rate of tertiary education, faster, and safer access to medical services, and spur economic activity in medium- to long-term through increase in tourism activities. Samoa's economy is based on subsistence level primary production. Crops, livestock, fisheries, and forestry account for 42% of gross domestic product (GDP) and provides 75% of the employment in the country. Tourism is growing and now represents 25% of the GDP. According to the Samoan Central Bank, the tourism sector is a key driver of country's economic development as it provides considerable employment and generates foreign exchange. The upgraded and climate change-proofed cross island road is also a major contribution to the island's disaster preparedness as it provides an alternate route for evacuation and post disaster relief and rehabilitation work between the northern and southern coasts. The upgrading of the project road will result in a more reliable and safer road network. The project will be aligned with the following impacts as envisioned in the government's Transport Sector Plan 2014 2019: (i) Goal 1 strengthen transport sector governance framework; and (ii) Goal 2 improve, sustain, and climate-proof road transport network. |
||||
| Project Rationale and Linkage to Country/Regional Strategy | Although passable throughout the year, significant sections of the project road have fallen into disrepair and become a safety concern for commuters as well as pedestrians walking along the roadside. This is especially an issue along the first 3 km of the road which is situated in a semi-urban area. In 2012, tropical cyclone Evan hit Samoa and caused significant damage to its road infrastructure. Some of the critically damaged road sections (5 locations total of 3,720 km) were since widened and resurfaced by the Government. The existing narrow road lanes without adequate pedestrian facilities in semi-urban areas, deficient drainage throughout the entire length, as well as unsafe horizontal and vertical alignment in hilly road sections will become a significant hazard as traffic levels increase, particularly in wet conditions. The World Bank and the Government of Australia have provided support to Samoa to restore road infrastructure after the cyclone in 2012 under the Enhanced Road Access Project (ERAP). Under the ERAP, initial economic viability, technical designs, preliminary safeguards documents, costs and draft bidding documents were prepared for the Cross Island Road and other key road links. Initial economic evaluations suggest high rates of economic return. Initial assessments of social, economic, and land acquisitions and resettlement impacts have also been commissioned under the ERAP. However, further detailed assessments will be required primarily to resolve road reserve issues relating to deficiencies between the Ministry of Natural Resources and Environment's cadastral data and survey done under the ERAP, and ensuring road safety and climate resilience features are incorporated into the project design. |
||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Nation-wide |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | Update as of 30 April 2020: 1. Consulting firm completed its contract on 30 June 2019 and has undertaken the following: a. Finalized of feasibility study on the ensuing project. b. Conducted due diligence to confirm and update the technical and economic feasibility of proposed solutions prepared under ERAP and prepared the necessary planning documents. c. Prepared and finalized engineering design components, procurement, safeguards, and implementation plans. d. Prepared the institutional capacity strengthening plan.
2. Engaged a Social Safeguards Specialist from April 2019 to May 2020 to review the resettlement plan, stakeholder communication, consultation plan and other relevant project documents to understand the safeguards planning undertaken to meet the ADB Safeguard Policy Statement (SPS) and relevant existing laws and policies in Samoa. |
| Business Opportunities | |
|---|---|
| Consulting Services | All activities completed |
| Procurement | All activities completed |
| Responsible ADB Officer | Ishenaliev, Rustam I. |
| Responsible ADB Department | Pacific Department |
| Responsible ADB Division | PATC |
| Executing Agencies |
Ministry of Finance Ministry of Finance Government of Samoa Private Bag, Apia, Samoa |
| Timetable | |
|---|---|
| Concept Clearance | - |
| Fact Finding | - |
| MRM | - |
| Approval | 03 May 2018 |
| Last Review Mission | - |
| Last PDS Update | 04 May 2020 |
TA 9519-SAM
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 03 May 2018 | 16 May 2018 | 16 May 2018 | 30 Jun 2019 | 30 Dec 2020 | 01 Mar 2021 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 17 Jun 2022 | 783,991.85 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Preparing the Central Cross Island Road Upgrading Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Apr 2018 |
| Preparing the Central Cross Island Road Upgrading Project: Technical Assistance Report | Technical Assistance Reports | Apr 2018 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
| Tender Title | Type | Status | Posting Date | Deadline |
|---|---|---|---|---|
| Central Cross Island Road Upgrading Project - Social Safeguards Specialist | Individual - Consulting | Closed |
Contracts Awarded
| Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
|---|---|---|---|---|---|---|
| Project Preparatory | Technical Assistance 9519 | 12 Jul 2018 | SMEC International Pty. Ltd., AUS(AUSTRALIA) | Level 10, 71 Queens Road Melbourne, VIC alia | Ministry of Finance | 698,955.00 | — |
Procurement Plan
None currently available.