Project Name | Uttarakhand Transmission Strengthening & Distribution Project | ||||
Project Number | 51308-008 | ||||
Country | India |
||||
Project Status | Proposed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth Regional integration |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||
Sector / Subsector | Energy / Electricity transmission and distribution |
||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | Impact the Project is Aligned with 24x7 power provided to all households, industry, commercial businesses, public needs, and any other electricity consuming entity (24x7 Power for All Uttarakhand)a |
||||
Outcome | Efficiency and reliability of power supply to consumers in the state of Uttarakhand improved | ||||
Outputs | Khandukhal - Rampura transmission system constructed Disaster- and climate-resilient distribution system in the arterial area of Dehradun and selected rural areas near community-based energy projects improved Community- centered energy projects harnessing indigenously available resources developed |
||||
Geographical Location | Nation-wide, India |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | All procurement of goods, works, nonconsulting, and consulting services will be undertaken in accordance with ADB Procurement Policy (2017, as amended from time to time) and ADB''s Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Procurement | All procurement of goods, works, nonconsulting, and consulting services will be undertaken in accordance with ADB Procurement Policy (2017, as amended from time to time) and ADB''s Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Responsible ADB Officer | Jaimes Kolantharaj |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Energy Division, SARD |
Executing Agencies |
Government of Uttarakhand Secretariat, 4-B, Subhash Road Dehradun 248001, India Power Transmission Corporation of Uttaranchal Ltd Kanwali Road Dehradun Uttaranchal 248001, India Uttarakhand Power Corporation Limited VCV Gabar Singh Urja Bhawan, Dehradun, Uttarakhand |
Timetable | |
---|---|
Concept Clearance | 16 May 2019 |
Fact Finding | 11 Nov 2019 to 22 Nov 2019 |
MRM | 08 Jan 2020 |
Approval | - |
Last Review Mission | - |
Last PDS Update | 17 May 2019 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Uttarakhand Transmission Strengthening and Distribution Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | May 2019 |
Uttarakhand Transmission Strengthening and Distribution Project: Concept Paper | Concept Papers | May 2019 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Loan No. 51308-IND: Uttarakhand Transmission Strengthening & Distribution Improvement Project [P-1/ADB/PTCUL/ 2018 /400 KV D/C Transmission Line] | Invitation for Bids | Closed | 08 Mar 2019 | 07 May 2019 |
IND: Uttarakhand Transmission Strengthening and Distribution Improvement Project | Advance Notice | Active | 13 Dec 2018 |
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.