China, People's Republic of : Guizhou Gui’an New District New Urbanization Smart Transport System Development Project
The proposed project will support Gui'an New District (Gui'an) in developing an Intelligent Transport System (ITS) and sustainable transport infrastructure. This will make public transport more enticing for all, averting congestion as Gui'an grows and improving quality of life for all.
Project Details
-
Project Officer
Chu, Chenglong
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Sector
- Transport
Project Name | Guizhou Gui’an New District New Urbanization Smart Transport System Development Project | ||||
Project Number | 51366-001 | ||||
Country / Economy | China, People's Republic of |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP4: Making cities more livable OP6: Strengthening governance and institutional capacity |
||||
Sector / Subsector | Transport / Urban public transport - Urban roads and traffic management |
||||
Gender | Effective gender mainstreaming | ||||
Description | The proposed project will support Gui'an New District (Gui'an) in developing an Intelligent Transport System (ITS) and sustainable transport infrastructure. This will make public transport more enticing for all, averting congestion as Gui'an grows and improving quality of life for all. | ||||
Project Rationale and Linkage to Country/Regional Strategy | The proposed project aims to assist Gui'an New District in developing innovative solutions to curb traffic congestion and other related negative impacts by providing advanced technological intervention. | ||||
Impact | Economic activity and livability improved |
Project Outcome | |
---|---|
Description of Outcome | Efficiency and sustainability of transport system in Gui'an New District improved |
Progress Toward Outcome | To be evaluated at project completion. |
Implementation Progress | |
Description of Project Outputs | Intelligent transport system designed and installed Sustainable transport infrastructure built Smart transport capacity strengthened |
Status of Implementation Progress (Outputs, Activities, and Issues) | Not yet started Not yet started The package for dynamic traffic information real-time perception system is being procured. procurement for 3 bus stations in progress procurement of 150 electric buses was completed in Nov 2022 15 electric charging stations in progress about 5. 05 km new urban roads financed by domestic funds were constructed. |
Geographical Location | Guizhou |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | Environmental assessment was prepared in compliance with ADB's Safeguard Policy Statement (2009) and related due diligence. |
Involuntary Resettlement | Resettlement planning assessment was prepared in compliance with ADB's Safeguard Policy Statement (2009) and related due diligence. |
Indigenous Peoples | Ethnic minorities are well integrated socially and economically into the urban fabric, and do not present any specific vulnerabilities. The social analysis has confirmed that they will not suffer any adverse impacts as a result of the project. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Project preparation relied on extensive consultations with current residents, including women, former farmers and the elderly using human-centered design methods. These consultations resulted in proposals for gender- and disability-sensitive bus and station design which will be developed further in detailed design. |
During Project Implementation | The project will be jointly monitored by (i) the project officer assigned to the project within East Asia Sustainable Infrastructure division of ADB, and (ii) the officer in ADB's PRC Resident Mission. |
Responsible ADB Officer | Chu, Chenglong |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | PRC Resident Mission (PRCM) |
Executing Agencies |
Government of Gui'an New District |
Timetable | |
---|---|
Concept Clearance | 30 Apr 2018 |
Fact Finding | 22 Jan 2019 to 25 Jan 2019 |
MRM | 13 May 2019 |
Approval | 16 Aug 2019 |
Last Review Mission | - |
Last PDS Update | 15 Sep 2023 |
Loan 3807-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
16 Aug 2019 | 04 Dec 2019 | 24 Feb 2020 | 30 Jun 2026 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 495.81 | Cumulative Contract Awards | |||
ADB | 199.46 | 24 Jul 2023 | 32.65 | 0.00 | 17% |
Counterpart | 296.35 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 24 Jul 2023 | 29.91 | 0.00 | 16% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB-Supported Sustainable Transport Project to Reduce Pollution, Improve Mobility in Guizhou, PRC
ADB has approved a $199.46 million loan to support the development of an innovative intelligent transport system to reduce pollution, cut traffic congestion, and improve transport safety in Gui’an in the PRC.Human-Centered Design Underpins New Intelligent Transport System in PRC City
A human-centered design approach is helping deliver an intelligent transport system in the city of Gui’an, People’s Republic of China (PRC).
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
3807-PRC: Guizhou Gui'an New District New Urbanization Smart Transport System Development Project | Tenders, Invitation for Bids | Tender, Active | ||
3807-PRC: Guizhou Gui'an New District New Urbanization Smart Transport System Development Project | Tenders, Invitation for Bids | Tender, Active | ||
3807-PRC: Guizhou Gui’an New District New Urbanization Smart Transport System Development Project | Invitation for Bids | Closed, Active | ||
Loan-3807 Guizhou Gui’an New District New Urbanization Smart Transport System Development Project (EQ 801) | Invitation for Bids | Closed | ||
Attitudes and Behaviors on Transportation Modes | Firm - Consulting | Closed | ||
Environmental Monitoring | Firm - Consulting | Closed | ||
RP and SDGAP Monitoring | Firm - Consulting | Closed | ||
Project Management Consultant | Firm - Consulting | Closed |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Civil works package CW101-1: Fukang north road-Xuanshui road station, Yunman Lake Station | Loan 3807 | 23 May 2023 | Joint Venture of Anhui Tengtai Construction Engineering Co., Ltd. and Anhui Lutan Construction Group Co., Ltd. | No. 16, West Yihu Road, Lujiang Economic Development Zone, Hefei, Anhui Province | Government of Gui'an New District | 2,326,662.98 | 2,299,255.30 |
Procurement of CW package CW102: PTIC 3 for 1 hub station: Biguiyuan/Jinma Avenue station | Loan 3807 | 04 May 2023 | Guilin Jian'an Construction Group Co., Ltd. | Guilin, Guangxi Province | Government of Gui'an New District | 3,845,304.43 | 3,757,588.97 |
Procurement of goods package EQ801:Electric Bus Package 1 (150 Buses) | Loan 3807 | 02 Dec 2022 | Joint Venture of BYD Automobile Industry Co., Ltd., Geely Sichuan Commercial Vehicle Co., Ltd. and Chery & Wanda Guizhou Bus Co., Ltd. | No. 3001, 3007, Hengping Road, New Area of Pingshan, Shenzhen | Government of Gui'an New District | 23,553,816.48 | 23,553,816.48 |
Signed contract for C202-Attitudes and Behavior on Transportation Modes | Loan 3807 | 28 Dec 2021 | Beijing Century Transport Consulting Co., Ltd. | 715, floor 7, building 2, No. 19, North Third Ring East Road, Chaoyang District, Beijing PRC | Government of Gui'an New District | 147,361.81 | 147,285.51 |
Signed contract for C103-Environmental Monitoring consulting services package | Loan 3807 | 28 Dec 2021 | Wuhan Yunhaichen Consulting Co., Ltd | A-913 Building 1, Guanggu International Chamber of Commerce Building, 2-2 Guangdongyuan Road, East Lake New Technology Development Zone, Wuhan PRC | Government of Gui'an New District | 196,262.42 | 196,160.80 |
Signed contract for C102 Consulting services package - Resettlement and Social Monitoring | Loan 3807 | 28 Dec 2021 | Hohai University | No. 1 Xikang Road, Nanjing City, Jiangsu Province, PRC | Government of Gui'an New District | 290,428.42 | 290,278.04 |
SIGNED CONTRACT FOR CONSULTING SERVICES PACKAGE C101, PROJECT MANAGEMENT CONSULTANT | Loan 3807 | 05 Apr 2021 | JOINT VENTURE OF URTRUST THINKTANK CONSULTING | ROOM 213, FLOOR 2, BUILDING 5, HUAYUAN ROAD 5, HAIDIAN DISTRICT BEIJING CHINA, PEOPLE'S REP. OF | Government of Gui'an New District | 3,289,492.68 | 3,289,492.68 |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Guizhou Gui’an New District New Urbanization Smart Transport System Development Project: Procurement Plan | Procurement Plans | Jun 2023 |