The proposed Project will improve the quality and reliability of electricity supply, reduce the aggregate technical and commercial (ATC) losses in electricity distribution and restore the financial sustainability of the rural electricity supply. The Project will convert the low voltage distribution lines to aerial bundle conductors (ABC), separate the 11 kilovolt (kV) feeders supplying agriculture and rural households to facilitate the rationing of electricity supply to agriculture consumers, increase the supply duration to rural households and enhance the community engagement for improving electricity supply cost recovery and gender inclusivity in electricity distribution related activities in rural areas.
Project Name | Uttar Pradesh Power Distribution Network Rehabilitation Project – Tranche 1 | ||||||||||
Project Number | 51395-003 | ||||||||||
Country | India |
||||||||||
Project Status | Approved | ||||||||||
Project Type / Modality of Assistance | Loan Technical Assistance |
||||||||||
Source of Funding / Amount |
|
||||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||||||||
Sector / Subsector | Energy / Electricity transmission and distribution |
||||||||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||||||||
Description | The proposed Project will improve the quality and reliability of electricity supply, reduce the aggregate technical and commercial (ATC) losses in electricity distribution and restore the financial sustainability of the rural electricity supply. The Project will convert the low voltage distribution lines to aerial bundle conductors (ABC), separate the 11 kilovolt (kV) feeders supplying agriculture and rural households to facilitate the rationing of electricity supply to agriculture consumers, increase the supply duration to rural households and enhance the community engagement for improving electricity supply cost recovery and gender inclusivity in electricity distribution related activities in rural areas. | ||||||||||
Project Rationale and Linkage to Country/Regional Strategy | The electricity supply to rural areas in Uttar Pradesh and in most parts of rural India is characterized by (i) frequent power failures resulting in an average supply duration of 16-18 hours per day (ii) inadequate cost recovery and poor bill collection efficiency from rural residential and agriculture consumers (iii) overloaded and dilapidated electricity distribution network. The rural electricity supply is saddled with following problems; (i) unauthorized connections of agricultural pumps and households/commercial connections, (ii) over-use of subsidized electricity for agricultural water pumping causing financial losses, (iii) aged and poorly maintained distribution lines and transformers, which are frequently operated above rated capacity, causing excessive technical losses to the DISCOMs and a poor quality of service to the customers and (iv) presence of large number of unmetered residential and agriculture connections, irregular meter reading and infrequent bill collections from rural consumers. | ||||||||||
Impact | Quality of power supply and financial cost recovery in power supply in Uttar Pradesh |
Project Outcome | |
---|---|
Description of Outcome | Efficiency, reliability, and sustainability of power supply in selected areas in Uttar Pradesh improved |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Rural electricity distribution network improved Systems for separating electricity distribution for agriculture consumers and for residential consumers established . Systems for bill collection in rural areas and financial management improved and gender-sensitive workplaces created |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Uttar Pradesh |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | All procurement of goods, works, nonconsulting, and consulting services will be undertaken in accordance with ADB Procurement Policy (2017, as amended from time to time) and ADB 's Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Procurement | All procurement of goods, works, nonconsulting, and consulting services will be undertaken in accordance with ADB Procurement Policy (2017, as amended from time to time) and ADB 's Procurement Regulations for ADB Borrowers (2017, as amended from time to time). |
Responsible ADB Officer | Perera, Pradeep |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Energy Division, SARD |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | 05 Aug 2020 |
Approval | 04 Dec 2020 |
Last Review Mission | - |
Last PDS Update | 04 Dec 2020 |
Loan 4025-IND
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 624.00 | Cumulative Contract Awards | |||
ADB | 300.00 | - | 0.00 | 0.00 | % |
Counterpart | 324.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | - | 0.00 | 0.00 | % |
TA 6636-IND
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
04 Dec 2020 | - | - | 31 Dec 2022 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
500,000.00 | 1,500,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 2,000,000.00 | 04 Dec 2020 | 0.00 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Loan Agreement (Ordinary Operations) for Loan 4025-IND: Uttar Pradesh Power Distribution Network Rehabilitation Project – Tranche 1 | Loan Agreement (Ordinary Resources) | Dec 2020 |
Project Agreement for Loan 4025-IND: Uttar Pradesh Power Distribution Network Rehabilitation Project - Tranche 1 | Project/Program Agreements | Dec 2020 |
Enhancing Community Participation, Gender Mainstreaming, and Institutional Capacity Building of Uttar Pradesh Power Corporation Limited: Technical Assistance Report | Technical Assistance Reports | Nov 2020 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
ADB, India Sign $300 Million Loan to Upgrade Power Distribution Network in Uttar Pradesh
The Asian Development Bank and the Government of India signed a $300 million loan to upgrade rural power distribution networks to provide reliable electricity supply to consumers in the state of Uttar Pradesh.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
National Project Management Expert | Individual - Consulting | Closed | 12 Feb 2021 | 18 Feb 2021 |
National Social Development Specialist | Individual - Consulting | Closed | 12 Feb 2021 | 18 Feb 2021 |
National Health and Safety Expert | Individual - Consulting | Closed | 12 Feb 2021 | 18 Feb 2021 |
National Environment Assessment Expert | Individual - Consulting | Closed | 03 Feb 2021 | 12 Feb 2021 |
International Environment Expert | Individual - Consulting | Closed | 03 Feb 2021 | 12 Feb 2021 |
Implementation of Outputs 1 & 2 of the TA | Firm - Consulting | Closed | 13 Jan 2021 | 10 Feb 2021 |
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan