China, People's Republic of : Preparing the Silk Road Ecological Protection and Rehabilitation
Project Details
-
Project Officer
Yee, Au Shion
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Sector
- Agriculture, natural resources and rural development
Related Projects
| Project Name | Preparing the Silk Road Ecological Protection and Rehabilitation | ||||
| Project Number | 51425-001 | ||||
| Country / Economy | China, People's Republic of |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||
| Sector / Subsector | Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Agro-industry, marketing, and trade - Forestry - Land-based natural resources management |
||||
| Gender | Effective gender mainstreaming | ||||
| Description | |||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Nation-wide, Gansu, Qinghai, Shaanxi |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | The technical assistance (TA) will require services of 38.0 person-months (pm) of international consultants and 46.5 pm of national consultants. Individual consultants will be recruited to provide advanced inputs to support the project design and start-up. The remaining positions will be filled by engaging a consulting firm through quality- and cost-based selection method using a quality-cost ratio of 90:10 and biodata technical proposal. Lump-sum or output-based contracts will also be considered for consulting services. The technical assistance will engage consulting firms and individual consultants in accordance with the Asian Development Bank Procurement Policy (2017, as amended from time to time) and the associated project administration instructions and/or staff instructions. The table below provides details of the consultancy requirements. |
| Responsible ADB Officer | Yee, Au Shion |
| Responsible ADB Department | East Asia Department |
| Responsible ADB Division | Environment, Natural Resources & Agriculture Division, EARD |
| Executing Agencies |
National Forestry and Grassland Administration |
| Timetable | |
|---|---|
| Concept Clearance | - |
| Fact Finding | - |
| MRM | - |
| Approval | 11 Feb 2019 |
| Last Review Mission | - |
| Last PDS Update | 23 Sep 2022 |
TA 9713-PRC
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 11 Feb 2019 | 21 Mar 2019 | 21 Mar 2019 | 30 Nov 2020 | 31 Aug 2022 | 10 Oct 2022 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 07 Nov 2022 | 676,998.61 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Preparing the Silk Road Ecological Protection and Rehabilitation: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Feb 2019 |
| Preparing the Silk Road Ecological Protection and Rehabilitation: Technical Assistance Report | Technical Assistance Reports | Feb 2019 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
| Tender Title | Type | Status | Posting Date | Deadline |
|---|---|---|---|---|
| Consulting Firm | Firm - Consulting | Closed | ||
| Preparing the Silk Road Ecological Protection and Rehabilitation - International Ecology Management and Innovations Specialist | Individual - Consulting | Closed | ||
| Preparing the Silk Road Ecological Protection and Rehabilitation - International Institutional Development/Start-up Expert | Individual - Consulting | Closed |
Contracts Awarded
| Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
|---|---|---|---|---|---|---|
| Project Preparatory | Technical Assistance 9713 | 23 Aug 2019 | NAREE International Limited (HONG KONG, CHINA) in association with NAREE Consulting Limited, China (CHINA,PEOPLE'SREP.OF) | Unit N, 5/F, 4 Cho Yuen Street, Yau Tong Kowloon, Hong Kong, China | State Forestry and Grassland Administration | 574,800.00 | — |
Procurement Plan
None currently available.